Professional Documents
Culture Documents
Subject Lions Gate Secondary Wastewater Treatment Plant – Project Definition Report
Technical Memorandum 1.6.1c
Management of Environmental Contamination
1. Introduction
This discussion paper (DP) provides commentary on considerations related to managing
environmental contamination on the site of the future Lions Gate Secondary Wastewater Treatment
Plant (LGSWWTP), based on site development concepts presented in Build Scenarios A, B and C
(refer to DP 1.13.4 Conceptual Development of Three Build Scenarios).
A summary of the surface areas and volumes of impacted soil and groundwater that are remaining on
site and require risk mitigation is shown in Table 14 (Revised) of the Confirmation of Remediation
Report and is summarized below in Table 1 (Piteau 2010). The Areas of Environmental Concern
(AEC) locations are shown in Figure 14 of the Confirmation of Remediation Report (Piteau 2010),
which is reprinted in Figure 1 at the end of this discussion paper.
Additional contamination not previously identified may be present on site and should be assessed by
a licensed professional, if encountered during construction activities.
st
Scenario A includes the potential for light industrial/commercial development along 1 St, which may
have implications for the amended risk-based CoC for the site and numeric remediation standards.
All three scenarios have park land to varying degrees, which would similarly inform requirements of
the amended CoC.
All three scenarios envisage major construction on the west and south sides of the site for structures,
such as digesters, tanks and buildings. Generally, the structures are founded near the groundwater
table, which is quite shallow at 1 to 1.5m below grade (or 1 to 1.5m above sea level (ASL)).
Contamination on the site is also quite shallow with impacted soils not extending beyond 4.0m below
grade.
The recommended handling of impacted soil will be influenced to a large extent by construction
methods selected by the contractor(s) and geotechnical requirements to support structures on the
site.
If construction methods require excavation of site soils, specific health and safety procedures will
need to be implemented to protect construction workers who will come into contact with impacted
soils, groundwater and vapours in the excavation. Impacted soils will need to be segregated during
excavation for disposal at an approved facility.
In some areas impacted soil is overlain by non impacted materials, therefore segregation and specific
handling of soils may be required during construction. In previous remediation activities on the site,
excavated rocks were washed on site and returned to the excavation to reduce disposal costs.
3
The total volume of impacted soils estimated by others on site is 13,487 m . Current tipping fees for
contaminated soil at a licensed facility is on the order of $100/tonne and with allowances for
excavation, hauling,management/monitoring during construction and contingencies the expected cost
for managing contaminated soil on the LGSWWTP site is $2.0 to $3.0M.
Based on the groundwater regime underlying the site a large-scale groundwater pump and treat
system is unlikely to be cost effective.
If piles are used to support structures, any impacts they contribute will receive a beneficial use
exemption. Creosote piles will contribute PAH contamination and steel piles will introduce zinc and
potentially other metals to site soils, both of which are currently present on site. Excavation and
replacement with clean fill prior to placement of piles is not likely to be necessary. Risk mitigation
strategies in the form of surface caps and impermeable liners may be used to reduce human and
ecological risks.
In situ remediation techniques such as bioremediation for the LEPH and PAH contamination or
solidification and stabilization of metals contamination are not likely to be cost effective consideration
for this site due to the limited extent of contamination, the planned use of the site and coverage with
concrete structures, and the low relative cost of alternative mitigation strategies, such as excavation
and disposal.
Previous investigations for soil vapour associated with LEPH and PAH contamination on site were
based on vapour migration to outdoor air (or direct measurement of concentrations in outdoor air).
Vapour attenuation factors which can be applied to in-situ vapour measures vary based on type and
materials of construction of structures on the property. Additional vapour mitigation in the form of
vapour extraction systems (passive or active) may be required to be included in the facility design
depending on mitigation measures included in the amended CoC. Capital costs for a vapour
extraction system, if required, can be determined once vapour concentrations and building design
parameters are known.
Groundwater Vapour
5. References
Ministry of Environment. 2010. Technical Guidance 4 on Contaminated Sites – Vapour Use
Investigation and Remediation, Sept.
http://www.env.gov.bc.ca/epd/remediation/guidance/technical/pdf/tg04.pdf.
Piteau Associates. 2010. Contamination of Remediation – Former North Vancouver Freight Shed and
st
Passenger Station – 1311, 1321 and 1350 West 1 Street, North Vancouver, BC. February.