Overview
Once, an equipment has been phased out of service it can be scrapped. This includes
removing it from the financial asset register, complying with regulations regarding the
environment, salvaging any re-usable parts, removing from site.
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 3
Equipment Phase - Out
The Equipment Phase – Out process is a cross module process in which the Plant
Maintenance module has a vital role to play. All maintenance relevant data pertaining to
equipment should be deleted / deactivated before Equipment is Phased-out.
Information of about equipments with various statuses will be available in the system
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 4
Equipment Outlived Report
SAP Menu
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 5
Input the plant and click on Execute
or press F8 key on the keyboard
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 6
Equipment Maintenance Expenses Report
SAP Menu SAP Menu---Logistics---Plant Maintenance---Maintenance Processing---
Order---Order List---Display
Click on Execute
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 7
Equipment Technology Details
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 8
Equipment Theft Case Report
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 9
Select the Line Item, Click on Settings
and then click on Show/Hide
Classification
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 10
Decision on Re-Parenting / Scrapping
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 11
Update Reason for Scrapping
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 12
Click on Class Overview
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 13
Update the Reason for Scrapping
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 14
Scrapping Process
Refer the User Manual for Scrapping Process
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 15
System will prompt pop-up window for List of Document Types available as below
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 16
Click on Continue or Press Enter key on the keyboard
System prompts for a pop-up window as below, Input the Log Field
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 17
Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 18
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 19
Right Click on the and Click on Check In
As….
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 20
Select the DMS_C1_ST and Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 21
Click on “Addnl Data” tab
To select the Current Equipment Status place the cursor in the field and press F4 Key
on the Keyboard or Click on
System will prompt for pop-up window showing list of Equipment statuses available as
below
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 22
Select the suitable status (Activate the Check Box) and click on continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 23
Click on “Object Links” Tab
Update the Equipment Number and press Enter key on the keyboard to get the
description of the Equipment
Click on Save
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 24
System prompts for a message as “Document ZEQ XXXXXXXXXXXXXXXXX XXX XX created
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 25
Change DIR
Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 26
Click on or Press F4 Key on the keyboard
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 27
Double click on the RR Request Review
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 28
Press Enter key on the keyboard
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 29
Click on “Reviewers/Approvers” Tab
Click on Save
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 30
SAP Menu SAP Menu----Office----Workplace
Click on
Double click on
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 31
Click on
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 32
Double click on the document
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 33
Review the document and Click on back (F3)
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 34
Click on Back (F3)
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 35
System will prompt for pop-up window as below
Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 36
The Express info received by the person who has sent for Review.
Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 37
Double click on the Content
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 38
Click on Back till you reach to the SAP Easy Access Menu
Note: Based the decision of the Reviewer the Document Status will be updated as
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 39
Now View the DIR using t code CV02N
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 40
Change DIR
Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 41
Click on “Reviewers/Approvers” Tab
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 42
Click on “Approvers” Tab
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 43
Change the Document status to RA: Request Approval
Click on Save
The Approver will receive the mail in his SAP mail box will take the decision
Note: Based on the Decision of Approver the Document status will be either updated to
AD: Approved
RJ: Rejected
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 44
Click on Status
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 45
Activate the SCAP: Scrapping Approved Check Box and Click on Back
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 46
System status will be updated as SCAP as shown above
Click on Save
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 47
ACE-9 Approved (Set Indicator in Equipment)
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 48
Click on Status
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 49
Activate the ACAP: ACE-9 Approved Check Box and Click on Back
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 50
The system will update the user status to ACAP
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 51
Equipment Dismantled (Set Indicator in Equipment)
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 52
Click on Status
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 53
Activate radio button of DISM: Dismantled
Click on Go Back
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 54
The User Status will be updated to DISM: Dismantled
Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 55
System will not allow you to save, until the equipment is dismantled from current
location (Current FL)
Before Dismantling
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 56
Deactivate & Delete Maintenance Plan
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 57
In the Maintenance Item for the
Equipment which is to be scrapped,
Click this icon to cancel the Task List
associated with Maintenance Plan
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 58
Now deactivate the Maintenance Plan
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 59
Set the Deletion Flag for Maintenance Plan
Click on Save
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 60
Delete Task List
SAP Menu SAP Menu---Logistics---Plant Maintenance---Preventive Maintenance---
Work Scheduling---Task Lists---For Equipment---Change
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 61
Click on Save
Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 62
Click on “Environment”
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 63
Input the period i.e. from to dates and click on Execute
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 64
From the above list select the order individually or collectively and set Technical
Completion (TECO)
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 65
Click on Complete (technically)
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 66
Order Status will be set to TECO
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 67
Click on “Environment” and click on Notifications
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 68
Click on Execute to get the Notifications list
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 69
From the above list select the notifications individually or collectively to complete the
notifications (Status NOCO)
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 70
Click on Complete
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 71
System will update the status as NOCO: Notification Completed
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 72
Input the equipment Number and Click on Continue
Click on
to get the list
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 73
Click on to go to the Measuring
point change mode
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 74
Click on Go Back or press F3 key on the keyboard till you reached to the
Equipment change screen
Click on save
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 75
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 76
Dismantle the Equipment
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 77
Click on “Structure” Tab
Click on Dismantle
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 78
After Dismantle the pop-up window appears as below
Click on Continue
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 79
The FL will disappear
Click on Save
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 80
System prompts for a message as “Equipment XXXXXXXXXXXXX changed”
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 81
Set Equipment Status to “SCRP” Scrapped
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 82
Lick on
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 83
Click on Go Back
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 84
System will prompt a Warning Message
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 85
To acknowledge the warning message press “Enter” key on the keyboard
Click on Save
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 86
Deletion Flag for Equipment (“DLFL” Deletion Flag)
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 87
Click on “Equipment” and follow the path as shown
Click on Set
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 88
Click on save
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 89
System prompts a message as “Equipment XXXXXXXXXXX changed
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 90
Decommissioning of Asset
Refer the FI process
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 91
To acknowledge the message press “Enter” key on the keyboard
Click on
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 92
Activate the suitable check box and Go back
BSNL_PM_UM_11_Equipment_Phase_Out_V2.0.doc Page 93
Click on Save
Sale of Scrapped asset, Profit & Loss on the sale of the Scrapped asset etc
Refer the Relevant MM and FI manuals to carry out the above step