RDS‐8 Construction Schedule
ADCO CONTRACT NO. 15606.02/EC 10870
RDS-8 Modification 206 206 04-Mar-15 29-Oct-15 03-Jun-15 08-Oct-15 07-Jun-15 03-Nov-15 36
Civil & Structural 70 70 04-Mar-15 24-May-15 03-Jun-15 16-Aug-15 07-Jun-15 16-Aug-15 172
CO-RD-CI-4280 Pipe Support Foundation Casting 60 60 04-Mar-15 12-May-15 03-Jun-15 01-Aug-15 07-Jun-15 01-Aug-15 113 0%
CO-RD-CI-5630 Pipe Support Prefab. 20 20 20-Apr-15 12-May-15 15-Jul-15 01-Aug-15 18-Jul-15 01-Aug-15 113 0%
CO-RD-CI-7080 Pipe Support Installation 10 10 13-May-15 24-May-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 113 0%
CO-RD-CI-4635 Inlet Manifold Foundation Casting 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130 0%
CO-RD-CI-4640 MPFM Foundation Casting 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130 0%
CO-RD-CI-4645 Passive Cooling Shelter Foundation Casting 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130 0%
CO-RD-CI-8000 RCC Concrete Trench / Duct Bank Installation 30 30 01-Apr-15 05-May-15 130 0%
Modification of Existing
Existi Platform 45 45 18-Mar-15 09-May-15 18-Jun-15 02-Aug-15 21-Jun-15 02-Aug-15 185
CO-RD-CI-4850 Platform Foundation Casting 35 35 18-Mar-15 27-Apr-15 18-Jun-15 26-Jul-15 21-Jun-15 26-Jul-15 130 0%
CO-RD-CI-5435 Platfrom Prefab. 12 12 14-Apr-15 27-Apr-15 09-Jul-15 26-Jul-15 12-Jul-15 26-Jul-15 185 0%
CO-RD-CI-6915 Platform Erection 10 10 28-Apr-15 09-May-15 27-Jul-15 02-Aug-15 26-Jul-15 02-Aug-15 185 0%
CO-RD-CI-5075 Access Platform Foundation Casting 35 35 25-Mar-15 04-May-15 25-Jun-15 02-Aug-15 28-Jun-15 02-Aug-15 130 0%
CO-RD-CI-5660 Access Platform Prefab. 12 12 21-Apr-15 04-May-15 16-Jul-15 02-Aug-15 19-Jul-15 02-Aug-15 179 0%
CO-RD-CI-7150 Access Platform Erection 10 10 05-May-15 16-May-15 03-Aug-15 09-Aug-15 02-Aug-15 09-Aug-15 179 0%
CO-RD-CI-5280 Cross Over Foundation Casting 35 35 01-Apr-15 11-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 130 0%
Remaining Level of Effort Actual Work Milestone Page 1 of 3 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CO-RD-CI-6920 Cross Over Prefab. 12 12 28-Apr-15 11-May-15 27-Jul-15 09-Aug-15 26-Jul-15 09-Aug-15 173 0%
CO-RD-CI-7315 Cross Over Erection 10 10 12-May-15 23-May-15 10-Aug-15 16-Aug-15 09-Aug-15 16-Aug-15 173 0%
CO-RD-CI-5285 Electrical JB Foundations Casting 30 30 01-Apr-15 05-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 130 0%
Instrument JB Foundations
Found 30 30 01-Apr-15 05-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 150
CO-RD-CI-5290 Instrument JB Foundation Casting 30 30 01-Apr-15 05-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 150 0%
CO-RD-PI-5400 Inlet Manifold Prefab. 18 18 15-Aug-15 05-Sep-15 08-Jul-15 01-Aug-15 11-Jul-15 01-Aug-15 38 0%
