You are on page 1of 3

ACTIVITY (WORK) SCHEDULE

A. Field Investigation and Study Items - Detailed Survey and Envireomental/Social Screening

Activities (Work) Bar Chart (Work Schedule)


No Months 1st
2nd 3rd 4th Remarks
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 Contract Signing for Consulting Service
2 Review and Study of Norms followed and design ctiteria etc.
2.1 Collection of related maps, Drawings and Reports
2.2 Collection of Information of existing infrastructure
2.3 Preparation of Design Criteria
2.4 Preparation of field report and Preliminary Design Report
Details of work: Detail Survey of Bridge and Geological,
3
Hydrologica, Environmental and Social Safeguard
3.1 Detailed Topographical Survey & Mapping
3.2 Geotechnical Study
3.3 Hydrological Study
3.4 Social Safeguard
4 Detailed Design of Bridge and Cost Estimate
4.1 Detailed Design of Bridge
4.2 Quantity Calculation, Rate Analysis& Cost Estimate
5 Draft Report Submission
6 Preparation of Detailed Project Report(DPR)
7 Final Report Submission

B. Completion and Submission of Report


Report Date Remarks
1.Inception Report Tuesday of 2nd Week
2. Iterim Progress Report
(a)First Status Report Thursday of 6th Week
(b) Second Status Report Thursday of 7th Week
3. Draft Report Monday of 14th Week
4. Final Report Friday of 16th Week
ACTIVITY (WORK) SCHEDULE
B. Completion and Submission of Reports - Design/Drawings, Cost Estimate and Report Production

No Activities Bar Chart (Work Schedule) Remarks


Months 1 2 3 4
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
6 Preparation and Submission of Report
6.1 Preparation of field report and Preliminary Design Report
6.2 Draft Report
6.3 Final Report