DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA SEWA

No. URAIAN KO HP KAPASITAS HARGA ALAT/JAM


DE ALAT

(diluar PPN)
1 BULLDOZER 100-150 HP E04 140.0 - - 1,200,000,000 574,636.47
2 COMPRESSOR 4000-6500 L\M E05 80.0 5,000.0 CPM/(L/m) 85,000,000 184,077.70
3 CONCRETE MIXER 0.3-0.6 M3 E06 15.0 500.0 Liter 39,500,000 50,000.00
4 DUMP TRUCK 3-4 M3 E08 100.0 6.0 Ton 207,000,000 280,000.00
5 DUMP TRUCK E09 125.0 8.0 Ton 320,000,000 340,000.00
6 EXCAVATOR 80-140 HP E10 80.0 0.5 M3 900,000,000 400,000.00
7 FLAT BED TRUCK 3-4 M3 E11 100.0 4.0 ton 162,000,000 238,322.21
8 GENERATOR SET E12 175.0 125.0 KVA 140,500,000 361,781.21
9 MOTOR GRADER >100 HP E13 125.0 10,800.0 - 635,000,000 280,000.00
10 TRACK LOADER 75-100 HP E14 90.0 1.6 M3 623,000,000 339,931.53
11 WHEEL LOADER 1.0-1.6 M3 E15 105.0 1.5 M3 670,000,000 377,844.41
12 THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 264,000,000 187,209.74
13 TANDEM ROLLER 6-8 T. E17 50.0 8.0 Ton 360,000,000 203,350.94
14 TIRE ROLLER 8-10 T. E18 60.0 10.0 Ton 386,100,000 238,333.68
15 VIBRATORY ROLLER 5-8 T. E19 75.0 7.0 Ton 431,200,000 200,000.00
16 CONCRETE VIBRATOR E20 3.0 25.0 Liter 21,120,000 43,036.75
17 WATER PUMP 70-100 mm E22 6.0 - - 19,800,000 42,846.98
18 WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 144,500,000 233,812.09
19 PEDESTRIAN ROLLER E24 11.0 1.00 Ton 77,000,000 65,134.60
20 TAMPER E25 5.0 0.20 Ton 29,000,000 51,861.57
21 JACK HAMMER E26 3.0 1,330.00 - 29,150,000 47,550.90
22 FULVI MIXER E27 75.0 2,005.00 - 159,500,000 194,677.91
23 CONCRETE PUMP E28 100.0 8.00 M3 175,000,000 239,020.76
24 TRAILER 20 TON E29 175.0 20.00 Ton 372,900,000 416,024.88
25 PILE DRIVER + HAMMER E30 25.0 2.50 Ton 122,100,000 99,039.15
26 CRANE ON TRACK 35 TON E31 125.0 35.0 Ton 1,000,000,000 482,139.01
27 WELDING SET E32 40.0 250.0 Amp 23,100,000 99,324.78
28 BORE PILE MACHINE E33 150.0 2,000.0 Meter 2,250,000,000 828,348.50
29 ASPHALT LIQUID MIXER E34 5.0 1,000.0 Liter 16,500,000 37,809.25
30 TRONTON E35 150.0 15.0 Ton 276,000,000 363,724.51
31 COLD MILLING E36 248.0 1,000.0 m - 469,417.14
32 ROCK DRILL BREAKER E37 3.0 - - - 48,017.14
33 COLD RECYCLER E38 900.0 2.2 M - 1,590,857.14
34 HOT RECYCLER E39 400.0 3.0 M - 730,857.14
35 AGGREGAT (CHIP) SPREADER E40 115.0 3.5 M - 240,657.14
36 ASPHALT DISTRIBUTOR E41 115.0 4,000.0 Liter - 240,657.14
37 SLIP FORM PAVER E42 105.0 2.5 M - 223,457.14
23 CONCRETE PAN MIXER E43 134.0 600.0 Liter 405,000,000 250,000.00
24 TRUK MIXER (AGITATOR) E49 220.0 5.0 M3 405,000,000 400,000.00

Banda Aceh,1 Juni 201


CV.MOLA AGUNG

RIZKY MOULANA
DIREKTUR
WA PERALATAN PER JAM KERJA

KET.

Banda Aceh,1 Juni 2015


CV.MOLA AGUNG

RIZKY MOULANA
HARGA DASAR SATUAN UPAH
HARGA
No. URAIAN KODE SATUAN YG DIGUNAKAN KETERANGAN
( Rp.)