CO-RD-PI-7085 Inlet Manifold Erection 6 6 05-Sep-15 12-Sep-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 38 0%
CO-RD-PI-7285 Mechanical Valves Installation 10 10 19-Sep-15 30-Sep-15 09-Aug-15 15-Aug-15 08-Aug-15 15-Aug-15 22 0%
CO-RD-PI-7590 Corrosion Probe / Coupon Installation 7 7 22-Sep-15 30-Sep-15 20-Aug-15 22-Aug-15 19-Aug-15 22-Aug-15 22 0%
CO-RD-EL-7090 Electrical Cable Laying 12 12 20-Jul-15 03-Aug-15 02-Aug-15 15-Aug-15 01-Aug-15 15-Aug-15 65 0%
CO-RD-EL-7095 Earthing Cable Laying 12 12 20-Jul-15 03-Aug-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 79 0%
CO-RD-EL-7100 Earth Bar Installation 7 7 20-Jul-15 28-Jul-15 02-Aug-15 03-Aug-15 01-Aug-15 03-Aug-15 84 0%
Electrical JB Installation
Installat 7 7 03-Aug-15 11-Aug-15 16-Aug-15 17-Aug-15 15-Aug-15 17-Aug-15 65
Remaining Level of Effort Actual Work Milestone Page 2 of 3 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CO-RD-EL-7480 Distribution Board Installation 7 7 03-Aug-15 11-Aug-15 16-Aug-15 17-Aug-15 15-Aug-15 17-Aug-15 65 0%
CO-RD-EL-7560 Lights & Fixture Installation 7 7 11-Aug-15 19-Aug-15 18-Aug-15 22-Aug-15 17-Aug-15 22-Aug-15 65 0%
CO-RD-EL-7625 Glading & Termination 12 12 19-Aug-15 02-Sep-15 23-Aug-15 05-Sep-15 22-Aug-15 05-Sep-15 65 0%
CO-RD-IC-7105 Instrument Cable Laying 6 6 26-Aug-15 02-Sep-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 48 0%
Instrument JB Installation
Install 7 7 02-Sep-15 10-Sep-15 10-Aug-15 11-Aug-15 09-Aug-15 11-Aug-15 48
CO-RD-IC-7715 Field Instrument Installation 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22 0%
Fire & Gas Equipment 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22
CO-RD-IC-7720 Fire & Gas Equipment Installation 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22 0%
CO-RD-IC-7735 CO2 Analyzer Installation 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22 0%
CO-RD-IC-7740 Intrument Trays, Tube & Fittings 12 12 10-Oct-15 24-Oct-15 30-Aug-15 12-Sep-15 15-Oct-15 28-Oct-15 22 0%
CO-RD-IC-7790 Glanding & Termination 12 12 15-Oct-15 29-Oct-15 05-Sep-15 17-Sep-15 21-Oct-15 03-Nov-15 22 0%
CO-RD-TE-7595 Telecom Works including works at BCDS 18 18 09-Sep-15 30-Sep-15 16-Sep-15 08-Oct-15 19-Aug-15 09-Sep-15 36 0%
Remaining Level of Effort Actual Work Milestone Page 3 of 3 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
ATTACHMENT‐2
Tie‐in Schedule
ADCO CONTRACT NO. 15606.02/EC 10870
TIE‐IN SCHEDULE
Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
EPC FOR BAB FA
FAR NORTH CO2 INJECTION PILOT PROJEC 151 151 09-Aug-15 31-Jan-16 02-Aug-15 06-Sep-15 01-Aug-15 06-Sep-15 34
CO-RU-PI-7700 6" HC Piping with Lift gas (Hydrocasrbon) (TP-23) 5 5 14-Oct-15 20-Oct-15 13-Aug-15 13-Aug-15 19-Aug-15 19-Aug-15 44 0%
