ATTACHMENT‐1

RDS‐8 Construction Schedule
ADCO CONTRACT NO. 15606.02/EC 10870

EPC FOR BAB FAR NORTH CO2 INJECTION PILOT PROJECT

RDS‐8 CONSTRUCTION SCHEDULE


Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
EPC FOR BAB FA
FAR NORTH CO2 INJECTION PILOT PROJEC 206 206 04-Mar-15 29-Oct-15 03-Jun-15 08-Oct-15 07-Jun-15 03-Nov-15 36

Construction & Pre-Commissioning


Pr 206 206 04-Mar-15 29-Oct-15 03-Jun-15 08-Oct-15 07-Jun-15 03-Nov-15 36

Construction 206 206 04-Mar-15 29-Oct-15 03-Jun-15 08-Oct-15 07-Jun-15 03-Nov-15 36

RDS-8 Modification 206 206 04-Mar-15 29-Oct-15 03-Jun-15 08-Oct-15 07-Jun-15 03-Nov-15 36

Civil & Structural 70 70 04-Mar-15 24-May-15 03-Jun-15 16-Aug-15 07-Jun-15 16-Aug-15 172

Pipe Supports / Sleepers


Sleep 70 70 04-Mar-15 24-May-15 03-Jun-15 08-Aug-15 07-Jun-15 08-Aug-15 113

CO-RD-CI-4280 Pipe Support Foundation Casting 60 60 04-Mar-15 12-May-15 03-Jun-15 01-Aug-15 07-Jun-15 01-Aug-15 113 0%

CO-RD-CI-5630 Pipe Support Prefab. 20 20 20-Apr-15 12-May-15 15-Jul-15 01-Aug-15 18-Jul-15 01-Aug-15 113 0%

CO-RD-CI-7080 Pipe Support Installation 10 10 13-May-15 24-May-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 113 0%

Inlet Manifold Foundation


Found 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130

CO-RD-CI-4635 Inlet Manifold Foundation Casting 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130 0%

MPFM Foundation 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130

CO-RD-CI-4640 MPFM Foundation Casting 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130 0%

Passive Cooling Shelter


Shel Foundation 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130

CO-RD-CI-4645 Passive Cooling Shelter Foundation Casting 35 35 11-Mar-15 20-Apr-15 11-Jun-15 15-Jul-15 14-Jun-15 19-Jul-15 130 0%

RCC Cable Trench / D


Duct Bank 30 30 01-Apr-15 05-May-15 130

CO-RD-CI-8000 RCC Concrete Trench / Duct Bank Installation 30 30 01-Apr-15 05-May-15 130 0%

Modification of Existing
Existi Platform 45 45 18-Mar-15 09-May-15 18-Jun-15 02-Aug-15 21-Jun-15 02-Aug-15 185

CO-RD-CI-4850 Platform Foundation Casting 35 35 18-Mar-15 27-Apr-15 18-Jun-15 26-Jul-15 21-Jun-15 26-Jul-15 130 0%

CO-RD-CI-5435 Platfrom Prefab. 12 12 14-Apr-15 27-Apr-15 09-Jul-15 26-Jul-15 12-Jul-15 26-Jul-15 185 0%

CO-RD-CI-6915 Platform Erection 10 10 28-Apr-15 09-May-15 27-Jul-15 02-Aug-15 26-Jul-15 02-Aug-15 185 0%

Access Platforms 45 45 25-Mar-15 16-May-15 25-Jun-15 09-Aug-15 28-Jun-15 09-Aug-15 179

CO-RD-CI-5075 Access Platform Foundation Casting 35 35 25-Mar-15 04-May-15 25-Jun-15 02-Aug-15 28-Jun-15 02-Aug-15 130 0%

CO-RD-CI-5660 Access Platform Prefab. 12 12 21-Apr-15 04-May-15 16-Jul-15 02-Aug-15 19-Jul-15 02-Aug-15 179 0%

CO-RD-CI-7150 Access Platform Erection 10 10 05-May-15 16-May-15 03-Aug-15 09-Aug-15 02-Aug-15 09-Aug-15 179 0%

Cross Overs 45 45 01-Apr-15 23-May-15 02-Jul-15 16-Aug-15 05-Jul-15 16-Aug-15 173

CO-RD-CI-5280 Cross Over Foundation Casting 35 35 01-Apr-15 11-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 130 0%

