You are on page 1of 117

PERHITUNGAN VOLUME TANAH

NO. PAT LUAS GALIAN (M2) LUAS TIMBUNAN (M2) JARAK (M') VOLUME GALIAN (M3)

GC.14 90.72 2.75


15 2,456
GC.15 236.78 4.15
15 4,197
GC.16 322.8 3.19
15 4,478
GC.17 274.24 24.83
15 3,613.43
GC.18 207.550 55.610
15 3,092.10
GC.19 204.730 47.73
15 2,538.08
GC.20 133.68 63.41
15 1,579.65
GC.21 76.94 46.91
15 1,190.40
GC.22 81.78 61.35
15 990.23
GC.23 50.25 58.36
15 701.63
GC.24 43.30 83.25
15 446.93
GC.25 16.29 26.05
JUMLAH 25,283.33
VOLUME TIMBUNAN (M3)

51.75

55.05

210.15

603.30

775.05

833.55

827.40

811.95

897.83

1,062.08

819.75

6,947.85
18,335.48
DAFTAR ANALISA HARGA SATUAN
A.2.2.1. HARGA SATUAN PEKERJAAN PERSIAPAN

A.2.2.1.9. 1 M2 Pembersihan Lapangan dan Perataan


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.1000
Mandor L04 OH 0.0500

JUMLAH TENAGA KERJA


B. BAHAN

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.Pagar Str Pembuatan 1 M Pagar Sementara


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.200
Tukang L02 OH 0.400
Kepala Tukang L03 OH 0.020
Mandor L04 OH 0.020
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Dolken diameter 8 - 10 / 400 cm Btg 1.200
Semen / PC (40 Kg) kg 0.250
Seng Gelombang 0.25 mm 8 "(kaki) Lbr 1.200
Kayu Kelas IV M3 0.025
Pasir Beton M3 0.050
Paku Kayu kg 0.060

JUMLAH HARGA BAHAN


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.2.3.1. HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1. 1 M3 Galian Tanah Biasa Sedalam 1 M'


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.7500
Mandor L04 OH 0.0250

JUMLAH TENAGA KERJA


B. BAHAN

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.2.3.1.9. 1 M3 Urugan Kembali Bekas Galian


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.2500
Mandor L04 OH 0.0500

JUMLAH TENAGA KERJA


B. BAHAN

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.2.3.1.11 1 M3 Timbunan Tanah Didatangkan
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.3000
Mandor L04 OH 0.0100

JUMLAH TENAGA KERJA


B. BAHAN
Tanah Timbun M3 1.2000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

Analisa ijuk 1 M2 memasang Ijuk Peresapan


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.1500
Mandor L04 OH 0.0150

JUMLAH TENAGA KERJA


B. BAHAN
Ijuk kg 6.0000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.2.3.1.11. a 1 M3 Mengurug dengan Pasir Urug


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.3000
Mandor L04 OH 0.0100

JUMLAH TENAGA KERJA


B. BAHAN
Pasir Urug M3 1.2000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.2.3.1.11.b 1 M3 Mengurug dengan Pasir Kerikil
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.3000
Mandor L04 OH 0.0100

JUMLAH TENAGA KERJA


B. BAHAN
Kerikil M3 1.2000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.2.3.1.11.c 1 M3 Mengurug dengan Pasir Pasang


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.3000
Mandor L04 OH 0.0100

JUMLAH TENAGA KERJA


B. BAHAN
Pasir Pasang M3 1.2000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.2. 1 M3 Pasangan Batu Gunung/Belah Campuran 1SP : 4 PP
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.5000
Tukang L02 OH 0.7500
Kepala Tukang L03 OH 0.0750
Mandor L04 OH 0.0750
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah M3 1.2000
Semen Portland Kg 163.00
Pasir Pasang M3 0.5200
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.3.2.1.9 1 M3 Pasangan Batu Kosong ( Anstamping )
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.7800
Tukang L02 OH 0.3900
Kepala Tukang L03 OH 0.0390
Mandor L04 OH 0.0390
JUMLAH TENAGA KERJA
B. BAHAN
Batu Belah M3 1.2000
Pasir Urug M3 0.4320
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

Analisa EI-422 1 M3 Lps. Pond. Ag. Kls. B (LPB)


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.250
Tukang L02 OH -
Kepala Tukang L03 OH -
Mandor L04 OH 0.036
JUMLAH TENAGA KERJA
B. BAHAN
Agregat Kasar B M3 0.420
Agregat Halus C M3 0.240
Sirtu M4 0.540
JUMLAH HARGA BAHAN
C. PERALATAN
Wheel Loader Jam 0.0350
Dump Truck Jam 0.2300
Motor Grader Jam 0.0040
Tandem Roller Jam 0.0060
Water Tanker Jam 0.0210
Alat Bantu Ls 1.0000
JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.1.1. HARGA SATUAN PEKERJAAN BETON
A.4.1.1.8. MEMBUAT 1 M3 BETON MUTU f’c = 21.7 MPa (K-250). SLUMP (12 ± 2) CM. W/C = 0.56 READY M
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.6500
Tukang L02 OH 0.2750
Kepala Tukang L03 OH 0.0280
Mandor L04 OH 0.0830
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland Kg 384.0000
Pasir Beton Kg 692.0000
Kerikil (Maks 30 mm) Kg 1,039.0000
Air Liter 215.0000

JUMLAH HARGA BAHAN


C. PERALATAN
Vibrator Jam 0.0520
Pompa beton Jam 0.0520
Peralatan Lainnya Ls 1.0000
JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.1.1.7. MEMBUAT 1 M3 BETON MUTU f’c = 19.3 MPa (K-225). SLUMP (12 ± 2) CM. W/C = 0.58
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.6500
Tukang L02 OH 0.2750
Kepala Tukang L03 OH 0.0280
Mandor L04 OH 0.0830
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland Kg 371.00
Pasir Beton Kg 698.00
Kerikil (Maks 30 mm) Kg 1,047.00
Air Liter 215.00

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.1.1.5 MEMBUAT 1 M3 Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.6500
Tukang L02 OH 0.2750
Kepala Tukang L03 OH 0.0280
Mandor L04 OH 0.0830
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland Kg 326.0000
Pasir Beton Kg 760.0000
Kerikil (Maks 30 mm) Kg 1,029.0000
Air Liter 215.0000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.1.1.17.a 10 Kg Pembesian dengan Besi Polos


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0700
Tukang L02 OH 0.0700
Kepala Tukang L03 OH 0.0070
Mandor L04 OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Besi Beton Polos Kg 10.50
Kawat Beton Kg 0.15

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
Harga Satuan Pekerjaan untuk 1 Kg Besi =
A.4.1.1.17.b 10 Kg Pembesian dengan Besi ulir
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0700
Tukang L02 OH 0.0700
Kepala Tukang L03 OH 0.0070
Mandor L04 OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Besi Beton Polos Kg 10.50
Kawat Beton Kg 0.15

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
Harga Satuan Pekerjaan untuk 1 Kg Besi =

A.4.1.1.19 1 Kg Memasang Jaring Kawat Baja / Wire Mesh


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0250
Tukang L02 OH 0.0250
Kepala Tukang L03 OH 0.0020
Mandor L04 OH 0.0010
JUMLAH TENAGA KERJA
B. BAHAN
Kawat Wiremesh Kg 1.0200
Kawat Beton Kg 0.0500

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.1.1.20 1 M2 Memasang Bekisting Untuk Pondasi
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.5200
Tukang L02 OH 0.2600
Kepala Tukang L03 OH 0.0260
Mandor L04 OH 0.0260
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III M3 0.0400
Paku 5-12 cm Kg 0.3000
Minyak Bekisting Liter 0.1000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.1.1.21 1 M2 Memasang Bekisting Untuk Sloof


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.5200
Tukang L02 OH 0.2600
Kepala Tukang L03 OH 0.0260
Mandor L04 OH 0.0260
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III M3 0.0450
Paku 5-12 cm Kg 0.3000
Minyak Bekisting Liter 0.1000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.1.1.22. 1 M2 Pemasangan Bekisting Untuk Kolom
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.6600
Tukang L02 OH 0.3300
Kepala Tukang L03 OH 0.0330
Mandor L04 OH 0.0330
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III M3 0.040
Paku 5-12 cm Kg 0.400
Minyak Bekisting Liter 0.200
Balok Kayu Kelas II M3 0.015
Plywood 9 mm Lbr 0.350
Dolken Kayu 8-10 cm x 4 m Batang 2.000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.1.1.23 1 M2 Pemasangan Bekisting Untuk Balok


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.6600
Tukang L02 OH 0.3300
Kepala Tukang L03 OH 0.0330
Mandor L04 OH 0.0330
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III M3 0.0400
Paku 5-12 cm Kg 0.4000
Minyak Bekisting Liter 0.2000
Balok Kayu Kelas II M3 0.0180
Plywood 9 mm Lbr 0.3500
Dolken Kayu 8-10 cm x 4 m Batang 2.0000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.1.1.24 1 M2 Memasang Bekisting Untuk Plat Lantai
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.6600
Tukang L02 OH 0.3300
Kepala Tukang L03 OH 0.0330
Mandor L04 OH 0.0330
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III M3 0.0400
Paku 5-12 cm Kg 0.4000
Minyak Bekisting Liter 0.2000
Balok Kayu Kelas II M3 0.0150
Plywood 9 mm Lbr 0.3500
Dolken Kayu 8-10 cm x 4 m Batang 6.0000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.1.1.25 1 M2 Memasang Bekisting Untuk Dinding


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.6600
Tukang L02 OH 0.3300
Kepala Tukang L03 OH 0.0330
Mandor L04 OH 0.0330
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas III M3 0.0300
Paku 5-12 cm Kg 0.4000
Minyak Bekisting Liter 0.2000
Balok Kayu Kelas II M3 0.0200
Plywood 9 mm Lbr 0.3500
Dolken Kayu 8-10 cm x 4 m Batang 3.0000
Penjaga jarak / Spacer bh 4.0000
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
Pekerjaan Lain-lain (Membongkar Bekisting & Menyiram Beton)
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.0000

JUMLAH TENAGA KERJA


B. BAHAN

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

Analisa 1 1 M3 Pondasi Tapak 180x180x30


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.b Pembesian /Besi Ulir 153.691 Kg
A.4.1.1.20 Bekisting 2.19 M2 1 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 2 1 M3 Pondasi Tapak 250x150x30


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.b Pembesian /Besi Ulir 156.498 Kg
A.4.1.1.20 Bekisting 2.23 M2 1 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 3 1 M3 Pondasi Tapak 60x60x20


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 180.210 Kg
A.4.1.1.20 Bekisting 3.57 M2 1 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 4 1 M3 Sloof Beton Bertulang 30x40cm


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 49.512 Kg
A.4.1.1.17.b Pembesian /Besi Ulir 67.665 Kg
A.4.1.1.21 Bekisting 6.67 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan
Analisa 5 1 M3 Sloof Beton Bertulang 20x25cm
Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 147.658 Kg
A.4.1.1.17.b Pembesian /Besi Ulir - Kg
A.4.1.1.21 Bekisting 11.11 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 6 1 M3 Kolom Bertulang 40x50


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 48.423 Kg
A.4.1.1.17.b Pembesian /Besi Ulir 99.435 Kg
A.4.1.1.21 Bekisting 9.00 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 7 1 M3 Kolom Bertulang 40x40


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 52.461 Kg
A.4.1.1.17.b Pembesian /Besi Ulir 103.578 Kg
A.4.1.1.21 Bekisting 10.00 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 8 1 M3 Kolom Bertulang 25x25


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 128.716 Kg
A.4.1.1.17.b Pembesian /Besi Ulir - Kg
A.4.1.1.21 Bekisting 16.00 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 9 1 M3 Kolom Bertulang 13x13


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 271.330 Kg
A.4.1.1.17.b Pembesian /Besi Ulir - Kg
A.4.1.1.21 Bekisting 30.77 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan
Analisa 10 1 M3 Balok Bertulang 35x50
Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 43.165 Kg
A.4.1.1.17.b Pembesian /Besi Ulir 76.44 Kg
A.4.1.1.21 Bekisting 7.71 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 11 1 M3 Balok Bertulang 30x40


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 49.512 Kg
A.4.1.1.17.b Pembesian /Besi Ulir 111.47 Kg
A.4.1.1.21 Bekisting 9.17 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 12 1 M3 Balok Bertulang 25x30