1. Pekerja (L01) Jam 8,571.43 56,000.00

2. Tukang (L02) Jam 11,428.57 85,000.00

3. Mandor (L03) Jam 11,428.57 85,000.00

4. Operator (L04) Jam 17,142.86 120,000.00

5. Pembantu Operator (L05) Jam 8,571.43 60,000.00

6. Sopir / Driver (L06) Jam 11,428.57 80,000.00

7. Pembantu Sopir / Driver (L07) Jam 7,428.57 52,000.00

8. Mekanik (L08) Jam 11,428.57 80,000.00

9. Pembantu Mekanik (L09) Jam 7,428.57 52,000.00

10. Kepala Tukang (L10) Jam 14,285.71 100,000.00

1. Pekerja (L01).a OH 70,000.00

2. Tukang (L02).a OH 80,000.00

3. Mandor (L03).a OH 80,000.00

4. Kepala Tukang (L10).a OH 100,000.00

Banda Aceh,1 Juni 2015


CV.MOLA AGUNG

RIZKY MOULANA
DIREKTUR
DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1 Pasir Pasang (Sedang) M01b M3 170,000.00 Base Camp


2 Pasir Beton (Kasar) M01a M3 170,000.00 Base Camp
3 Pasir Halus (untuk HRS) M01c M3 170,000.00 Base Camp
4 Pasir Urug (ada unsur lempung) M01d M3 150,000.00 Base Camp
5 Batu Kali M02 M3 170,000.00 Lokasi Pekerjaan
6 Agregat Kasar M03 M3 253,465.85 Base Camp
7 Agregat Halus M04 M3 253,465.85 Base Camp
8 Filler M05 Kg 1,350.00 Proses/Base Camp
9 Batu Belah / Kerakal M06 M3 140,000.00 Lokasi Pekerjaan
10 Gravel M07 M3 162,000.00 Base Camp
11 Bahan Tanah Timbunan M08 M3 45,000.00 Borrow Pit/quarry
12 Bahan Pilihan M09 M3 67,000.00 Quarry
14 Kerosen / Minyak Tanah M11 LITER 10,000.00 Base Camp
15 Semen / PC (40kg) M12 Zak 54,000.00 Base Camp
16 Semen / PC (kg) M12 Kg 1,350.00 Base Camp
17 Besi Beton Polos M13 Kg 12,000.00 Lokasi Pekerjaan
18 Kawat Beton M14 Kg 15,000.00 Lokasi Pekerjaan
20 Sirtu M16 M3 154,900.00 Lokasi Pekerjaan
23 Paku M18 Kg 12,000.00 Lokasi Pekerjaan
24 Kayu Perancah M19 M3 1,800,000.00 Lokasi Pekerjaan
Papan Perancah/Papan Bekisting M19a M3 1,800,000.00 Lokasi Pekerjaan
25 Bensin M20 LITER 9,000.00 Pertamina
26 Solar M21 LITER 10,200.00 Pertamina
27 Minyak Pelumas / Olie M22 LITER 44,500.00 Pertamina
28 Plastik Filter M23 M2 14,000.00 Lokasi Pekerjaan
30 Pipa Porus M25 M' 25,000.00 Lokasi Pekerjaan
40 Thinner M35 LITER 23,000.00 Lokasi Pekerjaan
45 Beton K-250 M39 M3 1,432,471.00 Lokasi Pekerjaan
46 Baja Tulangan (Polos) U24 M39a Kg 12,000.00 Lokasi Pekerjaan
47 Baja Tulangan (Ulir) D32 M39b Kg 18,500.00 Lokasi Pekerjaan
52 Pasir Urug M44 M3 133,100.00 Base Camp
55 Beton K-125 M47 M3 934,146.00 Lokasi Pekerjaan
59 Kawat Las M51 Dos 55,000.00 Lokasi Pekerjaan
65 Baja Tulangan (Polos) U32 M57a Kg 12,000.00 Lokasi Pekerjaan
75 Beton K-175 M60 M3 1,096,582.53 Lokasi Pekerjaan
84 Oxygen M87 Botol 385,000.00 Lokasi Pekerjaan
88 Agregat Pecah Mesin 0-5 mm M91 M3 253,465.85 Base Camp
89 Agregat Pecah Mesin 5-10 & 10-20 mm M92 M3 253,465.85 Base Camp
90 Agregat Pecah Mesin 20-30 mm M93 M3 253,465.85 Base Camp
91 Kayu Acuan M99 M3 1,800,000.00
96 Pohon Batang 45,000.00

Banda Aceh,1 Juni 2015


CV.MOLA AGUNG

RIZKY MOULANA
DIREKTUR
KEGIATAN : REHABILITASI DAN PENINGKATAN JARINGAN IRIGASI (DAK)
PEKERJAAN : PENINGKATAN SALURAN SEKUNDER JARINGAN IRIGASI D.I. KRUENG KALA (22 HA) KEC. LHOONG
LOKASI : KEC. LHOONG - KAB. ACEH BESAR
TAHUN ANGGARAN : 2016

