Project : TIENHAI - THAIBINH LOW PRESSURE GAS DISTRIBUTION PIPELINE SYSTEM PROJECT VENDOR DOCUMENT REGISTER

Package :GAS DEHYDRATION PACKAGE


Vendor : SOUTHERN PETROLEUM CONSTRUCTION J.S COMPANY COMMENT CODE EXPLAINATION
PO. No. : Approved with
1 Approved 2
Comment
Vend Doc. No. KTA.TB-PAC03-C01-002 4 Info 3 Reject

PROSERNAT's Commen
VDRL
Sequential No. Purchaser No. VENDOR'S No. Document DOCUMENT TITLE REV. t code DNV Review Status: ASME Status: Action by:
Code
Numbers status

INSTRUMENT
001 J19 KTA.TB-PAC03 KTA.TB-PAC03-J19-001 I/O list A Viet-VG
002 J09 KTA.TB-PAC03 KTA.TB-PAC03-J09-002 Instrument wiring diagram A Viet-VG
001 J18 KTA.TB-PAC03 KTA.TB-PAC03-J18-001 Instrument Index A Viet-VG
001 J05 KTA.TB-PAC03 KTA.TB-PAC03-J05-001 Hook-up drawing Viet-VG
002 J04 KTA.TB-PAC03 KTA.TB-PAC03-J04-002 Instrument JB, F&G Layout R Viet-VG
002 J22 KTA.TB-PAC03 KTA.TB-PAC03-J22-002 Instrument cable schedule A Viet-VG
001 J06 KTA.TB-PAC03 KTA.TB-PAC03-J06-001 Control Loop Diagram Viet-VG
001 J27 KTA.TB-PAC03 KTA.TB-PAC03-J27-001 Interfacing signal list (list of signal will be sent to ICSS) Viet-VG
003 J04 KTA.TB-PAC03 KTA.TB-PAC03-J04-003 UCP Layout Viet-VG
004 J04 KTA.TB-PAC03 KTA.TB-PAC03-J04-004 Instrument Air Routing Viet-VG
001 J13 KTA.TB-PAC03 KTA.TB-PAC03-J13-001 Instrument Datasheet A Viet-VG
ELECTRICAL
001 J09 KTA.TB-PAC03 KTA.TB-PAC03-J09-001 Lighting wiring diagram Viet-VG

Page : 1 of 12
Project : TIENHAI - THAIBINH LOW PRESSURE GAS DISTRIBUTION PIPELINE SYSTEM PROJECT VENDOR DOCUMENT REGISTER
Package :GAS DEHYDRATION PACKAGE
Vendor : SOUTHERN PETROLEUM CONSTRUCTION J.S COMPANY COMMENT CODE EXPLAINATION
PO. No. : Approved with
1 Approved 2
Comment
Vend Doc. No. KTA.TB-PAC03-C01-002 4 Info 3 Reject

PROSERNAT's Commen
VDRL
Sequential No. Purchaser No. VENDOR'S No. Document DOCUMENT TITLE REV. t code DNV Review Status: ASME Status: Action by:
Code
Numbers status