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 58.061 Kg
A.4.1.1.17.b Pembesian /Besi Ulir 112.06 Kg
A.4.1.1.21 Bekisting 11.33 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 13 1 M3 Balok Bertulang 30x50


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 46.724 Kg
A.4.1.1.17.b Pembesian /Besi Ulir 89.18 Kg
A.4.1.1.21 Bekisting 8.67 M2 2 x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan

Analisa 14 1 M3 Plat Lantai


Analisa Uraian Pekerjaan Volume Satuan

A.4.1.1.8. Beton K 250 1 M3


A.4.1.1.17.a Pembesian /Besi Polos 93.193 Kg
A.4.1.1.17.b Pembesian /Besi Ulir - Kg
A.4.1.1.21 Bekisting 3.33 M2 1x pakai
Pekerjaan Lain-Lain 1 Ls

Jumlah
Harga Satuan
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.7. 1 M2 Pasangan Bata Merah tebal 1/2 Bata Campuran 1SP : 2PP
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.3000
Tukang L02 OH 0.1000
Kepala Tukang L03 OH 0.0200
Mandor L04 OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Batu Bata Bh 70.00
Semen Portland Kg 18.95
Pasir Pasang M3 0.038

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.4.1.9. 1 M2 Pasangan Bata Merah tebal 1/2 Bata Campuran 1SP : 4PP
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.3000
Tukang L02 OH 0.1000
Kepala Tukang L03 OH 0.0200
Mandor L04 OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Batu Bata Bh 70.00
Semen Portland Kg 11.50
Pasir Pasang M3 0.043

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.2. 1 M2 Plesteran 1SP : 2PP, Tebal 15 mm
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.3000
Tukang L02 OH 0.1500
Kepala Tukang L03 OH 0.0150
Mandor L04 OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland Kg 10.2240
Pasir Pasang M3 0.0200

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.4.2.4. 1 M2 Plesteran 1SP : 4PP, Tebal 15 mm
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.3000
Tukang L02 OH 0.1500
Kepala Tukang L03 OH 0.0150
Mandor L04 OH 0.0150
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland Kg 6.24
Pasir Pasang M3 0.024

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.4.2.27. 1 M2 Pemasangan Acian


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.2000
Tukang L02 OH 0.1000
Kepala Tukang L03 OH 0.0100
Mandor L04 OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
Semen Portland Kg 3.25

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.4.3. HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.35.a 1 M2 Pasangan Lantai Granit Ukuran 60 cm x 60 cm


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.7000
Tukang L02 OH 0.3500
Kepala Tukang L03 OH 0.0350
Mandor L04 OH 0.0350
JUMLAH TENAGA KERJA
B. BAHAN
Granit Uk 60 x60 M2 1.0000
Semen Portland Kg 10.0000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.5000
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.4.3.35.b 1 M2 Pasangan Lantai Keramik Anti Slip Ukuran 40 cm x 40 cm


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.7000
Tukang L02 OH 0.3500
Kepala Tukang L03 OH 0.0350
Mandor L04 OH 0.0350
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 40cm x 40 cm Bh 6.6800
Semen Portland Kg 10.4000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.6200
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.4.3.35.c 1 M2 Pasangan Lantai Keramik Anti Slip Ukuran 20 cm x 20 cm
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.7000
Tukang L02 OH 0.3500
Kepala Tukang L03 OH 0.0350
Mandor L04 OH 0.0350
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 40cm x 40 cm Bh 26.7500
Semen Portland Kg 10.4000
Pasir Pasang M3 0.0450
Semen Warna Kg 1.6200
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.4.3.54.a 1 M2 Pasangan Dinding Keramik Ukuran 20 cm x 40 cm


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.9000
Tukang L02 OH 0.4500
Kepala Tukang L03 OH 0.0450
Mandor L04 OH 0.0450
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 20cm x 40 cm Bh 13.7500
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen Warna Kg 1.9400
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.4.3.54.b 1 M2 Pasangan Dinding Batu Alam Ukuran 20 cm x 40 cm
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.9000
Tukang L02 OH 0.4500
Kepala Tukang L03 OH 0.0450
Mandor L04 OH 0.0450
JUMLAH TENAGA KERJA
B. BAHAN
Batu Alam 20 cm x 40 cm Bh 13.7500
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen Warna Kg 1.9400
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.4.3.53. 1 M2 Pasangan Dinding Keramik Ukuran 10 cm x 20 cm


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.9000
Tukang L02 OH 0.4500
Kepala Tukang L03 OH 0.0450
Mandor L04 OH 0.0450
JUMLAH TENAGA KERJA
B. BAHAN
Keramik 10cm x 20 cm Bh 53.0000
Semen Portland Kg 9.3000
Pasir Pasang M3 0.0180
Semen Warna Kg 2.7500
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.6.1.1 1 M3 Membuat dan Memasang Kusen pintu dan Kusen Jendela, Kayu Kelas I
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 7.0000
Tukang L02 OH 21.0000
Kepala Tukang L03 OH 2.1000
Mandor L04 OH 0.3500
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kelas I M3 1.1000
Paku Kayu Kg 1.2500
Lem Kayu Kg 1.0000
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.6.1.10 1 M2 Memasang Jalusi Kusen, Kayu Kelas I


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.6700
Tukang L02 OH 2.0000
Kepala Tukang L03 OH 0.2000
Mandor L04 OH 0.3350
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kelas I M3 0.0600
Paku Kayu Kg 0.1500

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.6.1.5 Pembuatan dan Pemasangan 1 M2 daun pintu panel, Kayu Kelas I
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.0000
Tukang L02 OH 3.0000
Kepala Tukang L03 OH 0.3000
Mandor L04 OH 0.0500
JUMLAH TENAGA KERJA
B. BAHAN
Papan kayu M3 0.0400
Lem kayu Kg 0.5000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.6.1.6 Pembuatan dan Pemasangan 1 M2 pintu dan jendela kaca, Kayu Kelas I
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.8000
Tukang L02 OH 2.4000
Kepala Tukang L03 OH 0.2400
Mandor L04 OH 0.0400
JUMLAH TENAGA KERJA
B. BAHAN
Papan kayu M3 0.0240
Lem kayu Kg 0.3000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.7.1. HARGA SATUAN PEKERJAAN CAT

A.4.7.1.10. 1 M2 Mengecat Bidang Tembok Baru


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0200
Tukang L02 OH 0.0630
Kepala Tukang L03 OH 0.0063
Mandor L04 OH 0.0030
JUMLAH TENAGA KERJA
B. BAHAN
Plamir Kg 0.10
Cat Dasar Tembok Kg 0.10
Cat Penutup Tembok Kg 0.26

JUMLAH HARGA BAHAN


C. PERALATAN
Roller/Kuas bh 0.0100

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.7.1.4 1 M2 Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar,2 x cat penutup)
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0700
Tukang L02 OH 0.0090
Kepala Tukang L03 OH 0.0060
Mandor L04 OH 0.0030
JUMLAH TENAGA KERJA
B. BAHAN
Cat Menie Kg 0.2000
Plamir Kayu Kg 0.1500
Cat dasar kayu Kg 0.1700
Cat kayu penutup Kg 0.2600
Kuas Bh 0.0100
Pengencer Liter 0.0300
Ampelas' Lembar 0.2000
JUMLAH HARGA BAHAN
C. PERALATAN
Roller/Kuas bh 0.0100

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.5.1.2. HARGA SATUAN PEKERJAAN ATAP

A.4.5.2.32. Pemasangan 1 M2 Atap Spandek


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.2000
Tukang L02 OH 0.1000
Kepala Tukang L03 OH 0.0100
Mandor L04 OH 0.0010
JUMLAH TENAGA KERJA
B. BAHAN
Atap genteng metal m2 1.02
Paku biasa Kg 0.20

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.5.2.36.a Pemasangan 1 M' Nok Seng Spandek


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.2500
Tukang L02 OH 0.1500
Kepala Tukang L03 OH 0.0150
Mandor L04 OH 0.0130
JUMLAH TENAGA KERJA
B. BAHAN
Nok Genteng metal M' 1.10
Paku Kg 0.05

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.6.1.14 1 M3 Memasang Konstruksi Kuda-Kuda, Kayu Kelas I


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 6.7000
Tukang L02 OH 20.1000
Kepala Tukang L03 OH 2.0100
Mandor L04 OH 0.3350
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kelas I M3 1.2000
Besi Strip Tebal 5 mm Kg 15.0000
Paku Kayu Kg 5.6000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.6.1.15 1 M3 Memasang Konstruksi Gordeng, Kayu Kelas II
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 2.4000
Tukang L02 OH 7.2000
Kepala Tukang L03 OH 0.7200
Mandor L04 OH 0.1200
JUMLAH TENAGA KERJA
B. BAHAN
Balok Kayu Kelas II M3 1.2000
Besi Strip Tebal 5 mm Kg 15.0000
Paku Kayu Kg 5.6000

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.6.1.21 1 M Memasang Listplank Uk. 3 x 20 Cm Kayu Kelas II


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.1000
Tukang L02 OH 0.1000
Kepala Tukang L03 OH 0.0100
Mandor L04 OH 0.0500
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas II M3 0.0088
Paku Kayu Kg 0.0600

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.6.1.20 1 M2 Memasang Rangka Langit-Langit (60 x 60) Cm, Kelas II


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.2000
Tukang L02 OH 0.3000
Kepala Tukang L03 OH 0.0300
Mandor L04 OH 0.0100
JUMLAH TENAGA KERJA
B. BAHAN
Kayu Kelas II M3 0.0163
Paku Kayu Kg 0.2500

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.4.5.1.5 1 M2 Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 6 mm
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.1000
Tukang L02 OH 0.1000
Kepala Tukang L03 OH 0.0100
Mandor L04 OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Multiplek 6 mm lbr 0.3750
Paku Kayu Kg 0.0300

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.1. Pemasangan 1 Bh Kloset Duduk/Monoblock
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 3.3000
Tukang L02 OH 1.1000
Kepala Tukang L03 OH 0.0100
Mandor L04 OH 0.1600
JUMLAH TENAGA KERJA
B. BAHAN
Kloset duduk Bh 1.00
Perlengkapan % 6%

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.5.1.1.2. Pemasangan 1 Bh Kloset Jongkok


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.0000
Tukang L02 OH 1.5000
Kepala Tukang L03 OH 0.1500
Mandor L04 OH 0.1600
JUMLAH TENAGA KERJA
B. BAHAN
Kloset Jongkok Bh 1.00
Semen Portland Kg 6.00
Pasir Pasang M3 0.0100
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.5.1.1.4. Pemasangan 1 Bh Urinoir
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.0000
Tukang L02 OH 1.0000
Kepala Tukang L03 OH 0.1000
Mandor L04 OH 0.0500
JUMLAH TENAGA KERJA
B. BAHAN
Urinoir Bh 1.00
Semen Portland Kg 6.00
Pasir Pasang M3 0.01
Perlengkapan % 30%
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.5.1.1.5. Pemasangan 1 Bh Wastafel


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 1.2000
Tukang L02 OH 1.4500
Kepala Tukang L03 OH 0.1500
Mandor L04 OH 0.0600
JUMLAH TENAGA KERJA
B. BAHAN
Wastafel Bh 1.00
Semen Portland Kg 6.00
Pasir Pasang M3 0.01
Perlengkapan % 12%
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.5.1.1.14. Pemasangan 1 Bh Floor Drain
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0100
Tukang L02 OH 0.1000
Kepala Tukang L03 OH 0.0100
Mandor L04 OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Floor Drain Bh 1.00

JUMLAH HARGA BAHAN


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.5.1.1.19. Pemasangan 1 Bh Kran diameter 1/2" atau 3/4"


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0100
Tukang L02 OH 0.4000
Kepala Tukang L03 OH 0.0400
Mandor L04 OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Kran air Bh 1.00
Sealtape Bh 0.0250
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.5.1.1.19.a Pemasangan 1 Bh Shower Spray/Jet Shower
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0100
Tukang L02 OH 0.4000
Kepala Tukang L03 OH 0.0400
Mandor L04 OH 0.0050
JUMLAH TENAGA KERJA
B. BAHAN
Shower Spray Bh 1.00
Sealtape Bh 0.0250
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.5.1.1.25. Pemasangan 1 M' Pipa PVC tipe AW diameter 1/2"


