APUL Project Management Plan
_____________________________ _____________________________
P. Wanderer date S. Vigdor date
APUL Project Manager Associate Laboratory Director for Nuclear and
Particle Physics
Fermilab
_____________________________
S. Aronson date
_____________________________ Laboratory Director
S. Holmes date
Associate Director for Accelerators
_____________________________
G. Apollinari date
Head of Technical Division
______________________________
N. Grossman date
ES&H Director
______________________________
P. Garbincius date
Associate Director for Research, Fermilab
______________________________
P. Oddone date
iii
APUL Project Management Plan
iv
Table of Contents
Abbreviations Used in this Document...............................................................................vii
1 Introduction..................................................................................................................1
1.1 Approval and Revision........................................................................................1
1.2 Project Description..............................................................................................1
2 Project Objectives and Performance Criteria..............................................................2
2.1 Scientific Objectives............................................................................................2
2.2 Technical Requirements and Objectives..............................................................2
3 Project Structure and WBS Dictionary........................................................................3
3.1 Work Breakdown Structure (WBS) Overview....................................................3
3.2 WBS Dictionary...................................................................................................3
4 Project Management Structure....................................................................................5
4.1 The Fermilab Directorate.....................................................................................5
4.1.1 The Fermilab Director.................................................................................5
4.1.2 Fermilab Associate Director for Accelerators..............................................5
4.2 Fermilab Divisions & Sections............................................................................6
4.2.1 Technical Division Head..............................................................................6
4.2.2 Business Services Section Head..................................................................6
4.3 The APUL Project Management Team................................................................6
4.3.1 APUL Project Manager...............................................................................7
4.3.2 Deputy Project Manager..............................................................................7
4.3.3 APUL Project Engineer...............................................................................8
4.3.4 APUL ES&H Coordinator...........................................................................8
4.3.5 APUL Documentation Coordinator.............................................................8
4.3.6 APUL Scheduler..........................................................................................9
4.3.7 APUL Budget Officer..................................................................................9
4.4 APUL Subsystem (Level 2) Managers................................................................9
4.5 APUL Project Management Group....................................................................10
4.6 The Technical Advisory Committee..................................................................10
5 Project Controls System.............................................................................................11
5.1 Memoranda of Understanding/Statement of Work............................................11
5.2 Project Execution Plan.......................................................................................12
5.3 Cost Tracking.....................................................................................................12
5.4 Contingency Allocation.....................................................................................12
5.5 Change Controls................................................................................................12
5.5.1 Change Control Procedures.......................................................................13
5.5.2 Technical Change Control Levels..............................................................13
5.5.3 Schedule Change Control Levels...............................................................13
5.5.4 Cost Change Control Levels......................................................................13
5.5.5 Change Control Summary.........................................................................14
5.6 Reporting...........................................................................................................15
5.7 Reviews..............................................................................................................16
5.7.1 Level 2 Technical Reviews........................................................................16
5.7.2 Level 2 ES&H Reviews.............................................................................16
5.7.3 Director’s Reviews....................................................................................16
6 Environment, Safety and Health................................................................................17
6.1 ES&H Organizations.........................................................................................17
6.1.1 APUL ES&H Review Committee.............................................................17
6.1.2 ES&H Responsibilities of APUL Project Staff..........................................17
6.2 ES&H Documentation.......................................................................................18
6.2.1 Environmental Considerations...................................................................18
6.2.2 Safety Assessment Documentation............................................................18
7 Technical Considerations...........................................................................................18
7.1 Quality Assurance..............................................................................................18
7.2 Risk Management..............................................................................................19
7.3 Configuration Management...............................................................................19
7.4 Value Engineering..............................................................................................19
Appendices........................................................................................................................21
A APUL Technical Scope..............................................................................................21
B APUL Cost.................................................................................................................22
C APUL Schedule.........................................................................................................23
References..........................................................................................................................25
Abbreviations Used in this Document (NEED TO
UPDATE)
BAC: Budget At Completion
CCB: Change Control Board
CDR: Conceptual Design Report
DOE: U.S. Department of Energy
DPM: Deputy Project Manager
ES&H: Environment, Safety and Health
FMS: Financial Management System
FPD: Federal Project Director
HV: High Voltage
ISM: Integrated Safety Management
MAPMT: Multi-Anode Photo-Multiplier Tube
MND: MINOS Near Detector
MOU: Memorandum of Understanding
NuMI: Neutrinos at the Main Injector
NSF: National Science Foundation
PCR: Project Change Request
PEP: Project Execution Plan
PM: Project Manager
PMG: Project Management Group
PMP: Project Management Plan
PMR: (Universities) Project Management Representative
PMT: Photomultiplier Tube
PSAD: Preliminary Safety Assessment Document
QA: Quality Assurance
QAP: Quality Assurance Plan
RSO: Radiation Safety Officer
SAD: Safety Assessment Document
SOW: Statement of Work
TDR: Technical Design Report
TEC: Total Estimated Cost
VME: Versa Module Europa (bus system)
WBS: Work Breakdown Structure
WLS: Wavelength Shifting
1 Introduction
This document describes the Project Management Plan (PMP) that the Fermi National
Accelerator Laboratory (Fermilab) and Brookhaven National Laboratory (BNL) will
follow to meet the technical, cost, and schedule objectives of the APUL Project. DOE,
Fermilab and BNL will work together to accomplish the APUL Project. This PMP for the
APUL Project sets forth the plans, organization and management systems that will be
used by Fermilab and BNL. The PMP is complemented by a Project Execution Plan
(PEP). The PEP establishes the DOE APUL Project Management structure. The overall
project management will be in conformance with applicable DOE orders and established
management practices at Fermilab.