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP

Rizki Maulana
Direktur
LA (22 HA) KEC. LHOONG
REKAPITULASI
RENCANA ANGGARAN BIAYA

KEGIATAN : REHABILITASI DAN PENINGKATAN JARINGAN IRIGASI (DAK)

PEKERJAAN : PENINGKATAN SALURAN SEKUNDER JARINGAN IRIGASI D.I. KRUENG KALA (22
HA) KEC. LHOONG
LOKASI : KEC. LHOONG - KAB. ACEH BESAR
TAHUN ANGGARAN : 2016

NO. URAIAN PEKERJAAN TOTAL HARGA


(Rp.)

I PEKERJAAN PERSIAPAN Rp 6,300,000.00

II PEKERJAAN EMBUNG Rp 287,861,036.25

III PEKERJAAN LAIN-LAIN Rp 2,000,000.00

JUMLAH Rp 296,161,036.25

PPN 10% Rp 29,616,103.63

TOTAL JUMLAH Rp 325,777,139.88

DIBULATKAN Rp 325,777,000.00
TERBILANG : Tiga ratus dua puluh lima juta tujuh ratus tujuh puluh tujuh ribu rup

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP

Rizki Maulana
Direktur
RENCANA ANGGARAN BIAYA (RAB)

KEGIATAN : REHABILITASI DAN PENINGKATAN JARINGAN IRIGASI (DAK)


PEKERJAAN : PENINGKATAN SALURAN SEKUNDER JARINGAN IRIGASI D.I. KRUENG KALA (22 HA)
LHOONG
LOKASI : KEC. LHOONG - KAB. ACEH BESAR
TAHUN ANGGARAN : 2016

SATUA VOLUME ANALISA HARGA SATUAN


NO. URAIAN PEKERJAAN N
(Rp.)
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan Ls 1.00 Taksir Rp 1,000,000.00
2 Uitzet/Pemasangan Profil Ls 1.00 Taksir Rp 1,500,000.00
3 Sewa Pondok Kerja/ Gudang Ls 1.00 Taksir Rp 3,000,000.00
4 Papan Nama Proyek Unit 1.00 Taksir Rp 800,000.00
Jumlah
II PEKERJAAN EMBUNG
1 Galian Tanah (MP) M3 119.72 T.06.a Rp 39,000.00
2 Pasangan Batu 1 : 4 M3 232.75 P.01.c Rp 807,675.00
3 Plesteran 1 : 3 M2 1,511.20 P.04.e Rp 63,000.00
Jumlah
III PEKERJAAN LAIN-LAIN
1 Administrasi dan Dokumentasi Ls 1.00 Taksir Rp 2,000,000.00
Jumlah
JUMLAH HARGA
PPN 10%
TOTAL JUMLAH
DIBULATKAN

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP

Rizki Maulana
Direktur
A ANGGARAN BIAYA (RAB)

RAN SEKUNDER JARINGAN IRIGASI D.I. KRUENG KALA (22 HA) KEC.

JUMLAH HARGA
(Rp.)

Rp 1,000,000.00
Rp 1,500,000.00
Rp 3,000,000.00
Rp 800,000.00
Rp 6,300,000.00

Rp 4,669,080.00
Rp 187,986,356.25
Rp 95,205,600.00
Rp 287,861,036.25

Rp 2,000,000.00
Rp 2,000,000.00
Rp 296,161,036.25
Rp 29,616,103.63
Rp 325,777,139.88
Rp 325,777,000.00

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjan : Galian Tanah Biasa (MP); ≤ 1 M


Satuan/Unit : M3
Analisa : T.06.a

Kuantitas/Koe HargaSatuan Dasar


No. Uraian Satuan Jumlah Harga (Rp.)
fisien (Rp.)
(1) (2) (3) (4) (5) (6)=(4) x (5)

A Tenaga Kerja
1 Pekerja OH 0.5630 55,000.00 Rp 30,965.00
2 Mandor OH 0.0563 80,000.00 Rp 4,504.00

Sub Jumlah A Rp 35,469.00


B Bahan

Sub Jumlah B
C Peralatan

Sub Jumlah C Rp -
D Sub Jumlah ( A+B+C) Rp 35,469.00
E Overhead + Keuntungan 10% x Sub Jumlah (D) Rp 3,546.90
Jumlah Harga = (D + E) Rp 39,015.90
Harga Satuan Pekerjaan (Dibulatakan) Rp 39,000.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjan : Pasangan Batu Kali 1 : 4