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0360
Tukang L02 OH 0.0600
Kepala Tukang L03 OH 0.0060
Mandor L04 OH 0.0020
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC 1/2" M' 1.20
Perlengkapan % 35%
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.5.1.1.26. Pemasangan 1 M' Pipa PVC tipe AW diameter 3/4"


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0360
Tukang L02 OH 0.0600
Kepala Tukang L03 OH 0.0060
Mandor L04 OH 0.0020
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC 3/4" M' 1.20
Perlengkapan % 35%
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.5.1.1.27. Pemasangan 1 M' Pipa PVC tipe AW diameter 1"
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0360
Tukang L02 OH 0.0600
Kepala Tukang L03 OH 0.0060
Mandor L04 OH 0.0020
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC 1" M' 1.20
Perlengkapan % 35%
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.5.1.1.29. Pemasangan 1 M' Pipa PVC tipe AW diameter 2"


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0540
Tukang L02 OH 0.0900
Kepala Tukang L03 OH 0.0090
Mandor L04 OH 0.0030
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC 2" M' 1.20
Perlengkapan % 35%
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.5.1.1.31. Pemasangan 1 M' Pipa PVC tipe AW diameter 3"


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0810
Tukang L02 OH 0.1350
Kepala Tukang L03 OH 0.0135
Mandor L04 OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC 3" M' 1.200
Perlengkapan % 35%
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
A.5.1.1.32. Pemasangan 1 M' Pipa PVC tipe AW diameter 4"
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.0810
Tukang L02 OH 0.1350
Kepala Tukang L03 OH 0.0135
Mandor L04 OH 0.0040
JUMLAH TENAGA KERJA
B. BAHAN
Pipa PVC 4" M' 1.200
Perlengkapan % 35%
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

Analisa 15 15 M2 Pagar Kawat Harmonika


No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 4.0000
Tukang L02 OH 5.0000
Kepala Tukang L03 OH 1.0000
Mandor L04 OH 0.0520
JUMLAH TENAGA KERJA
B. BAHAN
Besi Siku L40.40.3 Btg 2.75
Kawat Harmonika Galvanis lubang 43x43 dia kawat 3.4mm M2 15.000
Pipa Galvanis 3" Btg 2.200
Kawat las Ls 1.000

JUMLAH HARGA BAHAN


C. PERALATAN
Peralatan Pengelasan Ls 1.0000

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
AHSP PU P.12.a Pemasangan Gebalan Rumput
No. Uraian Kode Satuan Koefesien

A. TENAGA
Pekerja L01 OH 0.075
Tukang L02 OH -
Kepala Tukang L03 OH -
Mandor L04 OH 0.010
JUMLAH TENAGA KERJA
B. BAHAN
Lempengan /Gebalan Rumput M2 1.000
JUMLAH HARGA BAHAN
C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A+B+C)
E. Overhead & Provit 10%
F. Harga Satuan Pekerjaan
AN

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 8,200.00
110,000.00 5,500.00
-
-
MLAH TENAGA KERJA 13,700.00

-
-
-
MLAH HARGA BAHAN -

-
-
-
MLAH HARGA ALAT -

13,700.00
XD 1,370.00
15,070.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 16,400.00
100,000.00 40,000.00
129,000.00 2,580.00
110,000.00 2,200.00
MLAH TENAGA KERJA 61,180.00

50,000.00 60,000.00
1,347.50 336.88
72,000.00 86,400.00
3,300,000.00 82,500.00
185,000.00 9,250.00
23,000.00 1,380.00

MLAH HARGA BAHAN 239,866.88

-
-
-
MLAH HARGA ALAT -

301,046.88
XD 30,104.69
331,151.56
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 61,500.00
110,000.00 2,750.00

MLAH TENAGA KERJA 64,250.00

-
-
-
MLAH HARGA BAHAN -

-
-
-
MLAH HARGA ALAT -

64,250.00
XD 6,425.00
70,675.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 20,500.00
110,000.00 5,500.00
-
-
MLAH TENAGA KERJA 26,000.00

-
-
-
MLAH HARGA BAHAN -

-
-
-
MLAH HARGA ALAT -

26,000.00
XD 2,600.00
28,600.00
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 24,600.00
110,000.00 1,100.00
-
-
MLAH TENAGA KERJA 25,700.00

69,000.00 82,800.00
-
-
MLAH HARGA BAHAN 82,800.00

-
-
MLAH HARGA ALAT -

108,500.00
XD 10,850.00
119,350.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 12,300.00
110,000.00 1,650.00
-
-
MLAH TENAGA KERJA 13,950.00

18,000.00 108,000.00
-
-
MLAH HARGA BAHAN 108,000.00

-
-
MLAH HARGA ALAT -

121,950.00
XD 12,195.00
134,145.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 24,600.00
110,000.00 1,100.00
-
-
MLAH TENAGA KERJA 25,700.00

103,000.00 123,600.00
-
-
MLAH HARGA BAHAN 123,600.00

-
-
MLAH HARGA ALAT -

149,300.00
XD 14,930.00
164,230.00
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 24,600.00
110,000.00 1,100.00
-
-
MLAH TENAGA KERJA 25,700.00

250,000.00 300,000.00
-
-
MLAH HARGA BAHAN 300,000.00

-
-
MLAH HARGA ALAT -

325,700.00
XD 32,570.00
358,270.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 24,600.00
110,000.00 1,100.00
-
-
MLAH TENAGA KERJA 25,700.00

185,000.00 222,000.00
-
-
MLAH HARGA BAHAN 222,000.00

-
-
MLAH HARGA ALAT -

247,700.00
XD 24,770.00
272,470.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 123,000.00
100,000.00 75,000.00
129,000.00 9,675.00
110,000.00 8,250.00
MLAH TENAGA KERJA 215,925.00

196,000.00 235,200.00
1,347.50 219,642.50
185,000.00 96,200.00
MLAH HARGA BAHAN 551,042.50

-
-
-
MLAH HARGA ALAT -

766,967.50
XD 76,696.75
843,664.25
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 63,960.00
100,000.00 39,000.00
129,000.00 5,031.00
110,000.00 4,290.00
MLAH TENAGA KERJA 112,281.00

196,000.00 235,200.00
103,000.00 44,496.00
MLAH HARGA BAHAN 279,696.00

-
-
-
MLAH HARGA ALAT -

391,977.00
XD 39,197.70
431,174.70

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 20,490.85
100,000.00 -
129,000.00 -
110,000.00 3,926.82
MLAH TENAGA KERJA 24,417.67

290,000.00 121,800.00
261,000.00 62,640.00
120,000.00 64,800.00
MLAH HARGA BAHAN 184,440.00

250,000.00 8,750.00
150,000.00 34,500.00
250,000.00 1,000.00
220,000.00 1,320.00
150,000.00 3,150.00
2,000.00 2,000.00
MLAH HARGA ALAT 50,720.00

259,577.67
XD 25,957.77
285,535.44
. W/C = 0.56 READY MIX
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 135,300.00
100,000.00 27,500.00
129,000.00 3,612.00
110,000.00 9,130.00
MLAH TENAGA KERJA 175,542.00

1,347.50 517,440.00
132.14 91,442.86
214.81 223,192.59
150.00 32,250.00

MLAH HARGA BAHAN 864,325.45

65,000.00 3,380.00
275,000.00 14,300.00
50,000.00 50,000.00
MLAH HARGA ALAT 67,680.00

1,107,547.45
XD 110,754.74
1,218,302.19

. W/C = 0.58
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 135,300.00
100,000.00 27,500.00
129,000.00 3,612.00
110,000.00 9,130.00
MLAH TENAGA KERJA 175,542.00

1,347.50 499,922.50
132.14 92,235.71
214.81 224,911.11
150.00 32,250.00

MLAH HARGA BAHAN 849,319.33

-
-
MLAH HARGA ALAT -

1,024,861.33
XD 102,486.13
1,127,347.46
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 135,300.00
100,000.00 27,500.00
129,000.00 3,612.00
110,000.00 9,130.00
MLAH TENAGA KERJA 175,542.00

1,347.50 439,285.00
132.14 100,428.57
214.81 221,044.44
150.00 32,250.00

MLAH HARGA BAHAN 793,008.02

-
-
MLAH HARGA ALAT -

968,550.02
XD 96,855.00
1,065,405.02

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 5,740.00
100,000.00 7,000.00
129,000.00 903.00
110,000.00 440.00
MLAH TENAGA KERJA 14,083.00

13,400.00 140,700.00
22,000.00 3,300.00

MLAH HARGA BAHAN 144,000.00

-
-
MLAH HARGA ALAT -

158,083.00
XD 15,808.30
173,891.30
17,389.13
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 5,740.00
100,000.00 7,000.00
129,000.00 903.00
110,000.00 440.00
MLAH TENAGA KERJA 14,083.00

15,000.00 157,500.00
22,000.00 3,300.00

MLAH HARGA BAHAN 160,800.00

-
-
MLAH HARGA ALAT -

174,883.00
XD 17,488.30
192,371.30
19,237.13

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 2,050.00
100,000.00 2,500.00
129,000.00 258.00
110,000.00 110.00
MLAH TENAGA KERJA 4,918.00

18,566.78 18,938.11
22,000.00 1,100.00

MLAH HARGA BAHAN 20,038.11

-
-
MLAH HARGA ALAT -

24,956.11
XD 2,495.61
27,451.72
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 42,640.00
100,000.00 26,000.00
129,000.00 3,354.00
110,000.00 2,860.00
MLAH TENAGA KERJA 74,854.00

4,300,000.00 172,000.00
23,000.00 6,900.00
19,000.00 1,900.00

MLAH HARGA BAHAN 180,800.00

-
MLAH HARGA ALAT -

255,654.00
XD 25,565.40
281,219.40

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 42,640.00
100,000.00 26,000.00
129,000.00 3,354.00
110,000.00 2,860.00
MLAH TENAGA KERJA 74,854.00

4,300,000.00 193,500.00
23,000.00 6,900.00
19,000.00 1,900.00

MLAH HARGA BAHAN 202,300.00

-
MLAH HARGA ALAT -

277,154.00
XD 27,715.40
304,869.40
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 54,120.00
100,000.00 33,000.00
129,000.00 4,257.00
110,000.00 3,630.00
MLAH TENAGA KERJA 95,007.00

4,300,000.00 172,000.00
23,000.00 9,200.00
19,000.00 3,800.00
5,800,000.00 87,000.00
218,000.00 76,300.00
50,000.00 100,000.00

MLAH HARGA BAHAN 448,300.00

-
MLAH HARGA ALAT -

543,307.00
XD 54,330.70
597,637.70

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 54,120.00
100,000.00 33,000.00
129,000.00 4,257.00
110,000.00 3,630.00
MLAH TENAGA KERJA 95,007.00

4,300,000.00 172,000.00
23,000.00 9,200.00
19,000.00 3,800.00
5,800,000.00 104,400.00
218,000.00 76,300.00
50,000.00 100,000.00

MLAH HARGA BAHAN 465,700.00

-
MLAH HARGA ALAT -

560,707.00
XD 56,070.70
616,777.70
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 54,120.00
100,000.00 33,000.00
129,000.00 4,257.00
110,000.00 3,630.00
MLAH TENAGA KERJA 95,007.00

4,300,000.00 172,000.00
23,000.00 9,200.00
19,000.00 3,800.00
5,800,000.00 87,000.00
218,000.00 76,300.00
50,000.00 300,000.00

MLAH HARGA BAHAN 648,300.00

-
MLAH HARGA ALAT -

743,307.00
XD 74,330.70
817,637.70

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 54,120.00
100,000.00 33,000.00
129,000.00 4,257.00
110,000.00 3,630.00
MLAH TENAGA KERJA 95,007.00

4,300,000.00 129,000.00
23,000.00 9,200.00
19,000.00 3,800.00
5,800,000.00 116,000.00
218,000.00 76,300.00
50,000.00 150,000.00
1,000.00 4,000.00
MLAH HARGA BAHAN 488,300.00

-
MLAH HARGA ALAT -

583,307.00
XD 58,330.70
641,637.70
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 82,000.00

MLAH TENAGA KERJA 82,000.00

MLAH HARGA BAHAN -

-
MLAH HARGA ALAT -

82,000.00
XD 8,200.00
90,200.00

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
19,237.13 2,956,571.38
281,219.40 616,182.95
90,200.00 90,200.00