001 J22 KTA.TB-PAC03 KTA.TB-PAC03-J22-001 Electric cable schedule Viet-VG


001 J04 KTA.TB-PAC03 KTA.TB-PAC03-J04-001 Electrical Lighting Layout Viet-VG
001 J11 KTA.TB-PAC03 KTA.TB-PAC03-J11-001 Single Line Diagram A R Viet-VG
002 J13 KTA.TB-PAC03 KTA.TB-PAC03-J13-002 Distribution Board Datasheet A R Viet-VG
001 J01 KTA.TB-PAC03 KTA.TB-PAC03-J01-001 Distribution Board Arrangement Drawing Viet-VG
003 J09 KTA.TB-PAC03 KTA.TB-PAC03-J09-003 Distribution Board Wiring Diagram A Viet-VG
001 G10 KTA.TB-PAC03 KTA.TB-PAC03-G10-001 Hazardous Area Certification R Viet-VG
001 J24 KTA.TB-PAC03 KTA.TB-PAC03-J24-001 Cable Ladder/Tray Layout Viet-VG
001 J16 KTA.TB-PAC03 KTA.TB-PAC03-J16-001 Instrument, F&G Block Diagram A R Viet-VG
003 J13 KTA.TB-PAC03 KTA.TB-PAC03-J13-003 Junction Box Datasheet R Viet-VG
PIPING AND MECHANICAL
001 M52 KTA.TB-PAC03 KTA.TB-PAC03-M52-001 Piping Plan Viet-VG
002 M52 KTA.TB-PAC03 KTA.TB-PAC03-M52-002 Pipe Support R Viet-VG
001 M05 KTA.TB-PAC03 KTA.TB-PAC03-M05-001 Pipe stress analysis Viet-VG
001 M55 KTA.TB-PAC03 KTA.TB-PAC03-M55-001 Piping iso metric Viet-VG
030 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-030 Mechanical datasheet skid - Contactor - C-101 A 2 R X Viet-VG
031 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-031 Mechanical datasheet skid - Still column -C-102 A R Viet-VG
032 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-032 Mechanical datasheet skid -Stripping column -C-103 A 2 R Viet-VG
033 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-033 Mechanical datasheet skid - Feed gas heater -E-101 A R Viet-VG
034 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-034 Mechanical datasheet skid - Still reflux condenser - E-104 A R Viet-VG
035 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-035 Mechanical datasheet skid - Overhead condenser -E-105 R Viet-VG
036 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-036 Mechanical datasheet skid - Lean Glycol cooler -E-106 A R Viet-VG
037 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-037 Mechanical datasheet skid - Flash drum - V-101 A 2 R Viet-VG
038 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-038 Mechanical datasheet skid - Glycol reboiler -V-102 A R Viet-VG
039 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-039 Mechanical datasheet skid - Surge drum - V-103 A R Viet-VG
040 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-040 Mechanical datasheet skid - Reflux drum - V-104 A 2 R Viet-VG
041 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-041 Mechanical datasheet skid - Glycol filter - F-101A/B A 2 R Viet-VG
001 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-001 Mechanical Calculation- Contactor - C-101 A 1 R X Viet-VG
002 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-002 Mechanical Calculation- Still column- C-102 A R X Viet-VG
003 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-003 Mechanical Calculation- Stripping column - C-103 A 1 R X Viet-VG
004 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-004 Mechanical Calculation- Feed gas heater- E-101 A R X Viet-VG
005 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-005 Mechanical Calculation- Still reflux condenser - E-104 A R Viet-VG
006 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-006 Mechanical Calculation- Overhead condenser - E-105 R Viet-VG
007 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-007 Mechanical Calculation- Lean Glycol cooler - E-106 A R X Viet-VG
008 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-008 Mechanical Calculation- Flash drum- V-101 A 1 R X Viet-VG
009 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-009 Mechanical Calculation- Glycol reboiler-V-102 A R X Viet-VG
010 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-010 Mechanical Calculation- Surge drum -V-103 A R X Viet-VG
011 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-011 Mechanical Calculation- Reflux drum- V-104 A 1 R X Viet-VG
Page : 2 of 12
Project : TIENHAI - THAIBINH LOW PRESSURE GAS DISTRIBUTION PIPELINE SYSTEM PROJECT VENDOR DOCUMENT REGISTER
Package :GAS DEHYDRATION PACKAGE
Vendor : SOUTHERN PETROLEUM CONSTRUCTION J.S COMPANY COMMENT CODE EXPLAINATION
PO. No. : Approved with
1 Approved 2
Comment
Vend Doc. No. KTA.TB-PAC03-C01-002 4 Info 3 Reject

PROSERNAT's Commen
VDRL
Sequential No. Purchaser No. VENDOR'S No. Document DOCUMENT TITLE REV. t code DNV Review Status: ASME Status: Action by:
Code
Numbers status