Remaining Level of Effort Actual Work Milestone Page 1 of 3 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CO-RD-CI-6920 Cross Over Prefab. 12 12 28-Apr-15 11-May-15 27-Jul-15 09-Aug-15 26-Jul-15 09-Aug-15 173 0%

CO-RD-CI-7315 Cross Over Erection 10 10 12-May-15 23-May-15 10-Aug-15 16-Aug-15 09-Aug-15 16-Aug-15 173 0%

Electrical JBs Foundations


Founda 30 30 01-Apr-15 05-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 130

CO-RD-CI-5285 Electrical JB Foundations Casting 30 30 01-Apr-15 05-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 130 0%

Instrument JB Foundations
Found 30 30 01-Apr-15 05-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 150

CO-RD-CI-5290 Instrument JB Foundation Casting 30 30 01-Apr-15 05-May-15 02-Jul-15 09-Aug-15 05-Jul-15 09-Aug-15 150 0%

Piping / Mechanical 46 46 15-Aug-15 07-Oct-15 08-Jul-15 29-Aug-15 11-Jul-15 29-Aug-15 22

Piping Erection 40 40 15-Aug-15 30-Sep-15 08-Jul-15 19-Aug-15 11-Jul-15 19-Aug-15 22

CO-RD-PI-5395 Piping Prefab. 20 20 15-Aug-15 07-Sep-15 08-Jul-15 01-Aug-15 11-Jul-15 01-Aug-15 22 0%

CO-RD-PI-7280 Piping Erection 20 20 07-Sep-15 30-Sep-15 09-Aug-15 19-Aug-15 08-Aug-15 19-Aug-15 22 0%

Inlet Manifold Erection 24 24 15-Aug-15 12-Sep-15 08-Jul-15 08-Aug-15 11-Jul-15 08-Aug-15 38

CO-RD-PI-5400 Inlet Manifold Prefab. 18 18 15-Aug-15 05-Sep-15 08-Jul-15 01-Aug-15 11-Jul-15 01-Aug-15 38 0%

CO-RD-PI-7085 Inlet Manifold Erection 6 6 05-Sep-15 12-Sep-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 38 0%

Mechanical Valves Installation


Ins 10 10 19-Sep-15 30-Sep-15 09-Aug-15 15-Aug-15 08-Aug-15 15-Aug-15 22

CO-RD-PI-7285 Mechanical Valves Installation 10 10 19-Sep-15 30-Sep-15 09-Aug-15 15-Aug-15 08-Aug-15 15-Aug-15 22 0%

Corrosion Fittings 7 7 22-Sep-15 30-Sep-15 20-Aug-15 22-Aug-15 19-Aug-15 22-Aug-15 22

CO-RD-PI-7590 Corrosion Probe / Coupon Installation 7 7 22-Sep-15 30-Sep-15 20-Aug-15 22-Aug-15 19-Aug-15 22-Aug-15 22 0%

Hydrotesting 6 6 30-Sep-15 07-Oct-15 23-Aug-15 29-Aug-15 22-Aug-15 29-Aug-15 22

CO-RD-PI-7620 Hydrotesting 6 6 30-Sep-15 07-Oct-15 23-Aug-15 29-Aug-15 22-Aug-15 29-Aug-15 22 0%

Passive Cooling Shelter


Shel Installation 7 7 22-Sep-15 30-Sep-15 28

CO-RD-PI-7790 Passive Cooling Sheleter Installation 7 7 22-Sep-15 30-Sep-15 28 0%

Electrical 38 38 20-Jul-15 02-Sep-15 02-Aug-15 05-Sep-15 01-Aug-15 05-Sep-15 65

Cable Laying 12 12 20-Jul-15 03-Aug-15 02-Aug-15 15-Aug-15 01-Aug-15 15-Aug-15 79

CO-RD-EL-7090 Electrical Cable Laying 12 12 20-Jul-15 03-Aug-15 02-Aug-15 15-Aug-15 01-Aug-15 15-Aug-15 65 0%

CO-RD-EL-7095 Earthing Cable Laying 12 12 20-Jul-15 03-Aug-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 79 0%

Earthing Works 7 7 20-Jul-15 28-Jul-15 02-Aug-15 03-Aug-15 01-Aug-15 03-Aug-15 84