4,881,256.53
4,881,256.53

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
19,237.13 3,010,565.04
281,219.40 628,056.66
90,200.00 90,200.00

4,947,123.90
4,947,123.90

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 3,133,689.67
281,219.40 1,004,890.66
90,200.00 90,200.00

5,447,082.52
5,447,082.52

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 860,971.93
19,237.13 1,301,680.34
152,434.70 1,016,231.33
90,200.00 90,200.00

4,487,385.80
4,487,385.80
Harga Satuan Jumlah Harga
Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 2,567,639.48
19,237.13 -
152,434.70 1,693,718.89
90,200.00 90,200.00

5,569,860.56
5,569,860.56

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 842,031.40
19,237.13 1,912,847.43
298,818.85 2,689,369.65
90,200.00 90,200.00

6,752,750.68
6,752,750.68

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 912,254.29
19,237.13 1,992,549.41
298,818.85 2,988,188.50
90,200.00 90,200.00

7,201,494.40
7,201,494.40

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 2,238,258.28
19,237.13 -
298,818.85 4,781,101.60
90,200.00 90,200.00

8,327,862.07
8,327,862.07
Harga Satuan Jumlah Harga
Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 4,718,200.91
19,237.13 -
298,818.85 9,194,426.15
90,200.00 90,200.00

15,221,129.26
15,221,129.26
Harga Satuan Jumlah Harga
Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 750,596.15
19,237.13 1,470,420.14
308,388.85 2,378,999.70
90,200.00 90,200.00

5,908,518.18
5,908,518.18

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 860,971.93
19,237.13 2,144,362.70
308,388.85 2,826,897.79
90,200.00 90,200.00

7,140,734.61
7,140,734.61

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 1,009,637.18
19,237.13 2,155,748.70
308,388.85 3,495,073.63
90,200.00 90,200.00

7,968,961.70
7,968,961.70

Harga Satuan Jumlah Harga


Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 812,488.95
19,237.13 1,715,490.16
308,388.85 2,672,703.37
90,200.00 90,200.00

6,509,184.67
6,509,184.67
Harga Satuan Jumlah Harga
Rp. Rp.

1,218,302.19 1,218,302.19
17,389.13 1,620,542.72
19,237.13 -
817,637.70 2,725,459.00
90,200.00 90,200.00

5,654,503.92
5,654,503.92
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 24,600.00
100,000.00 10,000.00
129,000.00 2,580.00
110,000.00 1,650.00
MLAH TENAGA KERJA 38,830.00

880.00 61,600.00
1,347.50 25,535.13
185,000.00 7,030.00

MLAH HARGA BAHAN 94,165.13

-
-
MLAH HARGA ALAT -

132,995.13
XD 13,299.51
146,294.64
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 24,600.00
100,000.00 10,000.00
129,000.00 2,580.00
110,000.00 1,650.00
MLAH TENAGA KERJA 38,830.00

880.00 61,600.00
1,347.50 15,496.25
185,000.00 7,955.00

MLAH HARGA BAHAN 85,051.25

-
-
MLAH HARGA ALAT -

123,881.25
XD 12,388.13
136,269.38

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 24,600.00
100,000.00 15,000.00
129,000.00 1,935.00
110,000.00 1,650.00
MLAH TENAGA KERJA 43,185.00

1,347.50 13,776.84
185,000.00 3,700.00

MLAH HARGA BAHAN 17,476.84

-
-
MLAH HARGA ALAT -

60,661.84
XD 6,066.18
66,728.02
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 24,600.00
100,000.00 15,000.00
129,000.00 1,935.00
110,000.00 1,650.00
MLAH TENAGA KERJA 43,185.00

1,347.50 8,408.40
185,000.00 4,440.00

MLAH HARGA BAHAN 12,848.40

-
-
MLAH HARGA ALAT -

56,033.40
XD 5,603.34
61,636.74

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 16,400.00
100,000.00 10,000.00
129,000.00 1,290.00
110,000.00 1,100.00
MLAH TENAGA KERJA 28,790.00

1,347.50 4,379.38

MLAH HARGA BAHAN 4,379.38

-
-
MLAH HARGA ALAT -

33,169.38
XD 3,316.94
36,486.31
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 57,400.00
100,000.00 35,000.00
129,000.00 4,515.00
110,000.00 3,850.00
MLAH TENAGA KERJA 100,765.00

290,000.00 290,000.00
1,347.50 13,475.00
185,000.00 8,325.00
4,660.00 6,990.00
MLAH HARGA BAHAN 318,790.00

-
-
MLAH HARGA ALAT -

419,555.00
XD 41,955.50
461,510.50

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 57,400.00
100,000.00 35,000.00
129,000.00 4,515.00
110,000.00 3,850.00
MLAH TENAGA KERJA 100,765.00

13,666.67 91,293.33
1,347.50 14,014.00
185,000.00 8,325.00
4,660.00 7,549.20
MLAH HARGA BAHAN 121,181.53

-
-
MLAH HARGA ALAT -

221,946.53
XD 22,194.65
244,141.19
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 57,400.00
100,000.00 35,000.00
129,000.00 4,515.00
110,000.00 3,850.00
MLAH TENAGA KERJA 100,765.00

2,720.00 72,760.00
1,347.50 14,014.00
185,000.00 8,325.00
4,660.00 7,549.20
MLAH HARGA BAHAN 102,648.20

-
-
MLAH HARGA ALAT -

203,413.20
XD 20,341.32
223,754.52

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 73,800.00
100,000.00 45,000.00
129,000.00 5,805.00
110,000.00 4,950.00
MLAH TENAGA KERJA 129,555.00

6,800.00 93,500.00
1,347.50 12,531.75
185,000.00 3,330.00
4,660.00 9,040.40
MLAH HARGA BAHAN 118,402.15

-
-
MLAH HARGA ALAT -

247,957.15
XD 24,795.72
272,752.87
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 73,800.00
100,000.00 45,000.00
129,000.00 5,805.00
110,000.00 4,950.00
MLAH TENAGA KERJA 129,555.00

31,666.67 435,416.67
1,347.50 12,531.75
185,000.00 3,330.00
4,660.00 9,040.40
MLAH HARGA BAHAN 460,318.82

-
-
MLAH HARGA ALAT -

589,873.82
XD 58,987.38
648,861.20

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 73,800.00
100,000.00 45,000.00
129,000.00 5,805.00
110,000.00 4,950.00
MLAH TENAGA KERJA 129,555.00

2,000.00 106,000.00
1,347.50 12,531.75
185,000.00 3,330.00
4,660.00 12,815.00
MLAH HARGA BAHAN 134,676.75

-
-
MLAH HARGA ALAT -

264,231.75
XD 26,423.18
290,654.93
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 574,000.00
100,000.00 2,100,000.00
129,000.00 270,900.00
110,000.00 38,500.00
MLAH TENAGA KERJA 2,983,400.00

6,500,000.00 7,150,000.00
23,000.00 28,750.00
35,000.00 35,000.00
MLAH HARGA BAHAN 7,213,750.00

-
MLAH HARGA ALAT -

10,197,150.00
XD 1,019,715.00
11,216,865.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 54,940.00
100,000.00 200,000.00
129,000.00 25,800.00
110,000.00 36,850.00
MLAH TENAGA KERJA 317,590.00

6,500,000.00 390,000.00
23,000.00 3,450.00
-
MLAH HARGA BAHAN 393,450.00

-
MLAH HARGA ALAT -

711,040.00
XD 71,104.00
782,144.00
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 82,000.00
100,000.00 300,000.00
129,000.00 38,700.00
110,000.00 5,500.00
MLAH TENAGA KERJA 426,200.00

6,500,000.00 260,000.00
35,000.00 17,500.00
-
MLAH HARGA BAHAN 277,500.00

-
MLAH HARGA ALAT -

703,700.00
XD 70,370.00
774,070.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 65,600.00
100,000.00 240,000.00
129,000.00 30,960.00
110,000.00 4,400.00
MLAH TENAGA KERJA 340,960.00

25,000.00 600.00
298,750.00 89,625.00
-
MLAH HARGA BAHAN 90,225.00

-
MLAH HARGA ALAT -

431,185.00
XD 43,118.50
474,303.50
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 1,640.00
100,000.00 6,300.00
129,000.00 812.70
110,000.00 330.00
MLAH TENAGA KERJA 9,082.70

25,000.00 2,500.00
28,000.00 2,800.00
28,000.00 7,280.00

MLAH HARGA BAHAN 12,580.00

27,000.00 270.00
-
MLAH HARGA ALAT 270.00

21,932.70
XD 2,193.27
24,125.97

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 5,740.00
100,000.00 900.00
129,000.00 774.00
110,000.00 330.00
MLAH TENAGA KERJA 7,744.00

32,000.00 6,400.00
21,000.00 3,150.00
67,000.00 11,390.00
67,000.00 17,420.00
27,000.00 270.00
27,000.00 810.00
4,200.00 840.00
MLAH HARGA BAHAN 40,280.00

20,000.00 200.00
-
MLAH HARGA ALAT 200.00

48,224.00
XD 4,822.40
53,046.40
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 16,400.00
100,000.00 10,000.00
129,000.00 1,290.00
110,000.00 110.00
MLAH TENAGA KERJA 27,800.00

95,000.00 96,900.00
23,000.00 4,600.00
-
-
MLAH HARGA BAHAN 101,500.00

-
MLAH HARGA ALAT -

129,300.00
XD 12,930.00
142,230.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 20,500.00
100,000.00 15,000.00
129,000.00 1,935.00
110,000.00 1,430.00
MLAH TENAGA KERJA 38,865.00

45,000.00 49,500.00
23,000.00 1,150.00
-
-
MLAH HARGA BAHAN 50,650.00

-
MLAH HARGA ALAT -

89,515.00
XD 8,951.50
98,466.50

Harga Satuan Jumlah Harga


Rp. Rp.
82,000.00 549,400.00
100,000.00 2,010,000.00
129,000.00 259,290.00
110,000.00 36,850.00
MLAH TENAGA KERJA 2,855,540.00

6,500,000.00 7,800,000.00
18,000.00 270,000.00
23,000.00 128,800.00
-
MLAH HARGA BAHAN 8,198,800.00

-
MLAH HARGA ALAT -

11,054,340.00
XD 1,105,434.00
12,159,774.00
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 196,800.00
100,000.00 720,000.00
129,000.00 92,880.00
110,000.00 13,200.00
MLAH TENAGA KERJA 1,022,880.00

5,800,000.00 6,960,000.00
18,000.00 270,000.00
23,000.00 128,800.00
-
MLAH HARGA BAHAN 7,358,800.00

-
MLAH HARGA ALAT -

8,381,680.00
XD 838,168.00
9,219,848.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 8,200.00
100,000.00 10,000.00
129,000.00 1,290.00
110,000.00 5,500.00
MLAH TENAGA KERJA 24,990.00

4,300,000.00 37,840.00
23,000.00 1,380.00
-
MLAH HARGA BAHAN 39,220.00

-
MLAH HARGA ALAT -

64,210.00
XD 6,421.00
70,631.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 16,400.00
100,000.00 30,000.00
129,000.00 3,870.00
110,000.00 1,100.00
MLAH TENAGA KERJA 51,370.00

5,800,000.00 94,540.00
23,000.00 5,750.00
-
MLAH HARGA BAHAN 100,290.00

-
MLAH HARGA ALAT -

151,660.00
XD 15,166.00
166,826.00
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 8,200.00
100,000.00 10,000.00
129,000.00 1,290.00
110,000.00 550.00
MLAH TENAGA KERJA 20,040.00

138,000.00 51,750.00
23,000.00 690.00
-
MLAH HARGA BAHAN 52,440.00

-
MLAH HARGA ALAT -

72,480.00
XD 7,248.00
79,728.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 270,600.00
100,000.00 110,000.00
129,000.00 1,290.00
110,000.00 17,600.00
MLAH TENAGA KERJA 399,490.00

2,500,000.00 2,500,000.00
2,500,000.00 150,000.00

MLAH HARGA BAHAN 2,650,000.00

-
-
MLAH HARGA ALAT -

3,049,490.00
XD 304,949.00
3,354,439.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 82,000.00
100,000.00 150,000.00
129,000.00 19,350.00
110,000.00 17,600.00
MLAH TENAGA KERJA 268,950.00