012 M03 KTA.TB-PAC03 KTA.TB-PAC03-M03-012 Mechanical Calculation- Glycol filter - F-101A/B A 1 R X Viet-VG
001 M04 KTA.TB-PAC03 KTA.TB-PAC03-M04-001 Structure calculation R Viet-VG
002 M04 KTA.TB-PAC03 KTA.TB-PAC03-M04-002 structure drawing Viet-VG
003 M04 KTA.TB-PAC03 KTA.TB-PAC03-M04-003 Handrail, ladder drawing Viet-VG
001 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-001 GA Drawing- Contactor - C-101 A 2 X Viet-VG
002 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-002 GA Drawing-Still column- C-102 A X Viet-VG
003 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-003 GA Drawing-Stripping column- C-103 A 2 X Viet-VG
004 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-004 GA Drawing-Feed gas heater -E-101 A X Viet-VG
005 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-005 GA Drawing-Still reflux condenser -E-104 A Viet-VG
006 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-006 GA Drawing-Overhead condenser-E-105 Viet-VG
007 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-007 GA Drawing-Lean Glycol cooler- E-106 A X Viet-VG
008 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-008 GA Drawing-Flash drum - V-101 A 2 X Viet-VG
009 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-009 GA Drawing-Glycol reboiler - V-102 A X Viet-VG

Page : 3 of 12
Project : TIENHAI - THAIBINH LOW PRESSURE GAS DISTRIBUTION PIPELINE SYSTEM PROJECT VENDOR DOCUMENT REGISTER
Package :GAS DEHYDRATION PACKAGE
Vendor : SOUTHERN PETROLEUM CONSTRUCTION J.S COMPANY COMMENT CODE EXPLAINATION
PO. No. : Approved with
1 Approved 2
Comment
Vend Doc. No. KTA.TB-PAC03-C01-002 4 Info 3 Reject

PROSERNAT's Commen
VDRL
Sequential No. Purchaser No. VENDOR'S No. Document DOCUMENT TITLE REV. t code DNV Review Status: ASME Status: Action by:
Code
Numbers status

010 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-010 GA Drawing-Surge drum - V-103 A X Viet-VG


011 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-011 GA Drawing-Reflux drum - V-104 A 2 X Viet-VG
012 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-012 GA Drawing-Glycol filter - F-101A/B A 2 X Viet-VG
013 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-013 Detail Drawing- Contactor - C-101 Viet-VG
014 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-014 Detail Drawing- Still column- C-102 Viet-VG
015 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-015 Detail Drawing- Stripping column- C-103 Viet-VG
016 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-016 Detail Drawing- Feed gas heater -E-101 Viet-VG
017 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-017 Detail Drawing- Still reflux condenser-E-104 Viet-VG
018 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-018 Detail Drawing- Overhead condenserE-105 Viet-VG
019 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-019 Detail Drawing- Lean Glycol cooler- E-106 Viet-VG
020 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-020 Detail Drawing- Flash drum - V-101 Viet-VG
021 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-021 Detail Drawing- Glycol reboiler - V-102 Viet-VG
022 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-022 Detail Drawing- Surge drum- V-103 Viet-VG
023 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-023 Detail Drawing- Reflux drum - V-104 Viet-VG
024 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-024 Detail Drawing- Glycol filter - F-101A/B Viet-VG
025 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-025 GA DRAWING SKID (TIE-IN POINT) Viet-VG
026 M35 KTA.TB-PAC03 KTA.TB-PAC03-M35-026 Equipment Plan Viet-VG
003 M65 KTA.TB-PAC03 KTA.TB-PAC03-M65-003 Piping Class Specification R Viet-VG
001 M32 KTA.TB-PAC03 KTA.TB-PAC03-M32-001 Lifting Arrangement Drawing R Viet-VG
002 Q29 KTA.TB-PAC03 KTA.TB-PAC03-Q29-002 Lifting Anylysis Report R Viet-VG
001 M38 KTA.TB-PAC03 KTA.TB-PAC03-M38-001 Weight Control Calculation Viet-VG
004 M65 KTA.TB-PAC03 KTA.TB-PAC03-M65-004 Pressure Vessel Specification R Viet-VG
002 Q04 KTA.TB-PAC03 KTA.TB-PAC03-Q04-002 Inspection and Test Plan for Piping Mark up Viet-VG
006 Q04 KTA.TB-PAC03 KTA.TB-PAC03-Q04-006 Inspection and Test Plan for Mechanical/Structure/Vessel Mark up Viet-VG
017 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-017 Air Cooler Datasheet for Cooling water system Viet-VG
018 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-018 Heater (or Boiler) Datasheet for Cooling water system Viet-VG
006 M20 KTA.TB-PAC03 KTA.TB-PAC03-M20-006 Water Pump & Motor datasheet for Cooling water system Viet-VG
008 M20 KTA.TB-PAC03 KTA.TB-PAC03-M20-008 Glycol Pump Datasheet (Glycol Make-up) Viet-VG
007 M20 KTA.TB-PAC03 KTA.TB-PAC03-M20-007 Chemical Injection Pump Datasheet Viet-VG
006 M51 KTA.TB-PAC03 KTA.TB-PAC03-M51-006 Piping Wall Thickness Calculation Viet-VG
021 M19 KTA.TB-PAC03 KTA.TB-PAC03-M19-021 Datasheet for Manual Valves Viet-VG