This PMP covers the construction of the US part of the LHC Phase I upgrades, i.e., the
design, fabrication, testing and delivery of components to CERN by the US Laboratory
Collaboration defined as the APUL project. It does not cover the installation and
commissioning of the delivered components at CERN, which are outside of the scope of
APUL.
1
magnets and cold powering systems at interaction regions at points 1 and 5 and two laser
profile monitors (LPM) for the linac (VERIFY to which CERN project LPM would
belong).
(Need to verify this following paragraph) General program oversight for the US LHC
Accelerator Project is the responsibility of the US Department of Energy (DOE) and the
Project is administered through the DOE Office of Energy Research, Division of High
Energy Physics (DHEP), the DOE Chicago Operations Office, and the DOE Fermi Group
Site Office. The project work will be undertaken by two US national laboratories:
Brookhaven National Laboratory (BNL), Fermi National Accelerator Laboratory
(Fermilab or FNAL), directed by the Project Manager and Project Management Office.
When taken together, these laboratories will be designated in this document as the US
Laboratory Collaboration. Fermilab has been designated as the lead laboratory with the
major responsibility to ensure the successful completion of APUL.
The TDR is a controlled document of APUL requiring approval of its initial contents and
of any changes by the Project Manager following recommendation by the Change
Control Board. The initial contents of, and any changes to, the TDR must also be
approved by CERN, as specified in the Implementing Arrangement (or MoU?).
Technical milestones to measure the progress and success in meeting these goals are
established as part of the Project Baseline. Meeting each subsystem’s objectives is the
responsibility of the corresponding Subsystem (Level 2) Manager. Ensuring that the
2
project as a whole meets the scientific objectives of the experiment is the responsibility of
the Project Manager.
APUL must be executed in a manner consistent with the overall LHC Phase I upgrade
project schedule. The current version of the overall Phase I upgrade schedule is found at
the web site http://slhc-irp1.web.cern.ch/slhc-irp1/. (There is currently only some rough
milestones here, will there be a CERN master schedule for upgrades that we are to work
to? If so, will APUL appear as milestones?) Coordination of the US Project schedule
with the master Phase I upgrade schedule maintained by CERN is accomplished by
setting milestones, typically corresponding to the delivery of equipment to CERN by
APUL or to the US laboratories by CERN for incorporation into US-provided systems.
These milestones are under joint US-CERN change control as specified in the
Implementing Arrangement and in Appendix C here.
Appendices A, B and C provide additional information on the project scope, cost and
schedule, respectively.
APUL Project
Figure Project Structure and WBS Dictionary.1: Overview of APUL Work Breakdown Structure, to Level 2
3
profile monitors for LHC Phase I Upgrade
1.0 Project Management Management support. Project financial, schedule,
budget, and change control, coordination with CERN
2.0 Beam Separation Design, fabricate, test, and deliver five(5) D1
Dipole Magnets standalone magnets
3.0 Cold Powering Design, fabricate, and deliver five(5) distribution
feed boxes and corresponding current leads and
superconducting links
4.0 Laser Profile Design, assemble, and deliver two laser profile
Monitoring monitors for LINAC4
Table Project Structure and WBS Dictionary.1: APUL Level-2 WBS Dictionary
4
4 Project Management Structure
Figure Project Management Structure.2 shows an organizational chart of the APUL
Project. The Integrated Project Team is expanded into the DOE hierarchy in the Project
Execution Plan.