435,000.00 435,000.00
1,347.50 8,085.00
185,000.00 1,850.00
MLAH HARGA BAHAN 444,935.00

-
-
MLAH HARGA ALAT -

713,885.00
XD 71,388.50
785,273.50
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 82,000.00
100,000.00 100,000.00
129,000.00 12,900.00
110,000.00 5,500.00
MLAH TENAGA KERJA 200,400.00

1,300,000.00 1,300,000.00
1,347.50 8,085.00
185,000.00 1,850.00
1,300,000.00 390,000.00
MLAH HARGA BAHAN 1,699,935.00

-
-
MLAH HARGA ALAT -

1,900,335.00
XD 190,033.50
2,090,368.50

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 98,400.00
100,000.00 145,000.00
129,000.00 19,350.00
110,000.00 6,600.00
MLAH TENAGA KERJA 269,350.00

415,000.00 415,000.00
1,347.50 8,085.00
185,000.00 1,850.00
415,000.00 49,800.00
MLAH HARGA BAHAN 474,735.00

-
-
MLAH HARGA ALAT -

744,085.00
XD 74,408.50
818,493.50
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 820.00
100,000.00 10,000.00
129,000.00 1,290.00
110,000.00 550.00
MLAH TENAGA KERJA 12,660.00

25,000.00 25,000.00

MLAH HARGA BAHAN 25,000.00

-
-
MLAH HARGA ALAT -

37,660.00
XD 3,766.00
41,426.00

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 820.00
100,000.00 40,000.00
129,000.00 5,160.00
110,000.00 550.00
MLAH TENAGA KERJA 46,530.00

75,000.00 75,000.00
5,000.00 125.00
MLAH HARGA BAHAN 75,125.00

-
-
MLAH HARGA ALAT -

121,655.00
XD 12,165.50
133,820.50
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 820.00
100,000.00 40,000.00
129,000.00 5,160.00
110,000.00 550.00
MLAH TENAGA KERJA 46,530.00

250,000.00 250,000.00
5,000.00 125.00
MLAH HARGA BAHAN 250,125.00

-
-
MLAH HARGA ALAT -

296,655.00
XD 29,665.50
326,320.50

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 2,952.00
100,000.00 6,000.00
129,000.00 774.00
110,000.00 220.00
MLAH TENAGA KERJA 9,946.00

6,000.00 7,200.00
6,000.00 2,100.00
MLAH HARGA BAHAN 9,300.00

-
-
MLAH HARGA ALAT -

19,246.00
XD 1,924.60
21,170.60

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 2,952.00
100,000.00 6,000.00
129,000.00 774.00
110,000.00 220.00
MLAH TENAGA KERJA 9,946.00

6,833.33 8,200.00
6,833.33 2,391.67
MLAH HARGA BAHAN 10,591.67

-
-
MLAH HARGA ALAT -

20,537.67
XD 2,053.77
22,591.43
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 2,952.00
100,000.00 6,000.00
129,000.00 774.00
110,000.00 220.00
MLAH TENAGA KERJA 9,946.00

10,166.67 12,200.00
10,166.67 3,558.33
MLAH HARGA BAHAN 15,758.33

-
-
MLAH HARGA ALAT -

25,704.33
XD 2,570.43
28,274.77

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 4,428.00
100,000.00 9,000.00
129,000.00 1,161.00
110,000.00 330.00
MLAH TENAGA KERJA 14,919.00

21,500.00 25,800.00
21,500.00 7,525.00
MLAH HARGA BAHAN 33,325.00

-
-
MLAH HARGA ALAT -

48,244.00
XD 4,824.40
53,068.40

Harga Satuan Jumlah Harga


Rp. Rp.
82,000.00 6,642.00
100,000.00 13,500.00
129,000.00 1,741.50
110,000.00 440.00
MLAH TENAGA KERJA 22,323.50

28,333.33 34,000.00
28,333.33 9,916.67
MLAH HARGA BAHAN 43,916.67

-
-
MLAH HARGA ALAT -

66,240.17
XD 6,624.02
72,864.18
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 6,642.00
100,000.00 13,500.00
129,000.00 1,741.50
110,000.00 440.00
MLAH TENAGA KERJA 22,323.50

45,833.33 55,000.00
45,833.33 16,041.67
MLAH HARGA BAHAN 71,041.67

-
-
MLAH HARGA ALAT -

93,365.17
XD 9,336.52
102,701.68

Harga Satuan Jumlah Harga


Rp. Rp.

82,000.00 328,000.00
100,000.00 500,000.00
129,000.00 129,000.00
110,000.00 5,720.00
MLAH TENAGA KERJA 962,720.00

110,000.00 302,500.00
105,000.00 1,575,000.00
850,000.00 1,870,000.00
20,000.00 20,000.00

MLAH HARGA BAHAN 3,767,500.00

150,000.00 150,000.00

MLAH HARGA ALAT 150,000.00

4,880,220.00
XD 488,022.00
5,368,242.00
1 M2 = 357,882.80
Harga Satuan Jumlah Harga
Rp. Rp.

82,000.00 6,150.00
100,000.00 -
129,000.00 -
110,000.00 1,100.00
MLAH TENAGA KERJA 7,250.00

37,000.00 37,000.00
MLAH HARGA BAHAN 37,000.00

-
-
MLAH HARGA ALAT -

44,250.00
XD 4,425.00
48,675.00
REKAPITULASI
BILL OF QUANTITY (BOQ)

PEKERJAAN : PEMBANGUNAN STADION MINI (LAP.SEPAK BOLA DAN FASILITAS ATLETIK)


SUMBER DANA : APBD
LOKASI : KAB.ACEH BESAR

No Uraian Pekerjaan Jumlah Harga (Rp)

I PEKERJAAN PERSIAPAN DAN PEMATANGAN LAHAN 1,239,523,207.74

II PEKERJAAN TRIBUN PENONTON 4,735,931,293.88


A. PEKERJAAN TANAH 166,989,793.63
B. PEKERJAAN PONDASI 965,768,878.45
C. PEKERJAAN BETON 2,160,214,003.57
D. PEKERJAAN PASANGAN & PLESTERAN 162,427,025.15
E. PEKERJAAN ATAP 656,032,085.39
F. PEKERJAAN ALUMINIUM, BESI DAN PVC 159,080,000.00
G. PEKERJAAN PENUTUP LANTAI DAN DINDING 304,881,514.07
H. PEKERJAAN LANGIT-LANGIT 54,000,000.00
I. PEKERJAAN ELECTRICAL DAN MEKANIKAL 25,865,000.00
J. PEKERJAAN PENGECATAN 37,812,150.26
K. PEKERJAAN SANITASI 42,860,843.37

III PEKERJAAN PAGAR 1,545,416,667.98


A. PEKERJAAN TANAH 11,710,416.67
B. PEKERJAAN PONDASI DAN SLOOF 497,749,176.21
C. PEKERJAAN PAGAR 1,035,957,075.10

IV PEMBUATAN LAPANGAN BOLA KAKI 1,955,263,145.59


A. PEKERJAAN TANAH 184,714,315.50
B. PEKERJAAN DRAINASE 1,291,114,555.09
C. PEKERJAAN LAPANGAN 479,434,275.00

V PEMBUATAN LINTASAN ATLETIK 9,121,799,431.21


A. PEKERJAAN TANAH 538,666,953.63
B. PEKERJAAN BETON 1,099,223,308.39
C. PEKERJAAN LINTASAN ATLETIK 7,136,716,326.89
D. PEKERJAAN PENDUKUNG PERALATAN DAN PERLENGKAPAN ATLETIK 347,192,842.31

JUMLAH HARGA 18,597,933,746.41


PPN 10% 1,859,793,374.64
JUMLAH 20,457,727,121.05
PEMBULATAN 20,457,700,000.00
Terbilang: Dua puluh milyar empat ratus lima puluh tujuh juta tujuh ratus ribu rupiah
BIL OF QUANTITY (BOQ)
PEKERJAAN : PEMBANGUNAN STADION MINI (LAP.SEPAK BOLA DAN FASILITAS ATLETIK)
LOKASI : KAB.ACEH BESAR