Satuan/Unit : m3
Analisa : P.01.c

Kuantitas/Koe HargaSatuan Dasar


No. Uraian Satuan Jumlah Harga (Rp.)
fisien (Rp.)
(1) (2) (3) (4) (5) (6)=(4) x (5)
A Tenaga Kerja
1 Pekerja OH 2.7000 55,000.00 Rp 148,500.00
2 Tukang OH 0.9000 85,000.00 Rp 76,500.00
3 Kepala Tukang OH 0.0900 100,000.00 Rp 9,000.00
4 Mandor OH 0.2700 80,000.00 Rp 21,600.00
Sub Jumlah A Rp 255,600.00
B Bahan
1 Batu Kali/Gunung m3 1.2000 146,000.00 Rp 175,200.00
2 Pasir Pasang m3 0.5200 160,000.00 Rp 83,200.00
3 Semen PC (1 kg) Kg 163.0000 1,300.00 Rp 211,900.00
Rp -
Rp -
Sub Jumlah B Rp 470,300.00
C Peralatan
Molen Unit/Hari 0.1670 50,000.00 Rp 8,350.00

Sub Jumlah C Rp 8,350.00


D Sub Jumlah ( A+B+C) Rp 734,250.00
E Overhead + Keuntungan 10% x Sub Jumlah (D) Rp 73,425.00
Jumlah Harga = (D + E) Rp 807,675.00
Harga Satuan Pekerjaan (Dibulatakan) Rp 807,675.00

Catatan :
Biaya Overhead + Keuntungan diisi Maksimal sebesar 15%( Lima Belas Persen)
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjan : 1 M2 Pekerjaan Plesteran 1 : 3 tebal 1,5 cm


Satuan/Unit : m2
Analisa : P.04.e

Kuantitas/Koe HargaSatuan Dasar


No. Uraian Satuan Jumlah Harga (Rp.)
fisien (Rp.)
(1) (2) (3) (4) (5) (6)=(4) x (5)

A Tenaga Kerja
1 Pekerja OH 0.3840 55,000.00 Rp 21,120.00
2 Tukang OH 0.1920 85,000.00 Rp 16,320.00
3 Kepala Tukang OH 0.0190 100,000.00 Rp 1,900.00
4 Mandor OH 0.0380 80,000.00 Rp 3,040.00
Sub Jumlah A Rp 42,380.00
B Bahan
1 Pasir Pasang m3 0.0300 160,000.00 Rp 4,800.00
2 Semen PC (1 kg) Kg 7.7760 1,300.00 Rp 10,108.80

Sub Jumlah B Rp 14,908.80


C Peralatan

Sub Jumlah C
D Sub Jumlah ( A+B+C) Rp 57,288.80
E Overhead + Keuntungan 10% x Sub Jumlah (D) Rp 5,728.88
Jumlah Harga = (D + E) Rp 63,017.68
Harga Satuan Pekerjaan (Dibulatakan) Rp 63,000.00

Catatan :
Biaya Overhead + Keuntungan diisi Maksimal sebesar 15%( Lima Belas Persen)
TAKSIRAN PRODUKSI ALAT
MENGANGKUT HASIL GALIAN

No. URAIAN KODE


I ASUMSI
1 Jam kerja efektif per-hari Tk

II PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
Tanah hasi Galian

2 ALAT
Dump Truck
A Tenaga mesin N
B Berat Dump Truck Bo
C. Kapasitas Bak Drump Truck qdt
D Kapasitas Bucket pemuat ql
E Waktu Siklus Pemuat Ctl
F Koefisien Rolling RR
G Berat Jenis Material Bj
H Kemiringan Medan a
I Jarak Angkut D
J Konsentrasi Beban Pada Roda Penggerak R
K Perhitungan Waktu Siklus Ct
1 Waktu Muat tm
qdt
tm = x Ctl
ql

2 Waktu angkut bermuatan tam


2.a Gaya Angkut Pam
Pam = R (Bo+qdt.Bj)(RR ±Sin a/1000)
2.b Kecepatan Angkut Vam
N x 75 x 60
Vam =
Pam
2.c Waktu Angkut Bermuatan tam
D
tam =
Vam

3 Waktu Kembali tk
3.a Gaya Angkut Pk
Pk = R.Bo(RR±Sin.a/1000)
3.b Kecepatan Balik Vk
N x 75 x 60
Vk =
Pk
3.c Waktu Kembali (Kosong) tk
= D
tk
Vk
4 Waktu Buang Muatan tb