CO-RD-EL-7100 Earth Bar Installation 7 7 20-Jul-15 28-Jul-15 02-Aug-15 03-Aug-15 01-Aug-15 03-Aug-15 84 0%

Electrical JB Installation
Installat 7 7 03-Aug-15 11-Aug-15 16-Aug-15 17-Aug-15 15-Aug-15 17-Aug-15 65

CO-RD-EL-7475 Electrical JB Installation 7 7 03-Aug-15 11-Aug-15 16-Aug-15 17-Aug-15 15-Aug-15 17-Aug-15 65 0%

Distribution Board Installation


In 7 7 03-Aug-15 11-Aug-15 16-Aug-15 17-Aug-15 15-Aug-15 17-Aug-15 65

Remaining Level of Effort Actual Work Milestone Page 2 of 3 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CO-RD-EL-7480 Distribution Board Installation 7 7 03-Aug-15 11-Aug-15 16-Aug-15 17-Aug-15 15-Aug-15 17-Aug-15 65 0%

Lights & Fixtures 7 7 11-Aug-15 19-Aug-15 18-Aug-15 22-Aug-15 17-Aug-15 22-Aug-15 65

CO-RD-EL-7560 Lights & Fixture Installation 7 7 11-Aug-15 19-Aug-15 18-Aug-15 22-Aug-15 17-Aug-15 22-Aug-15 65 0%

Testing / Termination 12 12 19-Aug-15 02-Sep-15 23-Aug-15 05-Sep-15 22-Aug-15 05-Sep-15 65

CO-RD-EL-7625 Glading & Termination 12 12 19-Aug-15 02-Sep-15 23-Aug-15 05-Sep-15 22-Aug-15 05-Sep-15 65 0%

Instrumentation & Control


Con 56 56 26-Aug-15 29-Oct-15 02-Aug-15 17-Sep-15 01-Aug-15 03-Nov-15 22

Cable Laying 6 6 26-Aug-15 02-Sep-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 48

CO-RD-IC-7105 Instrument Cable Laying 6 6 26-Aug-15 02-Sep-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 48 0%

Instrument JB Installation
Install 7 7 02-Sep-15 10-Sep-15 10-Aug-15 11-Aug-15 09-Aug-15 11-Aug-15 48

CO-RD-IC-7320 Instrument JB Installation 7 7 02-Sep-15 10-Sep-15 10-Aug-15 11-Aug-15 09-Aug-15 11-Aug-15 48 0%

Field Instrument Inst


Installation 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22

CO-RD-IC-7715 Field Instrument Installation 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22 0%

Fire & Gas Equipment 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22

CO-RD-IC-7720 Fire & Gas Equipment Installation 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22 0%

Multiphase Flowmeter 7 7 10-Sep-15 19-Sep-15 09-Aug-15 12-Aug-15 17-Oct-15 20-Oct-15 45

CO-RD-IC-7290 MPFM Installation 7 7 10-Sep-15 19-Sep-15 09-Aug-15 12-Aug-15 17-Oct-15 20-Oct-15 45 0%

Motor Operted Valve 7 7 22-Sep-15 30-Sep-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 35

CO-RD-IC-7725 MOV Installation 7 7 22-Sep-15 30-Sep-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 35 0%

Rotometer 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22

CO-RD-IC-7730 Rotameter Installation 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22 0%

Co2 Analyzer 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22

CO-RD-IC-7735 CO2 Analyzer Installation 7 7 07-Oct-15 15-Oct-15 30-Aug-15 31-Aug-15 29-Aug-15 31-Aug-15 22 0%

Cable Glanding / Termination


Term 17 17 10-Oct-15 29-Oct-15 30-Aug-15 17-Sep-15 15-Oct-15 03-Nov-15 22

CO-RD-IC-7740 Intrument Trays, Tube & Fittings 12 12 10-Oct-15 24-Oct-15 30-Aug-15 12-Sep-15 15-Oct-15 28-Oct-15 22 0%

CO-RD-IC-7790 Glanding & Termination 12 12 15-Oct-15 29-Oct-15 05-Sep-15 17-Sep-15 21-Oct-15 03-Nov-15 22 0%

Telecom 18 18 09-Sep-15 30-Sep-15 16-Sep-15 08-Oct-15 19-Aug-15 09-Sep-15 36

CO-RD-TE-7595 Telecom Works including works at BCDS 18 18 09-Sep-15 30-Sep-15 16-Sep-15 08-Oct-15 19-Aug-15 09-Sep-15 36 0%