Figure Project Management Structure.2 Fermilab APUL Organization Chart (Probably want to get rid of
“Future Projects”)
5
APUL Project Manager. To implement the work plan for the Project, APUL Memoranda
of Understanding are executed with collaborating institutions. The Associate Director for
Accelerators, on behalf of the Director, approves all APUL Institutional Memoranda of
Understanding related to the Project. The Associate Director for Accelerators also chairs
the APUL Project Management Group.
On guidance from the Director, the TD Head allocates yearly budgets to the Project.
These project funds are then administered by the Project Manager, according to the
responsibilities described below, within the context of TD procedures and policies and
with the support of the TD budget office.
The TD is the primary source of Fermilab manpower and technical resources for the
project.
6
Manager, are appointed by the TD Head with concurrence of the the Project Manager.
Collectively they comprise the Project Management Team.1 The Project Management
Team assists the APUL Project Manager in supporting and coordinating the efforts of the
subsystem managers in executing the APUL Project.
The APUL PM works with representatives of the divisions and sections at Fermilab and
BNL to obtain resources for the project as approved by the Fermilab and BNL
Directorate. This may include the development of additional MOU between the Project
and specific Fermilab and BNL divisions or sections.
The PM assigns responsibilities and resources to the Subsystem Managers. The progress
of these assignments is monitored through monthly status reports generated by the
Subsystem Managers, by means of regular Subsystem Managers meetings, and through
daily communications. The APUL PM is responsible for developing, maintaining, and
tracking the schedule for the project, which includes a complete list of milestones to
facilitate monitoring the progress of the project. The APUL PM provides monthly reports
summarizing the progress of the Project to the Fermilab Director and the Federal Project
Director.
The PM may delegate responsibilities to the Deputy Project Manager and/or other project
team members.
The DPM also reviews Memoranda of Understanding and other project documentation,
advising the Project Manager on risk management, ES&H, or other relevant issues.
7
4.3.3 APUL Project Engineer
The APUL Project Engineer is responsible for overall engineering coordination of the
design and fabrication phases of the project and works directly with the Level 2
Managers to achieve this. The Project Engineer is directly responsible to the APUL
Project Manager. In cooperation with them the Project Engineer works with the APUL
ES&H Coordinator to implement Fermilab’s policy of Integrated Safety Management
(ISM) in the project and resolve any ES&H issues that may arise. The Project Engineer
is also responsible for implementing quality assurance procedures and the Configuration
Management Plan and its associated change control procedures.
The APUL Documentation Coordinator also coordinates Quality Assurance issues and
maintains the APUL Quality Assurance Plan3 and other QA documentation, as discussed
in Section 7.1, reviews Memoranda of Understanding and SOW, and advises the Project
Manager on QA issues. The Documentation Coordinator prepares and maintains the
project risk management documentation, as discussed in Section 7.2. This includes
performing the risk matrix calculations and updating the documentation as necessary.
8
4.3.6 APUL Scheduler (Is this still the correct title, Project Controller
or something instead?)
The APUL Scheduler is responsible for project controls and earned value reporting. The
Scheduler maintains and updates the APUL Project cost and schedule plan and prepares
the schedule information for monthly reports and scheduled reviews, submitting them to
the APUL PM for approval and transmission. The Scheduler works with PM in
identifying schedule issues in a proactive manner in order to track and report deviations
from baseline schedules and costs as specified in Section 5. The Scheduler also assists
collaborators in preparing subproject schedules and collaborates with the Fermilab Office
of Project Management Oversight to develop project controls.
The Budget Officer also assists collaborators in preparing initial budget estimates and
collaborates with the Fermilab Office of Project Management Oversight to develop
project controls.
The Financial Management System (FMS) in use by Fermilab allows individual cost
codes to be established, where necessary. The Budget Officer has the responsibility for
establishing the proper cost codes. The FMS is also used to track and monitor such
expenses as charge-backs from other Divisions/Sections, and other Fermilab related
costs. At the successful completion of each project phase or WBS task, the Project
Manager or designated representative is required to verify that work was performed and
completed in accordance with acceptable standards before final payment is authorized by
the Business Services Section.
Level 2 Managers are assigned by the APUL Project Manager. The Project Manager may
make additional management support appointments, such as Level 3 managers or
subsystem coordinators, on an as-needed basis.
9
The primary responsibility of Level 2 managers is the planning and the coordination of
the work for the subsystem. In close consultation with the Project Management Team,
they develop the work plan, schedule, and budget for their individual subsystems. They
are responsible for implementing the plan and tracking its progress and use of resources.
They coordinate the personnel and facilities allocated to the subsystem.