5 Waktu Tunggu Dimuati t

6 Total Waktu Siklus Ct


Ct = tm + tam + tk + tb + t

L Job Factor ( Efesiensi Kerja) E


M faktor Konversi Material CF
N Produktifitas Alat
60 x qdt x CF
Q = x E Q
Ct
O Koefesien Alat (1/Q)
TAKSIRAN PRODUKSI ALAT
GALIAN TANAH BIASA

No. URAIAN KODE


I ASUMSI
1 Jam kerja efektif per-hari Tk

II PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
tidak ada bahan yang diperlukan

2 ALAT
EXCAVATOR
A. Tenaga yang tersedia dalam mesin N
B. Kapasitas Bucket q
C. Perhitungan Waktu Siklus Ct
1. Penggalian ( Cutting)
2. Pengangkatan & Swing (Loaded)
3. Pembuangan ( Dumping)
4. Swing Kembali (Unloaded)
Jumlah

D. Job Factor ( Efesiensi Kerja) E


E. faktor Konversi Material CF
F. Produktifitas Alat
60 x q x CF
Q = x E Q
Ct
G. Koefesien Alat (1/Q)

TAKSIRAN PRODUKSI ALAT


GALIAN TANAH BERBATU

No. URAIAN KODE


I ASUMSI
1 Jam kerja efektif per-hari Tk

II PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
tidak ada bahan yang diperlukan

2 ALAT
EXCAVATOR
A. Tenaga yang tersedia dalam mesin N
B. Kapasitas Bucket q
C. Perhitungan Waktu Siklus Ct
1. Penggalian ( Cutting)
2. Pengangkatan & Swing (Loaded)
3. Pembuangan ( Dumping)
4. Swing Kembali (Unloaded)
Jumlah

D. Job Factor ( Efesiensi Kerja) E


E. faktor Konversi Material CF
F. Produktifitas Alat
60 x q x CF
Q = x E Q
Ct
G. Koefesien Alat (1/Q)
TAKSIRAN PRODUKSI ALAT
TIMBUNAN TANAH HASIL GALIAN

No. URAIAN KODE


I ASUMSI
1 Jam kerja efektif per-hari Tk

II PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
tidak ada bahan yang diperlukan

2 ALAT
EXCAVATOR
A. Tenaga yang tersedia dalam mesin N
B. Kapasitas Bucket q
C. Perhitungan Waktu Siklus Ct
1. Penggalian ( Cutting)
2. Pengangkatan & Swing (Loaded)
3. Pembuangan ( Dumping)
4. Swing Kembali (Unloaded)
Jumlah

D. Job Factor ( Efesiensi Kerja) E


E. faktor Konversi Material CF
F. Produktifitas Alat
60 x q x CF
Q = x E Q
Ct
G. Koefesien Alat (1/Q)
TAKSIRAN PRODUKSI ALAT
MENYUSUN BATU Uk.>1000 Kg

No. URAIAN KODE


I ASUMSI
1 Jam kerja efektif per-hari Tk

II PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
Batu Uk.> 1.000 Kg

2 ALAT
EXCAVATOR
A. Tenaga yang tersedia dalam mesin N
B. Kapasitas Bucket q
C. Perhitungan Waktu Siklus Ct
1. Pengangkatan & Swing (Loaded)
2. Pembuangan (Dumping)
3. Penyusunan (Piling)
4. Swing Kembali (Unloaded)
Jumlah

D. Job Factor ( Efesiensi Kerja) E


E. faktor Konversi Material CF
F. Produktifitas Alat
60 x q x CF
Q = x E Q
Ct
G. Produktivitas Alat per Hari
Qt = ( Tk x Q) Qt
H. Koefesien Alat (1/Q) -

I. Tenaga Kerja
1. Kebutuhan tenaga : Pekerja P
Mandor M
2. Koefesien Tenaga : Pekerja= (Tk x P)/ Qt
Mandor = (Tk x M)/Qt
TAKSIRAN PRODUKSI ALAT
MENYUSUN BATU Uk. 250 - 1.000 Kg

No. URAIAN KODE


I ASUMSI
1 Jam kerja efektif per-hari Tk

II PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
Batu Uk.> 1.000 Kg

2 ALAT
EXCAVATOR
A. Tenaga yang tersedia dalam mesin N
B. Kapasitas Bucket q
C. Perhitungan Waktu Siklus Ct
1. Pengangkatan & Swing (Loaded)
2. Pembuangan (Dumping)
3. Penyusunan (Piling)
4. Swing Kembali (Unloaded)
Jumlah

D. Job Factor ( Efesiensi Kerja) E


E. faktor Konversi Material CF
F. Produktifitas Alat
60 x q x CF
Q = x E Q
Ct
G. Produktivitas Alat per Hari
Qt = ( Tk x Q) Qt
H. Koefesien Alat (1/Q) -