Remaining Level of Effort Actual Work Milestone Page 3 of 3 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
ATTACHMENT‐2

Tie‐in Schedule
ADCO CONTRACT NO. 15606.02/EC 10870

EPC FOR BAB FAR NORTH CO2 INJECTION PILOT PROJECT

TIE‐IN SCHEDULE
Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
EPC FOR BAB FA
FAR NORTH CO2 INJECTION PILOT PROJEC 151 151 09-Aug-15 31-Jan-16 02-Aug-15 06-Sep-15 01-Aug-15 06-Sep-15 34

Construction & Pre-Commissioning


Pr 151 151 09-Aug-15 31-Jan-16 02-Aug-15 06-Sep-15 01-Aug-15 06-Sep-15 34

Construction 151 151 09-Aug-15 31-Jan-16 02-Aug-15 06-Sep-15 01-Aug-15 06-Sep-15 34

Tie-Ins 151 151 09-Aug-15 31-Jan-16 02-Aug-15 06-Sep-15 01-Aug-15 06-Sep-15 34

Rumaitha 82 82 18-Aug-15 22-Nov-15 12-Aug-15 13-Aug-15 18-Aug-15 19-Aug-15 16

CO-RU-EL-7725 Telecom Tie-ins from FO Patch Panel NEB 5 5 18-Aug-15 24-Aug-15 93 0%

CO-RU-PI-7700 6" HC Piping with Lift gas (Hydrocasrbon) (TP-23) 5 5 14-Oct-15 20-Oct-15 13-Aug-15 13-Aug-15 19-Aug-15 19-Aug-15 44 0%

CO-RU-PI-7705 4" HC Piping with NEB Piping for Start up Pressurization (TP-101) 5 5 14-Oct-15 20-Oct-15 13-Aug-15 13-Aug-15 19-Aug-15 19-Aug-15 44 0%

CO-RU-PI-7685 8" CO2 Pipeline with NEB CO2 (TP-12) 5 5 17-Oct-15 22-Oct-15 12-Aug-15 12-Aug-15 18-Aug-15 18-Aug-15 42 0%

CO-RU-EL-7715 Electrical Tie-ins from 415 V Switchgear 5 5 16-Nov-15 22-Nov-15 16 0%

North Flank 34 34 18-Oct-15 26-Nov-15 12

CO-NF-PI-9000 6" Piping with Wing Valve Xmas Tree (TP-01A/B) 5 5 18-Oct-15 24-Oct-15 41 0%

CO-NF-PI-9010 4" Vent piping with Injection Well Casing (TP-03A/B & 04A/B) 5 5 18-Oct-15 24-Oct-15 41 0%

CO-NF-PI-9020 6" Flowline to Producer Well (TP-05A) 5 5 04-Nov-15 10-Nov-15 26 0%

CO-NF-PI-9030 2" Vent Connection form Producer Well to Annulus Bleed (TP-06A) 5 5 04-Nov-15 10-Nov-15 26 0%

CO-NF-PI-9040 2"Asphaltene / Corrosion Inhibitor at X mas Tree (TP-07A) 5 5 04-Nov-15 10-Nov-15 26 0%

CO-NF-EL-9050 Electrical Tie-ins (33 KV AC, 3 Phase to 33 KV OHL 7A) - Shut 5 5 21-Nov-15 26-Nov-15 12 0%
Down Required
East Flank 15 15 13-Jan-16 31-Jan-16 34

CO-NF-PI-9050 6" Piping with Wing Valve Xmas Tree (TP-01C/D) 5 5 13-Jan-16 19-Jan-16 44 0%

CO-NF-PI-9060 4" Vent piping with Injection Well Casing (TP-03C/D & 04C/D) 5 5 13-Jan-16 19-Jan-16 44 0%

CO-NF-EL-9060 Electrical Tie-ins (33 KV AC, 3 Phase to 33 KV OHL 7B) - Shut 5 5 20-Jan-16 26-Jan-16 38 0%
Down Required
CO-NF-PI-9070 6" Flowline to Producer Well (TP-05B) 5 5 25-Jan-16 31-Jan-16 34 0%

CO-NF-PI-9080 2" Vent Connection form Producer Well to Annulus Bleed (TP-06B) 5 5 25-Jan-16 31-Jan-16 34 0%