CO-RU-PI-7705 4" HC Piping with NEB Piping for Start up Pressurization (TP-101) 5 5 14-Oct-15 20-Oct-15 13-Aug-15 13-Aug-15 19-Aug-15 19-Aug-15 44 0%
CO-RU-PI-7685 8" CO2 Pipeline with NEB CO2 (TP-12) 5 5 17-Oct-15 22-Oct-15 12-Aug-15 12-Aug-15 18-Aug-15 18-Aug-15 42 0%
CO-NF-PI-9000 6" Piping with Wing Valve Xmas Tree (TP-01A/B) 5 5 18-Oct-15 24-Oct-15 41 0%
CO-NF-PI-9010 4" Vent piping with Injection Well Casing (TP-03A/B & 04A/B) 5 5 18-Oct-15 24-Oct-15 41 0%
CO-NF-PI-9030 2" Vent Connection form Producer Well to Annulus Bleed (TP-06A) 5 5 04-Nov-15 10-Nov-15 26 0%
CO-NF-EL-9050 Electrical Tie-ins (33 KV AC, 3 Phase to 33 KV OHL 7A) - Shut 5 5 21-Nov-15 26-Nov-15 12 0%
Down Required
East Flank 15 15 13-Jan-16 31-Jan-16 34
CO-NF-PI-9050 6" Piping with Wing Valve Xmas Tree (TP-01C/D) 5 5 13-Jan-16 19-Jan-16 44 0%
CO-NF-PI-9060 4" Vent piping with Injection Well Casing (TP-03C/D & 04C/D) 5 5 13-Jan-16 19-Jan-16 44 0%
CO-NF-EL-9060 Electrical Tie-ins (33 KV AC, 3 Phase to 33 KV OHL 7B) - Shut 5 5 20-Jan-16 26-Jan-16 38 0%
Down Required
CO-NF-PI-9070 6" Flowline to Producer Well (TP-05B) 5 5 25-Jan-16 31-Jan-16 34 0%
CO-NF-PI-9080 2" Vent Connection form Producer Well to Annulus Bleed (TP-06B) 5 5 25-Jan-16 31-Jan-16 34 0%
CO-EF-PI-9100 Water Injector Line Tie-in at Cluster 30 (TP-16A/B) - Shut Down 5 5 09-Aug-15 13-Aug-15 102 0%
Required
CO-NF-PI-9110 Water Injector Line Tie-in at Cluster 31 (TP-15A/B) - Shut Down 5 5 11-Aug-15 16-Aug-15 178 0%
Required
Remaining Level of Effort Actual Work Milestone Page 1 of 2 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RDS-8 44 44 02-Sep-15 22-Oct-15 02-Aug-15 06-Sep-15 01-Aug-15 06-Sep-15 42
CO-RD-PI-7760 2" Vent Header Header from Manifold to Blowdown Header 5 5 15-Oct-15 21-Oct-15 01-Sep-15 01-Sep-15 31-Aug-15 01-Sep-15 42 0%
(TP-17) - Shut Down Required
CO-RD-PI-7765 2" Drain Piping to from MPFM to Blowdown Header (TP-18 A/B) - 5 5 15-Oct-15 21-Oct-15 01-Sep-15 02-Sep-15 31-Aug-15 02-Sep-15 42 0%
Shut Down Required
CO-RD-PI-7770 2" Manual Vent from MPFM to Blowdown Header (TP-19A/B) - 5 5 17-Oct-15 22-Oct-15 02-Sep-15 06-Sep-15 01-Sep-15 06-Sep-15 42 0%
Shut Down Required
CO-RD-PI-7775 10" Production Header to 24"Transfer Line (TP-20A/B) - Shut 5 5 17-Oct-15 22-Oct-15 02-Sep-15 06-Sep-15 01-Sep-15 06-Sep-15 42 0%
Down Required
CO-RD-PI-7780 Tie-in with Exisiting Corrosion Inhibitor Package(TP-21) - Shut 5 5 17-Oct-15 22-Oct-15 02-Sep-15 02-Sep-15 01-Sep-15 02-Sep-15 42 0%
Down Required
CO-RD-PI-7800 2" Nitrogen piping to Exisitng Nitrogen Header (TP-102) - Shut 5 5 17-Oct-15 22-Oct-15 42 0%
Down Required
Remaining Level of Effort Actual Work Milestone Page 2 of 2 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
ATTACHMENT‐3
OHL Tie‐in duration from Sub Contractor M/s Ranya