I. Tenaga Kerja
1. Kebutuhan tenaga : Pekerja P
Mandor M
2. Koefesien Tenaga : Pekerja= (Tk x P)/ Qt
Mandor = (Tk x M)/Qt

CV. MENARA ACEH GROUP


T
AN

KOEF. SATUAN KETERANGAN

7.00 Jam

100.00 Hp
7.00 Ton
4.00 m3
0.80 m3
0.97 menit
100.00 Kg/Ton
1.70 Ton/m3
0.00 Derajat
500.00 m
0.60

4.83 menit

0.92
828.00 Kg

543.48 m/menit

0.92 menit

420.00 Kg

1071.43 m/menit

0.47 menit
0.70 menit

0.20 menit

6.65 menit

0.66
1.00

36.07 m3/jam

0.03 jam/m3
T

KOEF. SATUAN KETERANGAN

7.00 Jam

105 Hp
0.80 m3

30 detik
12 detik
8 detik
8 detik
58 detik
0.97 menit
0.602
1.25

37.3655 m3/jam

0.0268 jam/m3

KOEF. SATUAN KETERANGAN

7.00 Jam

105 Hp
0.80 m3
30 detik
12 detik
8 detik
8 detik
58 detik
0.97 menit
0.602
1.13

33.7784 m3/jam

0.0296 jam/m3
T
LIAN

KOEF. SATUAN KETERANGAN

7.00 Jam

105 Hp
0.80 m3

30 detik
12 detik
8 detik
8 detik
58 detik
0.97 menit
0.602
1.43

42.7462 m3/jam

0.0234 jam/m3
T
Kg

KOEF. SATUAN KETERANGAN

7.00 Jam

105 Hp
0.8 m3

10 detik
10 detik
120 detik
10 detik
150 detik
2.500 menit
0.602
0.77

8.899968 m3/jam

62.299776 m3/hari
0.1124 jam/m3

2 Orang
1 Orang
0.2247 jam
0.1124 jam
T
00 Kg

KOEF. SATUAN KETERANGAN

7.00 Jam

105 Hp
0.8 m3

10 detik
10 detik
180 detik
10 detik
210 detik
3.500 menit
0.602
0.77

6.3571 m3/jam

44.4998 m3/hari
0.1573 jam/m3

2 Orang
1 Orang
0.3146 jam
0.1573 jam

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP

Rizki Maulana
Direktur
ANALISA HARGA SATUAN ALAT BERAT
I. DATA PERALATAN
1 Jenis Peralatan EXCAVATOR 0.8 M3 (Kapasitas Bucket))
2 Tenaga N = 105 HP
3 Harga = Rp 800,000,000.00
4 Umur Kerja = 5.00 Tahun
5 1 Hari kerja = 7.00 Jam
6 Umur Ekonomis (Tahun) UE = 5.00 Thn 10,000.00
7 Jam Kerja per tahun (Tahun) h = 2,000.00 jam
8 Harga Pokok HP = Rp 800,000,000.00
9 Harga Bahan Pokok/ Ban Hbp = Rp 35,000,000.00
10 Harga Sisa HS = 10% x HP = Rp 80,000,000.00
11 Harga Penyusutan = (HP-hbp-HS) = Rp 685,000,000.00
II BIAYA KEPEMILIKAN (OWNERSHIP) Rp/jam Jumlah II
- Penyusutan D = (HP-Hbp - HS)/ (UE x h) Rp 68,500.00
- Bunga Modal BM (i = 15%) BM = i((UE + 1)/( 2 UE) x (HP/h) Rp 36,000.00

- Asuransi (P=2%) Ba = p ((UE+1)/(2 x UE) x (HP/h)) Rp 4,800.00


III BIAYA OPERASIONAL (OPERTIONAL COST) Jumlah III
-Biaya Bahan Bakar
BBM = ((0,8 x N x S)/E) x Hbbm #REF!
S = (Solar) = 0.15
E = = 0.602
N = = 105
Hbbm= (Harga BBM) = #REF!

-Biaya Bahan Oli Pelumas


a. Mesin
BBom = ((C/T) + (S/E)) x n x Hbop #REF!
C = = 0.130
T = (jam) = 250.00
S = = 0.0005
E = = 0.602
N = = Rp 105
Hbop = (Harga bahan oli) = #REF!

b. Transmisi
BBOt = ((C/T) + (S/E)) x n x Hbop #REF!
C = = 0.223
T = (jam) = 1,000.00
S = = 0.0003
E = = 0.602
N = = Rp 105
Hbop = (Harga bahan oli) = #REF!