CO-NF-PI-9090 2"Asphaltene / Corrosion Inhibitor at X mas Tree (TP-07B) 5 5 25-Jan-16 31-Jan-16 34 0%

Water Injection Clusters


Cluste 7 7 09-Aug-15 16-Aug-15 178

CO-EF-PI-9100 Water Injector Line Tie-in at Cluster 30 (TP-16A/B) - Shut Down 5 5 09-Aug-15 13-Aug-15 102 0%
Required
CO-NF-PI-9110 Water Injector Line Tie-in at Cluster 31 (TP-15A/B) - Shut Down 5 5 11-Aug-15 16-Aug-15 178 0%
Required

Remaining Level of Effort Actual Work Milestone Page 1 of 2 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
Activity ID Activity Name Original Remainin Revised Revised Baseline Baseline Recovery Recovery Total Activity % 2014 2015 2016
Duration Duration Start Finish Start Finish Start Finish Float Complete Q3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RDS-8 44 44 02-Sep-15 22-Oct-15 02-Aug-15 06-Sep-15 01-Aug-15 06-Sep-15 42

CO-RD-IC-7800 SCMS Moditfication (BAB CDS) 5 5 02-Sep-15 08-Sep-15 81 0%

CO-RD-IC-7810 DCS Modification (BAB CDS) 5 5 02-Sep-15 08-Sep-15 81 0%

CO-RD-EL-7135 Electrical Tie-ins 5 5 02-Sep-15 08-Sep-15 80 0%

CO-RD-IC-7110 DCS Modification 5 5 30-Sep-15 06-Oct-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 36 0%

CO-RD-IC-7115 FGS Modification 5 5 30-Sep-15 06-Oct-15 02-Aug-15 08-Aug-15 01-Aug-15 08-Aug-15 56 0%

CO-RD-IC-7125 SDH Cabinet Modification 5 5 30-Sep-15 06-Oct-15 56 0%

CO-RD-IC-7145 Telecom Tie-ins 5 5 30-Sep-15 06-Oct-15 56 0%

CO-RD-IC-7820 SDH Modification (BAB CDS) 5 5 30-Sep-15 06-Oct-15 56 0%

CO-RD-IC-7830 Telecom Modification (BAB CDS) 5 5 30-Sep-15 06-Oct-15 56 0%

CO-RD-IC-7840 SCADA Modification (BAB CDS) 5 5 30-Sep-15 06-Oct-15 56 0%

CO-RD-PI-7760 2" Vent Header Header from Manifold to Blowdown Header 5 5 15-Oct-15 21-Oct-15 01-Sep-15 01-Sep-15 31-Aug-15 01-Sep-15 42 0%
(TP-17) - Shut Down Required
CO-RD-PI-7765 2" Drain Piping to from MPFM to Blowdown Header (TP-18 A/B) - 5 5 15-Oct-15 21-Oct-15 01-Sep-15 02-Sep-15 31-Aug-15 02-Sep-15 42 0%
Shut Down Required
CO-RD-PI-7770 2" Manual Vent from MPFM to Blowdown Header (TP-19A/B) - 5 5 17-Oct-15 22-Oct-15 02-Sep-15 06-Sep-15 01-Sep-15 06-Sep-15 42 0%
Shut Down Required
CO-RD-PI-7775 10" Production Header to 24"Transfer Line (TP-20A/B) - Shut 5 5 17-Oct-15 22-Oct-15 02-Sep-15 06-Sep-15 01-Sep-15 06-Sep-15 42 0%
Down Required
CO-RD-PI-7780 Tie-in with Exisiting Corrosion Inhibitor Package(TP-21) - Shut 5 5 17-Oct-15 22-Oct-15 02-Sep-15 02-Sep-15 01-Sep-15 02-Sep-15 42 0%
Down Required
CO-RD-PI-7800 2" Nitrogen piping to Exisitng Nitrogen Header (TP-102) - Shut 5 5 17-Oct-15 22-Oct-15 42 0%
Down Required

Remaining Level of Effort Actual Work Milestone Page 2 of 2 Date Revision Checked Approved
27-Jan-15 Revised Project Schedule PCM PM
Primary Baseline Remaining Work Summary Cut off Date: 28 Nov 14
Second Baseline Critical Remaining Work
ATTACHMENT‐3

OHL Tie‐in duration from Sub Contractor M/s Ranya