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7

I PEKERJAAN PERSIAPAN DAN PEMATANGAN LAHAN


1 Pasang bowplank/pengukuran 1.000 Ls Taksir 12,000,000.00 12,000,000.00
2 Direksi Keet/barak kerja 1.000 Sewa Taksir 15,000,000.00 15,000,000.00
3 Mobilisasi dan Demobilisasi 1.000 Ls Taksir 30,000,000.00 30,000,000.00
4 Papan nama proyek 1.000 Ls Taksir 450,000.00 450,000.00
5 Keselamatan pekerja dan P3K 1.000 Ls Taksir 3,000,000.00 3,000,000.00
6 Pagar pengaman sementara Proyek/ Seng Gelombang BJLS 0.25 190.000 m A.Pagar Str 331,151.56 62,918,796.88
mm 8" Rangka Kayu Bagian Depan dan Samping Rencana Stadion
7 Air Kerja 1.000 Ls Taksir 5,000,000.00 5,000,000.00
8 Listrik Kerja 1.000 Ls Taksir 7,000,000.00 7,000,000.00
9 Penyiapan Lahan 0.000
- Tebang Tebas Pohon,semak dan lain-lain 19,368.000 m2 Taksir 3,000.00 58,104,000.00
- Cut and Fill lahan 25,283.325 m3 Taksir 19,000.00 480,383,175.00
- Timbunan Tanah Didatangkan 1,936.800 m3 A.2.3.1.11 119,350.00 231,157,080.00
- Dinding Penahan Tanah
Tapak 50 x 50 cm tiang pagar dan Tiang Sokong 3.33 m3 Analisa 3 5,447,082.52 18,156,941.72
Pedestal 25x25cm tiang pagar dan Tiang Sokong 10.42 m3 Analisa 8 8,327,862.07 86,748,563.23
Lantai Kerja K175 16.00 m3 A.4.1.1.5 1,065,405.02 17,046,480.28
Pasangan pondasi batu gunung 180.00 m3 A.3.2.1.2. 843,664.25 151,859,565.00
Sloof beton S1 (20 x 25) cm 10.00 m3 Analisa 5 5,569,860.56 55,698,605.64
10 Quality control 1.00 Ls Taksir 2,000,000.00 2,000,000.00
11 Pembersihan Terakhir 1.00 Ls Taksir 3,000,000.00 3,000,000.00
Jumlah 1,239,523,207.74
II PEKERJAAN TRIBUN PENONTON
A. PEKERJAAN TANAH
1 Galian tanah Pondasi 1,010.726 m3 A.2.3.1.1. 70,675.00 71,433,024.71
2 Urugan kembali galian pondasi 336.909 m3 A.2.3.1.9. 28,600.00 9,635,583.10
3 Urugan tanah timbun dalam bangunan 406.500 m3 A.2.3.1.11 119,350.00 48,515,775.00
4 Urugan pasir di bawah pondasi 35.367 m3 A.2.3.1.11. a 164,230.00 5,808,322.41
5 Lapisan pasir bawah lantai 101.625 m3 A.2.3.1.11. a 164,230.00 16,689,873.75
6 Pasangan Batu Bata 1 PC : 2 PS/Trasram tangga teras 53.288 m2 A.4.4.1.7. 146,294.64 7,795,675.50
7 Plesteran 1 PC : 2 PS 106.575 m2 A.4.4.2.2. 66,728.02 7,111,539.16
Jumlah 166,989,793.63
B. PEKERJAAN PONDASI
1 Tapak / Poor Pile 180 x 180 cm 104.98 m3 Analisa 1 4,881,256.53 512,414,785.44
2 Tapak / Poor Pile 250 x 150 (Pondasi Tangga) 1.13 m3 Analisa 2 4,947,123.90 5,565,514.39
3 Pedestal K1 (40/50) cm 48.88 m3 Analisa 6 6,752,750.68 330,074,453.40
4 Pedestal K2(40/40) cm 1.50 m3 Analisa 7 7,201,494.40 10,831,047.58
5 Pasangan Batu Kosong ( Anstamping ) Dibawah Pondasi Tapak 67.75 m3 A.3.2.1.9 431,174.70 29,212,301.51
6 Lantai Kerja Dibawah Pondasi batu Gunung 14.70 m3 A.4.1.1.5 1,065,405.02 15,661,453.76
7 Pasangan pondasi batu gunung 73.500 m3 A.3.2.1.2. 843,664.25 62,009,322.38
Jumlah 965,768,878.45
C. PEKERJAAN BETON
1 Cor Rabat Beton K.175 (Dibawah Lantai Keramik) 67.750 m3 A.4.1.1.5 1,065,405.02 72,181,189.93
2 Sloof beton S1 (30 x 40) cm 51.360 m3 Analisa 4 4,487,385.80 230,472,134.76
3 Kolom K1 (40/50) cm 69.152 m3 Analisa 6 6,752,750.68 466,966,215.26
4 Kolom K2(40/40) cm 2.912 m3 Analisa 7 7,201,494.40 20,970,751.69
5 Balok B1 ( 35 x 50 ) cm 31.360 m3 Analisa 10 5,908,518.18 185,291,130.13
6 Balok B2 (30 x 50 ) cm 29.400 m3 Analisa 13 6,509,184.67 191,370,029.34
7 Balok B3 ( 25 x 30 ) cm 2.400 m3 Analisa 12 7,968,961.70 19,125,508.09
8 Balok B4 (30x40)cm 5.280 m3 Analisa 11 7,140,734.61 37,703,078.77
8 Plat Lantai T. 30 cm 152.400 m3 Analisa 14 5,654,503.92 861,746,396.84
9 Tangga tempat duduk Tribun 7.280 m3 Analisa 14 5,654,503.92 41,164,788.51
10 Tangga Akses 2.600 m3 Analisa 14 5,654,503.92 14,701,710.18
10 Kolom Praktis 1.217 m3 Analisa 9 15,221,129.26 18,521,070.08
Jumlah 2,160,214,003.57
D. PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan batu bata trasram 1 PC : 2 PS /dinding toilet 145.90 m2 A.4.4.1.7. 146,294.64 21,344,387.61
2 Pasangan batu bata 1 PC : 4 PS 468.560 m2 A.4.4.1.9. 136,269.38 63,850,378.35
3 Plasteran 1 PC : 2 PS 291.80 m2 A.4.4.2.2. 66,728.02 19,471,237.40
4 Plasteran 1 PC : 4 PS 937.12 m2 A.4.4.2.4. 61,636.74 57,761,021.79
Jumlah 162,427,025.15
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7
E. PEKERJAAN ATAP
1 Rangka dan sokongan kuda-kuda
- Rangka Atap Kuda -kuda Tribun besi Siku L 40.40.3 676.48 m2 Taksir 350,000.00 236,768,000.00
- Rangka Atap Teras Rangka Baja ringan 45.90 m2 Taksir 200,000.00 9,180,000.00
- Sopi-sopi/kerawang /tolak Angin diteras 9.20 m2 Taksir 750,000.00 6,900,000.00
2 Gording
- Besi Holow 40x60x2 mm fin cat 966.40 m Taksir 35,000.00 33,824,000.00
- Pemasangan dan Pengelasan + Pengait 966.40 m Taksir 15,000.00 14,496,000.00
3 Tiang kuda-kuda
Tiang pipa gip 4'' Tingg 600 cm terpasang 16.00 Buah Taksir 1,800,000.00 28,800,000.00
Tiang pipa gip 4'' Tingg 370 cm terpasang 16.00 Buah Taksir 1,200,000.00 19,200,000.00
Tiang pipa gip 4'' Tingg 310 cm terpasang 16.00 Buah Taksir 850,000.00 13,600,000.00
Plat tumpuan tiang + angkur 48.00 Buah Taksir 600,000.00 28,800,000.00
4 Ikatan angin besi polos dia 10 mm + pasang 570 cm per ikatan 60.00 btg Taksir 95,000.00 5,700,000.00
5 Penutup Atap
Seng Spandek 0.40 mm 722.38 m2 A.4.5.2.32. 142,230.00 102,744,107.40
Lisplang Alumunium Composite Panel 71.60 m2 Taksir 1,300,000.00 93,080,000.00
Talang Plat Alumunium 60.40 m Taksir 850,000.00 51,340,000.00
6 Pipa Pembuang 159.20 m2 A.5.1.1.31. 72,864.18 11,599,977.99
Jumlah 656,032,085.39
F. PEKERJAAN ALUMINIUM, BESI DAN PVC
1 Pintu Type P1 (Lengkap Acessories/Handle,Engsel,Kunci) 2.00 Unit Taksir 4,000,000.00 8,000,000.00
2 Pintu Type P2 (Lengkap Acessories/Engsel ,Pacok,Kunci) 2.00 Unit Taksir 1,500,000.00 3,000,000.00
3 Pintu Type P3 fiber 10.00 Unit Taksir 300,000.00 3,000,000.00
4 Jendela Type J1 (Lengkap Acessories) 4.00 Unit Taksir 2,000,000.00 8,000,000.00
5 Ventilasi Type V1 (Lengkap Acessories) 8.00 Unit Taksir 300,000.00 2,400,000.00
6 Reiling Tribun dan Tangga T 1m pakai Pipa gip 1,5'' fin cat 207.20 m Taksir 650,000.00 134,680,000.00
Jumlah 159,080,000.00
G. PEKERJAAN PENUTUP LANTAI DAN DINDING
Penutup lantai
1 Lantai Keramik Ukuran 40 x 40 cm termasuk Tribun 1,073.60 m² A.4.4.3.35.b 244,141.19 262,109,978.01
2 Lantai Keramik Ukuran 20 x 20 cm (anti slip) 40.00 m² A.4.4.3.35.c 223,754.52 8,950,180.80
Penutup Dinding
3 Dinding Keramik Ukuran 20 x 40 cm 124.00 m² A.4.4.3.54.a 272,752.87 33,821,355.26
Jumlah 304,881,514.07
H. PEKERJAAN LANGIT-LANGIT
1 Rangka Furring Holow 360.00 m2 Taksir 80,000.00 28,800,000.00
2 Pemasangan Plafond Gibsum 9 mm 360.00 m2 Taksir 70,000.00 25,200,000.00
Jumlah 54,000,000.00
I. PEKERJAAN ELECTRICAL DAN MEKANIKAL
1 MCB 2.00 Unit Taksir 750,000.00 1,500,000.00
2 Box Panel 1.00 Unit Taksir 500,000.00 500,000.00
3 Lampu Downlight 14.00 Buah Taksir 40,000.00 560,000.00
4 Lampu Hemat Energi 14.00 Buah Taksir 30,000.00 420,000.00
5 Saklar Tunggal 5.00 Buah Taksir 35,000.00 175,000.00
6 Saklar Ganda 2.00 Buah Taksir 35,000.00 70,000.00
7 Stop Kontak 4.00 Buah Taksir 35,000.00 140,000.00
8 Kabel NYM 2,5 1.00 Ls Taksir 7,500,000.00 7,500,000.00
9 Penangkal Petir 1.00 Ls Taksir 15,000,000.00 15,000,000.00
Jumlah 25,865,000.00
J. PEKERJAAN PENGECATAN
1 Cat tembok 1,207.28 m2 A.4.7.1.10. 24,125.97 29,126,801.06
2 Cat plafond 360.00 m2 A.4.7.1.10. 24,125.97 8,685,349.20
Jumlah 37,812,150.26
K. PEKERJAAN SANITASI
1 Memasang Closet Jongkok 8 buah A.5.1.1.2. 785,273.50 6,282,188.00
2 Urinoir 8 buah A.5.1.1.4. 2,090,368.50 16,722,948.00
3 Pipa Air kotor PVC 3"/acesoris/instalasi 54 m1 A.5.1.1.31. 72,864.18 3,934,665.90
4 Pipa Air bersih 3/4"/acesoris/instalasi 68 m1 A.5.1.1.26. 22,591.43 1,536,217.47
5 Fooldrain 10 buah A.5.1.1.14. 41,426.00 414,260.00
6 Kran 8 buah A.5.1.1.19. 133,820.50 1,070,564.00
7 bak fiber 6 buah Taksir 150,000.00 900,000.00
8 Pembuatan Septiktank 3 buah Taksir 3,000,000.00 9,000,000.00
9 Pembuatan Peresapan 3 buah Taksir 1,000,000.00 3,000,000.00
Jumlah 42,860,843.37
III PEKERJAAN PAGAR
A. PEKERJAAN TANAH
1 Galian tanah Pondasi 146.000 m3 A.2.3.1.1. 70,675.00 10,318,550.00
2 Urugan kembali galian pondasi 48.667 m3 A.2.3.1.9. 28,600.00 1,391,866.67
Jumlah 11,710,416.67
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7
B. PEKERJAAN PONDASI DAN SLOOF
1 Tapak 50 x 50 cm tiang pagar dan Tiang Sokong 15.21 m3 Analisa 3 5,447,082.52 82,841,046.61
2 Pedestal 25x25cm tiang pagar dan Tiang Sokong 11.41 m3 Analisa 8 8,327,862.07 94,989,676.73
3 Lantai Kerja K175 36.50 m3 A.4.1.1.5 1,065,405.02 38,887,283.14
4 Pasangan pondasi batu gunung 182.50 m3 A.3.2.1.2. 843,664.25 153,968,725.63
5 Sloof beton S1 (20 x 25) cm 22.81 m3 Analisa 5 5,569,860.56 127,062,444.11
Jumlah 497,749,176.21
C. PEKERJAAN PAGAR
1 Pintu Penonton Rangka GIP 3", Kawat Harmonika + Assesoris 8.000 Buah Taksir 3,500,000.00 28,000,000.00
lubang 43x43 dia kawat 3.4mm Ukuran 150 cm x220 cm x 2 daun

2 Pintu Mobilisasi Rangka GIP 3", Kawat Harmonika + Assesoris 1.000 Buah Taksir 4,400,000.00 4,400,000.00
lubang 43x43 dia kawat 3.4mm Ukuran 150 cm x300cm x 2 daun

3 Pagar Rangka GIP 3"dan Besi siku L 40.40.3,8 Kawat Harmonika + 2,273.250 m2 Analisa 15 357,882.80 813,557,075.10
Assesoris lubang 43x43 dia kawat 3.4mm
4 Tiang Sokong GIP 3" 152.000 btg Taksir 1,250,000.00 190,000,000.00
Jumlah 1,035,957,075.10
IV PEMBUATAN LAPANGAN BOLA KAKI
A. PEKERJAAN TANAH
1 Pemerataan dan Pemadatan Lapangan 7,150.000 m2 Taksir 21,000.00 150,150,000.00
2 Galian tanah Untuk Peresapan 489.060 m3 A.2.3.1.1. 70,675.00 34,564,315.50
Jumlah 184,714,315.50
B. PEKERJAAN DRAINASE
1 Drainase Dalam Area Lapangan
- Pipa utama PVC 6 '' ( sudah di lobang 10 mm) terpasang 626.40 m Taksir 368,333.33 230,724,000.00
- Pipa sirip PVC 4 '' ( sudah di lobang 10 mm) terpasang 1,152.00 m Taksir 59,583.33 68,640,000.00
- Kerikil Lapisan Setelah Ijuk 240.08 m3 A.2.3.1.11.b 358,270.00 86,014,894.68
- Ijuk Lapisan Pipa Utama dan Sirip 2,703.17 m2 Analisa ijuk 134,145.00 362,616,471.36
2 Drainase /Saluran( Luar Lapangan /Samping dalam Lintasan )
- Galian tanah 179.10 m3 A.2.3.1.1. 28,600.00 5,122,260.00
- Pasir Urug Dibawah Saluran 11.94 m3 A.2.3.1.11. a 164,230.00 1,960,906.20
- Cor Dinding Saluran K175 95.52 m3 A.4.1.1.5 1,065,405.02 101,767,487.27
- Mal /Cetakan Dinding Saluran 2X pakai 477.60 m2 A.4.1.1.25 320,818.85 153,223,082.76
- Penutup Saluran /Grill Besi 380.00 m Taksir 350,000.00 133,000,000.00
- Pipa Pembuang 4 " Kelua Area Stadion 159.20 m A.5.1.1.32. 102,701.68 16,350,107.99
3 Drainase /Saluran( Luar Lintasan /Samping Pagar Dalam )
- Galian tanah 90.00 m3 A.2.3.1.1. 28,600.00 2,574,000.00
- Pasir Urug Dibawah Saluran 6.00 m3 A.2.3.1.11. a 164,230.00 985,380.00
- Cor Dinding Saluran K175 48.00 m3 A.4.1.1.5 1,065,405.02 51,139,440.84
- Mal /Cetakan Dinding Saluran 2X pakai 240.00 m2 A.4.1.1.25 320,818.85 76,996,524.00
Jumlah 1,291,114,555.09
C. PEKERJAAN LAPANGAN
1 Urugan Pasir di atas Lapangan 5 cm 357.500 m3 A.2.3.1.11.c 272,470.00 97,408,025.00
2 Penanaman Lempeng Rumput 7,150.000 m2 AHSP PU P.12.a 48,675.00 348,026,250.00
3 Pengecatan Garis Garis Lapangan 1.000 Ls Taksir 10,000,000.00 10,000,000.00
4 Pengadaan Gawang Goal Standar 2.000 buah Taksir 12,000,000.00 24,000,000.00
Jumlah 479,434,275.00
V PEMBUATAN LINTASAN ATLETIK
A. PEKERJAAN TANAH
1 Penyiapan Badan Jalan/Lintasan 4,267.88 m2 12,000.00 51,214,560.00
2 Pondasi Lintasan/ lapisan Agregat Base B 1,707.15 m3 Analisa EI-422 285,535.44 487,452,393.63
Jumlah 538,666,953.63
B. PEKERJAAN BETON
1 Mal /Cetakan Pengecoran 2x Pakai 168.80 m2 A.4.1.1.25 320,818.85 54,154,221.88
2 Pemasangan Wiremesh M6 Pemasangan Besi WireMesh Ø 6mm 13,102.39 kg A.4.1.1.19 27,451.72 359,683,209.43
(Standar Pabrikasi)
3 Pemasangan Plastik Cor dibawah beton 4,267.88 m2 Taksir 10,000.00 42,678,800.00