-Biaya Bahan Hydraulik


BBH = ((C/T) + (S/E)) x n x Hbbh #REF!
C = (Excavator) 2.875
T = (jam) 2,000.00
S =(Excavator) 0.00064
E = 0.602
N = 105.00
Hbbh = (Harga bahan hydraulik) #REF!

-Biaya Bahan Gemok (Grease)


BBG = (S/E) x N x Hbbg #REF!
S =(Excavator) = 0.0006
E = = 0.602
N = = 105.00
Hbbg= (Harga bahan gemok) = #REF!

-Biaya Saringan (filter-filter)


BBF = 0,5 (BBM + BBO + BBH + BBG) #REF!

-Biaya Bahan Pokok/Ban


BBP Hbp/ T Rp 17,500.00
Hbp = 35,000,000.00
T = (jam) 2,000.00

-Biaya Operator/Jam #REF!

-Biaya Pemeliharaan/ Perbaikan (f = 90%)


BBP = f x (HP - Hbp)/UE Rp 68,850.00

Harga Satuan Pekerjaan/ Jam ( Jumlah Biaya II + III )


Dibulatkan

ANALISA HARGA SATUAN ALAT BERAT


I. DATA PERALATAN
1 Jenis Peralatan DUMP TRUCK 4 M3 (Kapasitas Bucket))
2 Tenaga N = 100 HP
3 Harga = Rp 209,000,000.00
4 Umur Kerja = 5.00 Tahun
5 1 Hari kerja = 7.00 Jam
6 Umur Ekonomis (Tahun) UE = 5.00 Thn 10,000.00
7 Jam Kerja per tahun (Tahun) h = 2,000.00 jam
8 Harga Pokok HP = Rp 209,000,000.00
9 Harga Bahan Pokok/ Ban Hbp = Rp 20,000,000.00
10 Harga Sisa HS = 10% x HP = Rp 20,900,000.00
11 Harga Penyusutan = (HP-hbp-HS) = Rp 168,100,000.00
II BIAYA KEPEMILIKAN (OWNERSHIP) Rp/jam Jumlah II
- Penyusutan D = (HP-Hbp - HS)/ (UE x h) Rp 16,810.00
- Bunga Modal BM (i = 15%) BM = i((UE + 1)/( 2 UE) x (HP/h) Rp 9,405.00
- Asuransi (P=2%) Ba = p ((UE+1)/(2 x UE) x (HP/h)) Rp 1,254.00

III BIAYA OPERASIONAL (OPERTIONAL COST) Jumlah III


-Biaya Bahan Bakar
BBM = ((0,8 x N x S)/E) x Hbbm #REF!
S = (Solar) = 0.15
E = = 0.657
N = = 100
Hbbm= (Harga BBM) = #REF!

-Biaya Bahan Oli Pelumas


a. Mesin
BBom = ((C/T) + (S/E)) x n x Hbop #REF!
C = = 0.130
T = (jam) = 250.00
S = = 0.0005
E = = 0.657
N = = Rp 100
Hbop = (Harga bahan oli) = #REF!

b. Transmisi
BBOt = ((C/T) + (S/E)) x n x Hbop #REF!
C = = 0.223
T = (jam) = 1,000.00
S = = 0.0003
E = = 0.657
N = = Rp 100
Hbop = (Harga bahan oli) = #REF!

-Biaya Bahan Hydraulik


BBH = ((C/T) + (S/E)) x n x Hbbh #REF!
C = (Dump Truck) 2.620
T = (jam) 2,000.00
S =(Excavator) 0.00064
E = 0.657
N = 100.00
Hbbh = (Harga bahan hydraulik) #REF!

-Biaya Bahan Gemok (Grease)


BBG = (S/E) x N x Hbbg #REF!
S =(Dump Truck) = 0.00009
E = = 0.602
N = = 100.00
Hbbg= (Harga bahan gemok) = #REF!

-Biaya Saringan (filter-filter)


BBF = 0,5 (BBM + BBO + BBH + BBG) #REF!

-Biaya Bahan Pokok/Ban


BBP Hbp/ T Rp 10,000.00
Hbp = 20,000,000.00
T = (jam) 2,000.00

-Biaya Sopir/Jam #REF!

-Biaya Pemeliharaan/ Perbaikan (f = 90%)


BBP = f x (HP - Hbp)/UE Rp 17,010.00

Harga Satuan Pekerjaan/ Jam ( Jumlah Biaya II + III )


Dibulatkan
jam

Rp 109,300.00
/jam
/jam

/jam
#REF!

/jam

/jam

/jam

/jam

/jam
/jam

/jam

/jam

#REF!
#REF!

jam

Rp 27,469.00
/jam
/jam
/jam

#REF!