Level 2 managers provide the Project Manager with monthly status reports. These reports
highlight progress of their subsystem toward the project goals and difficulties
encountered or anticipated. The report shall include a short discussion of technical
management relevant to their responsibilities and measure the progress of the subsystem
effort against the milestones of the subproject. Furthermore, it shall give an accounting
of the budgetary expenditures during the monthly period, highlighting items costing more
or less than expected.
Issues requiring consideration are brought to the attention of the PMG by the Project
Manager. For the purpose of their deliberations, the PMG may organize any reviews they
deem necessary. Once the CCB has examined the request for change, a recommendation
for appropriate actions is made to the Project Manager. Records of their decisions are
maintained in the APUL Document Database and changes to the Project are tracked in the
accounting system.
10
from the other laboratories are appointed in consultations with the Directors of those
laboratories. Other members, who have experience and expertise in the management and
design of accelerator construction projects, may be appointed by the Fermilab Director or
designee.
11
The MOU/SOW delegates certain responsibilities for management and related
activities as appropriate to each participating institution.
The MOU are updated as appropriate, generally through addenda or SOW.
The use of contingency is approved in accordance with Table Project Controls System.2.
Subsystem managers are responsible for requesting the use of contingency funds from the
Project Manager as soon as the need for such funds is discovered. These requirements
will naturally arise during the monthly reviews of expenditures for each subtask. Funds
not used in a subsystem are returned to the contingency.
12
changes of personnel assignments, or schedule impact are considered changes to the
project plan that may require authorization to implement.
Technical changes that affect more than one subproject but that do not diminish
performance must be approved by the Project Manager.
Technical changes that affect ES&H requirements or changes in scope that affect physics
capabilities require a Change Request to be submitted for consideration by the APUL
PMG and approved by the Fermilab Associate Director for Accelerators. Depending on
the importance of the scope change, the Associate Director for Accelerators may seek the
advice of the Technical Advisory Committee.
Changes that result in the delay of Level 3 milestones by six months or more require a
Change Request be submitted for consideration by the APUL PMG and approved by the
Fermilab Associate Director for Accelerators. The response to such a Change Request
may be to initiate a plan to reallocate resources to recover the schedule or rescheduling of
the milestone.
Any change that delays a Level 2 milestone must be approved by the FPD.
13
5.5.5 Change Control Summary (which of these two is more
appropriate? Perhaps OPMO can advise)
Table Project Controls System.2 summarizes the Fermilab change control thresholds and
responsibilities.
14
Associate DOE Federal Fermilab Fermilab Subproject
Director Project Associate Project Manager
OHEP (Level Director Director Manager (Level 5)
1) (Level 2) (Level 3) (Level 4)
Scope Any change in Any significant Major technical Related technical Minor technical
the KPPs as change to the changes that are changes to changes to a single
referenced in technical scope significant multiple subproject that does
PEP. (as described in departures from subprojects that not diminish
PEP) that affect the technical do not diminish performance
ES&H baseline. performance
requirements or Changes that
meeting Project affect ES&H.
Closeout Out-of-scope
definitions in changes to
PEP. upgrade physics
capabilities.
Schedule Any change Any change to a Any change that Any change that Any change that
that causes a Level 2 results in the results in the results in the delay
delay in CD-4 milestone > 1 delay of a Level delay of a Level of a Level 5
project month or a 3 Director’s 4 milestone by milestone by more
completion Level 1 milestone. more than one than one month
date . milestone < 3 month.
months.
Cost Any change in Any cumulative Increase in the Increase in the Increase in the cost
Total use of cost of a single cost of a single of a single item by
Estimated contingency of item by more item by more more than $25k.
Cost or Total > $1M. than $250k. than $100k.
Project Cost. Increase in the
Project base cost
exceeding $500k
during the
previous 12
months.
Table Project Controls System.2 Change control levels for the APUL Project.
5.6 Reporting
The APUL Project provides reports on a monthly basis to Fermilab and DOE
management. The objective of the monthly reports is to collect and integrate essential
information pertaining to the cost, schedule and performance of the project in order to aid
its monitoring and management. The monthly Project Report comprises information
submitted to the Project Manager in reports by the WBS Level 2 managers and
summarizes it in the context of the overall project status. The Level 2 managers submit
written reports to the Project Manager on a monthly basis, within two weeks following
the end of the subject month. These reports summarize the activities of the previous
month, describe activities planned for the upcoming month, and include comments and
concerns.
15
5.7 Reviews
The APUL Project will undergo a series of reviews to monitor the progress of the cost,
schedule, technical aspects and safety of the project.