4 Cor Beton K250 pakai ready Mix 426.79 m3 A.4.1.1.8. 1,218,302.19 519,956,757.08
5 Kerb beton Pembatas Lintasan 840.00 m Taksir 75,000.00 63,000,000.00
6 Finishing Level Lintasan Yang Sudah Dicor 4,267.88 m2 Taksir 14,000.00 59,750,320.00
Jumlah 1,099,223,308.39
C. PEKERJAAN LINTASAN ATLETIK
1 Pengadaan dan pemasangan lapisan sintetik t=13 mm (standar 4,267.88 m2 Analisa Khusus 1 1,633,397.00 6,971,142,388.36
IAAF)

2 Pengecatan Garis Lintasan Bahan Polyuerthane 2,107.00 m Analisa Khusus 2 78,582.79 165,573,938.53
Jumlah 7,136,716,326.89
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT ANALISA
(Rp) (Rp)
1 2 3 4 5 6 7
D. PEKERJAAN PENDUKUNG PERALATAN DAN PERLENGKAPAN ATLETIK
1 Pondasi papan lompat Jauh dan Lompat jangkit 12.00 set Analisa Khusus 3 7,062,915.15 84,754,981.81
2 Papan Tumpuan Lompat jauh 6.00 Bh Analisa Khusus 4 10,291,900.00 61,751,400.00
3 Bak Tumpuan Loncat Galah 2.00 Bh Analisa Khusus 5 4,661,897.00 9,323,794.00
4 Ring Besi Untuk Cakram dan Martil 1.00 Bh Analisa Khusus 7 20,605,982.50 20,605,982.50
5 Ring Besi Untuk Tolak Peluru 2.00 Bh Analisa Khusus 8 9,805,692.00 19,611,384.00
6 Almunium curb 400.00 M' Analisa Khusus 10 312,100.00 124,840,000.00
7 Pondasi dan gawang Pada Bak Air untuk Lari Halang rintang 1.00 Bh Analisa Khusus 9 26,305,300.00 26,305,300.00
Jumlah 347,192,842.31
DAFTAR HARGA UPAH DAN BAHAN KAB. ACEH BESAR
Pekerjaan : PEMBANGUNAN STADION MINI (LAP.SEPAK BOLA DAN FASILITAS ATLETIK)

Lokasi : KAB.ACEH BESAR

Harga
No. Uraian Upah/Bahan Satuan
Rp.

A. UPAH
1 L01 Pekerja OH 82,000.00
2 L02 Tukang OH 100,000.00
3 L03 Kepala Tukang OH 129,000.00
4 L04 Mandor OH 110,000.00
5 Instalator Lintasan Atletik OH 250,000.00
6 Pembatu Instalator OH 85,000.00
7 Tenaga Ahli Equiment Atletik OH 200,000.00

B. ALAT
1 Vibrator Jam 65,000.00
2 Pompa beton Jam 275,000.00

C. BAHAN
1 Kayu Balok 5/7 M3 4,300,000.00
2 Paku 2" - 3" Kg 23,000.00
3 Kayu Papan M3 4,300,000.00
4 Pasir Urug M3 103,000.00
5 Semen Portland 40kg Kg 53,900.00
6 Semen Portland 40kg Kg 1,347.50
7 Pasir Pasang M3 185,000.00
8 Pasir Pasang Kg 13,214.29
9 Pasir Beton M3 185,000.00
10 Pasir Beton Kg 132.14
11 Batu gunung/belah M3 196,000.00
10 Kerikil Biasa Untuk Peresapan M3 250,000.00
12 Kerikil /batu pecah (Maks 30 mm) M3 290,000.00
13 Kerikil/batu pecah (Maks 30 mm) Kg 214.81
14 Agregat Kelas B M3 290,000.00
15 Agregat Kelas C M3 261,000.00
15 Sirtu M3 120,000.00
16 Tanah Timbun M3 69,000.00
17 Air Liter 150.00
18 Besi Beton Polos Kg 13,400.00
19 Besi Beton Ulir Kg 15,000.00
20 Besi Siku L40.40.3,8 Kg 110,000.00
21 Kawat Beton Kg 22,000.00
22 Kawat Harmonika Galvanis lubang 43x43 dia kawat 3.4mm M2 105,000.00
23 WireMesh Ø 6mm (Standar Pabrikasi) M2 57,000.00
24 WireMesh Ø 6mm (Standar Pabrikasi) Kg 18,566.78
25 Paku 5-10 cm Kg 23,000.00
26 Minyak Bekisting Liter 19,000.00
27 Kayu Kelas I M3 6,500,000.00
28 Kayu Kelas II M3 5,800,000.00
Harga
No. Uraian Upah/Bahan Satuan
Rp.
29 Kayu Kelas III M3 4,300,000.00
Harga
No. Uraian Upah/Bahan Satuan
Rp.
30 Kayu Kelas IV M3 3,300,000.00
31 Besi Strip Tebal 5 mm Kg 18,000.00
32 Multiplek 9 mm Lembar 218,000.00
33 Multiplek 6 mm Lembar 138,000.00
34 Dolken Kayu (sembarang keras) 8-10 cm x 4 m Batang 50,000.00
35 Kloset duduk lengkap asesoris TOTO Bh 2,500,000.00
36 Kloset Jongkok Bh 435,000.00
37 Urinoir Keramik Bh 1,300,000.00
38 Wastafel lengkap asesoris Bh 415,000.00
39 Floor Drain Bh 25,000.00
40 Stop Kran Bh 75,000.00
41 Bak Mandi fibre glass, uk. Besar Bh 250,000.00
42 Sealtape Bh 5,000.00
43 Seng gelombang Lbr 72,000.00
44 Seng plat Lbr 65,000.00
45 Jet Shower Buah 250,000.00
46 Plamur Kg 25,000.00
47 Cat dasar Kg 28,000.00
48 Cat Penutup Kg 28,000.00
49 Cat Menie Kg 32,000.00
50 Plamir kayu Kg 21,000.00
51 Cat Dasar kayu Kg 67,000.00
52 Cat Penutup kayu Kg 67,000.00
53 Pengecer /tiner Liter 27,000.00
54 Amplase Lembar 4,200.00
55 Kuas bh 27,000.00
56 Seng Spandek 0.4 mm M2 95,000.00
57 Nok genteng metal M' 45,000.00
58 Pipa PVC 1/2" M' 6,000.00
59 Pipa PVC 3/4" M' 6,833.33
60 Pipa PVC 1" M' 10,166.67
61 Pipa PVC 2" M' 21,500.00
62 Pipa PVC 3" M' 28,333.33
63 Pipa PVC 4" M' 45,833.33
64 Pipa PVC 6" M' 283,333.33
64 Pipa Galvanis 3" Btng 850,000.00
65 Pipa Galvanis 4" Btng 1,200,000.00
66 Skrup fixer bh 3,000.00
67 Sealant Kg 180,000.00
68 Batu bata bh 880.00
69 Keramik Lantai 40cm x 40 cm bh 13,666.67
70 Granit Lantai 60 cm x 60 cm anti gores M2 290,000.00
71 Keramik Lantai 20 cm x20 cm bh 2,720.00
72 Keramik Dinding 20cm x 40 cm bh 6,800.00
73 Keramik 10cm x 20 cm bh 2,000.00
74 Batu Alam bh 31,666.67
75 Semen warna Kg 4,660.00
76 Shower Spray toto THX 20 NBW Bh 300,000.00
77 Lem pipa Liter 160,000.00
78 Lem kayu kg 35,000.00
79 Lempengan Rumput m2 37,000.00
80 Kunci Pintu Bh 154,000.00
81 Engsel Pintu Pasang 20,000.00
82 Engsel Jendela Pasang 20,000.00
Harga
No. Uraian Upah/Bahan Satuan
Rp.
83 Pacok Jendela Bh 18,200.00
84 Tarikan Jendela Bh 8,000.00
85 Hak Angin Steenless Bh 19,000.00
86 Lampu TL 2 X 36 Watt termasuk cover Bh 420,000.00
87 Lampu HE 45 Watt Bh 53,000.00
88 Lampu HE 14 Watt Bh 35,000.00
89 Kabel NYA 2.5 Rol 442,750.00
90 Saklar Tunggal stara Panasonic Bh 29,000.00
91 Saklar Ganda stara Panasonic Bh 43,000.00
92 Stop Kontak stara Panasonic Bh 27,000.00
93 Eksosfans Bh 800,000.00
94 Ijuk Kg 18,000.00
95 Kaca Polos 5 mm M2 155,000.00
Bahan Khusus Atletik
1 Cat Polyurethane Kg 144,375.00
2 PU Adhesive Kg 130,360.00
3 Shockpad 10 mm m2 275,100.00
4 Seal coat Kg 217,140.00
5 PU wear coat Kg 298,750.00
6 Granule / EPDM Kg 97,020.00
SEWA ALAT BERAT
1 Wheel Loader Jam 250,000.00
2 Dump Truck Jam 150,000.00
3 Motor Grader Jam 250,000.00
4 Tandem Roller Jam 220,000.00
5 Water Tanker Jam 150,000.00
pengurangan K1 1 0.33 2
2 0.99 2
3 1.65 2
4 2.31 2
5 2.97 2
6 3.63 2
7 4.29 2
8 4.95 2
9 5.61 2
10 6.27 2
11 6.93 2
0.66
1.98
3.3
4.62
5.94
7.26
8.58
9.9
11.22
12.54
13.86
79.86
Berat Besi (kg/m)
6 0.222
7 0.302
8 0.395
10 0.617
12 0.888
14 1.208
16 1.578
18 1.998
19 2.226
20 2.466
21 2.719
22 2.984

PERHITUNGAN BERAT TULANGAN / M3 BETON

Besi Bangunan Gudang

1 Tapak 180x180
D14
b= 1.800 m h= 0.300 m Lb = 1.85 m
Spasi = 0.125 m
D14 = 1.208 kg/m n= 15.81 btg
D14 = 1.208 kg/m n= 15.40 btg
Teromol 2Ø14 = 1.208 kg/m n= 2.00 btg
berat tul. Ulir b = 81.412 kg » 2.19
berat tul. Ulir Lb = 70.041 kg » 1.10
berat tul. Ulir tromol = 2.238 kg »
153.691

2 Tapak 250x150
D14
b= 1.500 m h= 0.300 m Lb = 2.22 m
Spasi = 0.125 m
D14 = 1.208 kg/m n= 18.78 btg
D14 = 1.208 kg/m n= 13.00 btg
Teromol 2D14 = 1.208 kg/m n= 2.00 btg
berat tul. Ulir 14 b = 83.050 kg » 2.23
berat tul. Ulir14 Lb = 70.762 kg » 1.12
berat tul. Ulir tromol = 2.685 kg »
156.498