Page : 4 of 12
ATION
roved with
mment
ct

TK-KTDA AECC-DNVGL

Submission Submission Return Submission Return Submission


Finish Plan
plan
Requir Trans Require Trans
Trans No. Sub Date Deadline % Date CS NO. Status Trans No. Sub Date Deadline Date CS NO. Status Trans No. Sub Date
e for No. for No.

30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014

30-Nov-2014 20-Dec-2014

Page : 5 of 12
ATION
roved with
mment
ct

TK-KTDA AECC-DNVGL

Submission Submission Return Submission Return Submission


Finish Plan
plan
Requir Trans Require Trans
Trans No. Sub Date Deadline % Date CS NO. Status Trans No. Sub Date Deadline Date CS NO. Status Trans No. Sub Date
e for No. for No.
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014
30-Nov-2014 20-Dec-2014

21-Oct-2014 15-Nov-2014
21-Oct-2014 15-Nov-2014
21-Oct-2014 15-Nov-2014
21-Oct-2014 15-Nov-2014
28-Sep-2014 15-Oct-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 002 10-Oct-2014 IFR 17-Oct-14 001 11-Oct-2014
28-Sep-2014 15-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14
28-Sep-2014 15-Oct-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 002 10-Oct-2014 IFR 17-Oct-14
28-Sep-2014 15-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14
28-Sep-2014 15-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14
28-Sep-2014 15-Oct-2014
28-Sep-2014 15-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14
28-Sep-2014 15-Oct-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 002 10-Oct-2014 IFR 17-Oct-14
28-Sep-2014 15-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14
28-Sep-2014 15-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14
28-Sep-2014 15-Oct-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 002 10-Oct-2014 IFR 17-Oct-14
28-Sep-2014 15-Oct-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 002 10-Oct-2014 IFR 17-Oct-14
30-Sep-2014 6-Oct-2014 6-Oct-2014 IFR 13-Oct-14 95% 21-Oct-2014 017.1 1 002 10-Oct-2014 IFR 17-Oct-14 001 11-Oct-2014
3-Oct-2014 10-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14 004 25-Oct-2014
3-Oct-2014 10-Oct-2014 6-Oct-2014 IFR 13-Oct-14 95% 21-Oct-2014 017.1 1 002 10-Oct-2014 IFR 17-Oct-14 001 11-Oct-2014
3-Oct-2014 10-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14 004 25-Oct-2014
3-Oct-2014 10-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14
30-Sep-2014 6-Oct-2014
3-Oct-2014 10-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14 004 25-Oct-2014
30-Sep-2014 6-Oct-2014 6-Oct-2014 IFR 13-Oct-14 95% 21-Oct-2014 017.1 1 002 10-Oct-2014 IFR 17-Oct-14 001 11-Oct-2014
3-Oct-2014 10-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14 004 25-Oct-2014
3-Oct-2014 10-Oct-2014 24-Oct-2014 IFR 31-Oct-14 40% 007 25-Oct-2014 IFR 1-Nov-14 004 25-Oct-2014
3-Oct-2014 10-Oct-2014 6-Oct-2014 IFR 13-Oct-14 95% 21-Oct-2014 017.1 1 002 10-Oct-2014 IFR 17-Oct-14 001 11-Oct-2014