16
6 Environment, Safety and Health
The design, construction, and testing of APUL equipment provided by Fermilab will be
performed in compliance with the standards in the Fermilab ES&H Manual, and all
applicable ES&H standards in the Laboratory’s “Work Smart Standards” set. In addition,
all related work, including work performed off-site, will be performed in compliance with
applicable federal, state and local regulations.
The Brookhaven Safety and Health Services Division (SHSD) provides ES&H support
for all activities at Brookhaven, including guidance on ES&H issues, environmental
monitoring and safety assessments.
17
6.2 ES&H Documentation
6.2.1 Environmental Considerations
Both Brookhaven and Fermilab have implemented an Environmental Management
Systems (EMS) as part of their Integrated ES&H Management Plans. The EMS
integrates environmental considerations into the planning and decision-making process,
with the aim of evaluating the environmental impact of actions and mitigating any
adverse effects. Compliance with the National Environmental Protection Act (NEPA) is
part of this system. The APUL Project submitted an Environmental Evaluation
Notification Form, on the basis of which a Categorical Exclusion was granted on [DATE
HERE].
7 Technical Considerations
7.1 Quality Assurance (assumption is tha BNL, FNAL have
separate QA plans, is this ok?)
All work on the APUL Project will be performed in compliance with the Quality
Assurance programs established at Fermilab and Brookhaven. The Fermilab Technical
Division and Brookhaven Superconducting Magnet Division have each developed a
Quality Assurance Plan (QAP) that describes how QA is implemented on the
project.Error: Reference source not found The major elements of the APUL QAPs
address the project’s management, performance and assessment. Each institution will be
expected to cover the following topics in their quality programs:
Document control; at a minimum applied to drawings, specifications and work
instructions
Design control; at a minimum to include holding technical design reviews at a
level appropriate to the risk of the work
18
Process control; at a minimum to include a system for identifying, recording and
tracking nonconformances to closure, as well as a system for control of measuring
and test equipment (i.e. calibration)
Assessments; it is expected that internal or external assessments will be
performed and documented to ensure that work is being performed according to
the defined quality program
The key QA management elements of the project are the QAP itself, the qualification and
training of personnel, the quality improvement process and documentation. Performance
elements include work processes, design, procurement and acceptance criteria. The
assessment elements include assessments by project management and from independent
sources. The implementation of each of these QA elements is described in the QAP.
Other risk management tools include, but are not limited to, project reviews, monthly
reports and the Level 2 Managers’ meeting. This meeting is held weekly and provides a
forum for identification of risks and discussion of risk handling strategies.
19
Specific project notes on design modifications are maintained in an assigned Value
Engineering category in the document database. The database allows for easy access,
review and updating by participants in the APUL Project.8
20
Appendices
The technical definition of project completion for APUL is summarized in Table APUL
Technical Scope (need agreement from DOE).3.
Table APUL Technical Scope (need agreement from DOE).3 Technical definition of APUL project
completion.
21
9 APUL Cost (need to populate table)
Table APUL Cost (need to populate table).4 presents the base cost for the APUL Project
TEC broken down by WBS, in AYM$, followed by the contingency. Other Project Costs
include detector R&D; these costs and their contingency are also shown. The Total
Project Cost is the sum of all these.
Table APUL Cost (need to populate table).4 Baseline cost of the APUL Project in $AYM.
22
10 APUL Schedule (more wild guesses)
This appendix sets out the schedule of DOE Critical Decisions for the APUL project.
These are listed in Table APUL Schedule (more wild guesses).5.
Table APUL Schedule (more wild guesses).5 DOE Critical Decisions for the APUL Project.
23
The major project milestones are listed in Table APUL Schedule (more wild guesses).6
(and the wildest guesses of all. Not good that all milestones are in 2012. Need more
work on project schedule)
Table APUL Schedule (more wild guesses).6 Level 1 and 2 milestones for the APUL Project. These
milestone dates include schedule contingency.
24
References (needs to be updated in its entirety. Should we
reference FRA EVMS procedures as well?)
25
1
MINERνA Project Team, MINERνA Document 583, March 22, 2006.
2
Eric W. Vaandering and Lynn Garren, BTeV Document Database Design and Interface, BTeV-doc-140 (2001).
3
MINERνA Quality Assurance Program, MINERνA Document 971, August 10, 2006.
4
Particle Physics Division Operating Manual, ES&H Reviews for Experiments, PPD_ESH_006, March 1, 2006.
5
Department of Energy, Project Management for the Acquisition of Capital Assets, DOE M 413.3-1 (2003).
6
MINERA Risk Management, MINERA Document 327, December 9, 2005.
7
MINERA Configuration Management, MINERA Document 326, December 9, 2005.
8
Value Management on the MINERA Project, MINERA Document 329, December 7, 2005.