3 Tapak 60x60
Ø12
b= 0.600 m h= 0.200 m Lb = 8.33 m
Spasi = 0.125 m
Ø12 = 0.888 kg/m n= 67.67 btg
Ø12 = 0.888 kg/m n= 5.80 btg
Teromol 2Ø12 = 0.888 kg/m n= 2.00 btg
berat tul. Ulir 14 b = 87.710 kg » 3.57
berat tul. Ulir14 Lb = 85.101 kg » 1.79
berat tul. Ulir tromol = 7.398 kg »
180.210
4 Sloof 30/40
tulang 5D14,2D12, behel Ø10 - 10 cm
b= 0.300 m h= 0.400 m Lb = 8.33 m
Spasi = 0.10-0.15 m Panjang behel = 1.14 m
D14 = 1.208 kg/m n= 5.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 70.44 btg
berat tul. Ulir 14 = 52.868 kg » 6.67
berat tul. Ulir 12 = 14.797 kg
total ulir 67.665
berat tul. Polos = 49.512 kg » 3.33
117.177
5 Sloof 20/25
5Ø12,Ø8 - 10 cm
b= 0.180 m h= 0.250 m Lb = 22.22 m
Spasi = 0.10-0.15 m Ls = 0.60 m
Ø12 = 0.888 kg/m n= 5.00 btg
Ø8 = 0.395 kg/m n= 186.19 btg
berat tul. Polos = 103.578 kg » 11.11
berat tul. Polos = 44.079 kg » 5.56
147.658
6 Kolom 40/50
tulang 12D16,behel Ø10 - 10 cm
b= 0.400 m h= 0.500 m Lb = 5.00 m
Spasi = 0.100 m Ls = 1.54 m
D16 = 1.578 kg/m n= 12.00 btg
Ø10 = 0.617 kg/m n= 51.00 btg
berat tul. Ulir = 99.435 kg » 9.00
berat tul. Polos = 48.423 kg » 4.50
total besi 147.858

7 Kolom 40/40
tulang 10D16,behel Ø10 - 10 cm
b= 0.400 m h= 0.400 m Lb = 6.25 m
Spasi = 0.100 m Ls = 1.34 m
D16 = 1.578 kg/m n= 10.00 btg
Ø10 = 0.617 kg/m n= 63.50 btg
berat tul. Ulir = 103.578 kg » 10.00
berat tul. Polos = 52.461 kg » 5.00
total besi 156.039

8 Kolom 25/25
6Ø12, Ø8 - 10 cm
b= 0.250 m h= 0.250 m Lb = 16.00 m
Spasi = 0.10-0.15 m Ls = 0.74 m
Ø12 = 0.888 kg/m n= 6.00 btg
Ø8 = 0.395 kg/m n= 134.33 btg
berat tul. Polos = 89.492 kg » 16.00
berat tul. Polos = 39.224 kg » 8.00
128.716
9 Kolom 13/13
4Ø12, Ø8 - 10 cm
b= 0.130 m h= 0.130 m Lb = 59.17 m
Spasi = 0.10-0.15 m Ls = 0.26 m
Ø12 = 0.888 kg/m n= 4.00 btg
Ø8 = 0.395 kg/m n= 494.10 btg
berat tul. Polos = 220.640 kg » 30.77
berat tul. Polos = 50.690 kg » 15.38
271.330

10 Balok 35/50
tulang 7D14,2D12, behel Ø10 - 10 cm
b= 0.350 m h= 0.500 m Lb = 5.71 m
Spasi = 0.10-0.15 m Panjang behel = 1.44 m
D16 = 1.578 kg/m n= 7.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 48.62 btg
berat tul. Ulir 14 = 66.290 kg » 7.71
berat tul. Ulir 12 = 10.146 kg
total ulir 76.437
berat tul. Polos = 43.165 kg » 3.86
119.601

11 Balok 30/40
tulang 7D14,2D12, behel Ø10 - 10 cm
b= 0.300 m h= 0.400 m Lb = 8.33 m
Spasi = 0.10-0.15 m Panjang behel = 1.14 m
D16 = 1.578 kg/m n= 7.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 70.44 btg
berat tul. Ulir 14 = 96.673 kg » 9.17
berat tul. Ulir 12 = 14.797 kg
total ulir 111.470
berat tul. Polos = 49.512 kg » 4.58
160.982

12 Balok 25/30
tulang 4D14,2D12, behel Ø10 - 10 cm
b= 0.250 m h= 0.300 m Lb = 13.33 m
Spasi = 0.10-0.15 m Panjang behel = 0.84 m
D16 = 1.578 kg/m n= 4.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 112.11 btg
berat tul. Ulir 14 = 88.387 kg » 11.33
berat tul. Ulir 12 = 23.675 kg
total ulir 112.062
berat tul. Polos = 58.061 kg » 5.67
170.123

13 Balok 30/50
tulang 7D14,2D12, behel Ø10 - 10 cm
b= 0.300 m h= 0.500 m Lb = 6.67 m
Spasi = 0.10-0.15 m Panjang behel = 1.34 m
D16 = 1.578 kg/m n= 7.00 btg
D12 = 0.888 kg/m n= 2.00 btg
Ø10 = 0.617 kg/m n= 56.56 btg
berat tul. Ulir 14 = 77.338 kg » 8.67
berat tul. Ulir 12 = 11.838 kg
total ulir 89.176
berat tul. Polos = 46.724 kg » 4.33
135.900

14 Plat Beton/Lantai
Ø12
b= 1.000 m h= 0.300 m Lb = 3.33 m 3.33
Spasi = 0.150 m
Ø12 = 0.888 kg/m n= 23.22 btg
Ø12 = 0.888 kg/m n= 7.67 btg
berat tul. Polos = 46.182 kg » 3.33
berat tul. Polos = 47.011 kg » 1.67
93.193
M2 Bekistg

M2 Bekistg

M2 Bekistg
M2 Bekistg

M2 Bekistg

M2 Bekistg

M2 Bekistg

M2 Bekistg
M2 Bekistg

M2 Bekistg

M2 Bekistg

M2 Bekistg

M2 Bekistg
M2 Bekistg
PEKERJAAN Analisa Khusus 1
KHUSUS M2 Pekerjaan Lapisan Sintetik prefebricated mat t=13mm
BAHAN
PU Adhesive Kg 1.1000
Shockpad 10 mm m2 1.0000
Seal coat Kg 0.5000
PU wear coat Kg 2.1000
Granule / EPDM Kg 2.8000
Alat bantu kerja Jam 0.2000
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli pasang Sintetik Oh 0.4000
Pekerja Oh 0.1500
Mandor Oh 0.5000
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN
Analisa Khusus 2
M1 Pekerjaan Pengecatan Garis Lintasan
BAHAN
Cat Polyurethane Kg 0.0600

JUMLAH HARGA BAHAN


TENAGA
Pekerja Oh 0.4667
Tukang cat Oh 0.1167
Mandor Oh 0.1167
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
OVER HEAD DAN PROFIT
HARGA SATUAN PEKERJAAN
Analisa Khusus 3
1 Set Foundation tray for take off board & Blanking Board /Pondasi papan lompat Jauh dan Lom
BAHAN
Foundation tray for take off board & Blanking Board set 1.0000
Lapisan sintetik m2 0.4148
Semen Portland zak 0.8150
Pasir beton m3 0.0594
Koral beton m3 0.0955
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli built in equipment Oh 0.8000
Pekerja Oh 1.6500
Mandor Oh 0.0680
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN
Analisa Khusus 4
1 bh Take off board/Papan Tumpuan Lompat jauh
BAHAN
Take off board bh 1.0000
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli built in equipment Oh 0.7500
Pekerja Oh 1.6500
Mandor Oh 0.0600
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN
Analisa Khusus 5
1 Set Pole vault galvanis steel/Bak Tumpuan Loncat Galah
BAHAN
Pole vault + cover galvanis steel set 1.0000
Lapisan sintetik m2 0.2500
Semen Portland zak 0.7300
Pasir beton m3 0.0500
Koral beton m3 0.0700
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli built in equipment Oh 0.8000
Pekerja Oh 1.6500
Mandor Oh 0.0700
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN
Analisa Khusus 6
1 Set Soft curb for landing pit/Ring Besi Untuk Tolak Peluru
BAHAN
Soft curb for landing pit set 1.0000
Semen Portland zak 6.5000
Pasir beton m3 0.7000
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli built in equipment Oh 2.0000
Pekerja Oh 4.0000
Mandor Oh 0.4000
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN

Analisa Khusus 7
1 bh Discus ring & hammer ring and adjust ring dia 3.15 m/Ring Besi Untuk Cakram dan Martil
BAHAN
Discus ring & hammer ring and adjust ring dia 3.15 m bh 1.0000
Semen Portland zak 16.3000
Pasir beton m3 1.0925
Koral beton m3 1.8700
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli built in equipment Oh 3.0000
Pekerja Oh 4.0000
Mandor Oh 0.5000
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN

Analisa Khusus 8
1 bh Shot put ring with concrete floor dia 2.50 m/Ring Besi Untuk Tolak Peluru
BAHAN
Shot put ring dia 2.50 m bh 1.0000
Semen Portland zak 9.7800
Pasir beton m3 0.7900
Koral beton m3 0.8600
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli built in equipment Oh 2.5000
Pekerja Oh 4.0000
Mandor Oh 0.5000
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN
Analisa Khusus 9
1 Set Water jump high hurdle /Pondasi dan gawang Pada Bak Air untuk Lari Halang rintang
BAHAN
Water jump high hurdle set 1.0000
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli built in equipment Oh 4.5000
Pekerja Oh 4.5000
Mandor Oh 0.3300
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN

Analisa Khusus 10
1 M' Alumunium Curb
BAHAN
Alumunium Curb M' 1.0000
JUMLAH HARGA BAHAN
TENAGA
Tenaga ahli built in equipment Oh 0.4500
Pekerja Oh 0.4500
Mandor Oh 0.3200
JUMLAH HARGA TENAGA
JUMLAH HARGA TENAGA DAN BAHAN
HARGA SATUAN PEKERJAAN
1,633,397

130,360 143,396
275,100 275,100
217,140 108,570
298,750 627,375
97,020 271,656
200,000 40,000
1,466,097

250,000 100,000
82,000 12,300
110,000 55,000
167,300
1,633,397
1,633,397

78,583

Rp 144,375 8,663

8,663

Rp 82,000 38,269
Rp 100,000 11,670
Rp 110,000 12,837
62,776
71,439
7,144
78,583

an lompat Jauh dan Lompat jangkit 7,062,915

6,000,000 6,000,000
1,633,397 677,533
53,900 43,929
185,000 10,984
290,000 27,689
6,760,135

200,000 160,000
82,000 135,300
110,000 7,480
302,780
7,062,915
7,062,915
10,291,900

10,000,000 10,000,000
10,000,000

200,000 150,000
82,000 135,300
110,000 6,600
291,900
10,291,900
10,291,900

4,661,897

4,000,000 4,000,000
1,160,000 290,000
53,900 39,347
185,000 9,250
290,000 20,300
4,358,897

200,000 160,000
82,000 135,300
110,000 7,700
303,000
4,661,897
4,661,897
2,751,850

1,500,000 1,500,000
53,900 350,350
185,000 129,500
1,979,850

200,000 400,000
82,000 328,000
110,000 44,000
772,000
2,751,850
2,751,850

ntuk Cakram dan Martil 20,605,983

18,000,000 18,000,000
53,900 878,570
185,000 202,113
290,000 542,300
19,622,983

200,000 600,000
82,000 328,000
110,000 55,000
983,000
20,605,983
20,605,983

9,805,692

8,000,000 8,000,000
53,900 527,142
185,000 146,150
290,000 249,400
8,922,692

200,000 500,000
82,000 328,000
110,000 55,000
883,000
9,805,692
9,805,692
Lari Halang rintang 26,305,300

25,000,000 25,000,000
25,000,000

200,000 900,000
82,000 369,000
110,000 36,300
1,305,300
26,305,300
26,305,300

312,100

150,000 150,000
150,000

200,000 90,000
82,000 36,900
110,000 35,200
162,100
312,100
312,100
1.6
352000
563,200.00

You might also like