Page : 6 of 12
ATION
roved with
mment
ct

TK-KTDA AECC-DNVGL

Submission Submission Return Submission Return Submission


Finish Plan
plan
Requir Trans Require Trans
Trans No. Sub Date Deadline % Date CS NO. Status Trans No. Sub Date Deadline Date CS NO. Status Trans No. Sub Date
e for No. for No.
30-Sep-2014 6-Oct-2014 6-Oct-2014 IFR 13-Oct-14 95% 21-Oct-2014 017.1 1 002 10-Oct-2014 IFR 17-Oct-14 001 11-Oct-2014
30-Oct-2014 15-Nov-2014
30-Oct-2014 15-Nov-2014
30-Oct-2014 15-Nov-2014
30-Oct-2014 15-Nov-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 001 11-Oct-2014
30-Oct-2014 15-Nov-2014 25-Oct-2014 IFR 1-Nov-14 40% 004 25-Oct-2014
30-Oct-2014 15-Nov-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 001 11-Oct-2014
30-Oct-2014 15-Nov-2014 25-Oct-2014 IFR 1-Nov-14 40% 004 25-Oct-2014
30-Oct-2014 15-Nov-2014 25-Oct-2014 IFR 1-Nov-14 40%
30-Oct-2014 15-Nov-2014
30-Oct-2014 15-Nov-2014 25-Oct-2014 IFR 1-Nov-14 40% 004 25-Oct-2014
30-Oct-2014 15-Nov-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 001 11-Oct-2014
30-Oct-2014 15-Nov-2014 25-Oct-2014 IFR 1-Nov-14 40% 004 25-Oct-2014

Page : 7 of 12
ATION
roved with
mment
ct

TK-KTDA AECC-DNVGL

Submission Submission Return Submission Return Submission


Finish Plan
plan
Requir Trans Require Trans
Trans No. Sub Date Deadline % Date CS NO. Status Trans No. Sub Date Deadline Date CS NO. Status Trans No. Sub Date
e for No. for No.
30-Oct-2014 15-Nov-2014 25-Oct-2014 IFR 1-Nov-14 40% 004 25-Oct-2014
30-Oct-2014 15-Nov-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 001 11-Oct-2014
30-Oct-2014 15-Nov-2014 6-Oct-2014 IFR 13-Oct-14 70% 21-Oct-2014 017.1 2 001 11-Oct-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 4-Dec-2014
15-Nov-2014 30-Nov-2014
15-Nov-2014 30-Nov-2014
15-Nov-2014 30-Nov-2014
15-Nov-2014 30-Nov-2014
15-Nov-2014 30-Nov-2014
15-Nov-2014 30-Nov-2014
30-Sep-2014 15-Oct-2014
15-Nov-2014 30-Nov-2014
15-Nov-2014 30-Nov-2014
3-Oct-2014 15-Oct-2014
3-Oct-2014 15-Oct-2014
15-Oct-2014 30-Oct-2014
15-Oct-2014 30-Oct-2014
30-Oct-2014 15-Nov-2014
15-Nov-2014 30-Nov-2014
15-Oct-2014 30-Oct-2014

Page : 8 of 12
AECC-ASME

Submission Return REMARKS

Require Trans
Deadline Date CS NO. Status
for No.

Page : 9 of 12
AECC-ASME

Submission Return REMARKS

Require Trans
Deadline Date CS NO. Status
for No.

IFR 18-Oct-14

IFR 18-Oct-14
IFR 1-Nov-14
IFR 18-Oct-14
IFR 1-Nov-14

IFR 1-Nov-14
IFR 18-Oct-14
IFR 1-Nov-14
IFR 1-Nov-14
IFR 18-Oct-14
Page : 10 of 12
AECC-ASME

Submission Return REMARKS

Require Trans
Deadline Date CS NO. Status
for No.
IFR 18-Oct-14

IFR 18-Oct-14
IFR 1-Nov-14
IFR 18-Oct-14
IFR 1-Nov-14

IFR 1-Nov-14
IFR 18-Oct-14
IFR 1-Nov-14

Page : 11 of 12
AECC-ASME

Submission Return REMARKS

Require Trans
Deadline Date CS NO. Status
for No.
IFR 1-Nov-14
IFR 18-Oct-14
IFR 18-Oct-14

Page : 12 of 12