/jam

/jam
/jam

/jam

/jam

/jam

/jam

/jam

#REF!
#REF!
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Galian Tanah (AB) (Tanah Biasa)


Satuan/Unit : M3
Analisa : Dihitung

Kuantitas/ HargaSatuan
No. Uraian Satuan Jumlah Harga (RP.)
Koefisien Dasar (Rp.)
(1) (2) (3) (4) (5) (6) = (4) X (5)
A Tenaga Kerja

Sub Jumlah A Rp -
B Bahan

Sub Jumlah B Rp -
C Peralatan
1 Excavator Jam 0.0317 Rp 438,292 Rp 13,894

Sub Jumlah C Rp 13,894


D Sub Jumlah (A + B + C) Rp 13,894
E Overhead + Profit 15% x Sub Jumlah (D) Rp 2,084
Jumlah Harga = (D + E) Rp 15,978
Harga Satuan Pekerjaan (Dibulatkan) 15,900.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Timbunan Tanah Didatangkan Dipadatkan (AB)


Satuan/Unit : M3
Analisa : Dihitung

Kuantitas/ HargaSatuan
No. Uraian Satuan Jumlah Harga (RP.)
Koefisien Dasar (Rp.)
(1) (2) (3) (4) (5) (6) = (4) X (5)
A Tenaga Kerja
1 Pekerja Alat Berat Jam 0.0810 Rp 8,571 Rp 693.98
2 Mandor Alat Berat Jam 0.0202 Rp 11,429 Rp 231.33

Sub Jumlah A Rp 925.30


B Bahan
1 Tanah Timbun m3 1.2000 60,000 Rp 72,000.00

Sub Jumlah B Rp 72,000.00


C Peralatan
1 Bulldozer Jam 0.004 Rp 402,643 Rp 1,505.61
2 Vibrator Roller Jam 0.004 Rp 279,385 Rp 1,168.78

Sub Jumlah C Rp 2,674.39


D Sub Jumlah (A + B + C) Rp 75,599.69
E Overhead + Profit 10% x Sub Jumlah (D) Rp 7,559.97
Jumlah Harga = (D + E) Rp 83,159.66
Harga Satuan Pekerjaan (Dibulatkan) 83,100.00
DAFTAR ANALISA HARGA SATUAN

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1 Penggalian 1 M3 tanah biasa sedalam 1 m
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.750 OH
Mandor L.04 OH 0.025 Err:509
Jumlah Tenaga Kerja:
B BAHAN

Jumlah Harga Bahan:


C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)

A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah


Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.167 OH
Mandor L.04 OH 0.017 Err:509
Jumlah Tenaga Kerja:
B BAHAN

Jumlah Harga Bahan:


C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)

A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 OH
Mandor L.04 OH 0.010 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Pasir Urug M3 1.200 Err:509
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)
Jumlah Harga (RP.)

#VALUE!
Err:509
#VALUE!

Rp -

Rp -
#VALUE!
#VALUE!
#VALUE!

Jumlah Harga (RP.)

#VALUE!
Err:509
#VALUE!

Rp -

Rp -
#VALUE!
#VALUE!
#VALUE!

Jumlah Harga (RP.)

#VALUE!
Err:509
#VALUE!

Err:509
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!
A.2.3.1.8 Pembuangan 1 m3 tanah sejauh 30 meter
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.330 OH
Mandor L.04 OH 0.010 Err:509
Jumlah Tenaga Kerja:
B BAHAN

Jumlah Harga Bahan:


C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 1.500 OH
Tukang L.02 OH 0.750 OH
Kepala Tukang L.03 OH 0.075 OH
Mandor L.04 OH 0.075 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Batu Belah M3 1.200 Err:509
Semen Portland Kg 163.000 Err:509
Pasir Pasang M3 0.520 Err:509
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)
Jumlah Harga (RP.)

#VALUE!
Err:509
#VALUE!

Rp -
Rp -

Rp -
#VALUE!
#VALUE!
#VALUE!

Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!
A.3.2.1.7 Pemasangan 1 m3 aanstamping
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.780 OH
Tukang L.02 OH 0.390 OH
Kepala Tukang L.03 OH 0.039 OH
Mandor L.04 OH 0.039 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Batu Belah M3 1.200 Err:509
Pasir Pasang M3 0.432 Err:509
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.4.1.1.1 Membuat 1 m3 beton mutu F'c = 7,4 Mpa (K100), Slump (12±2) cm, w/c = 0,87
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 OH
Tukang L.02 OH 0.275 OH
Kepala Tukang L.03 OH 0.028 OH
Mandor L.04 OH 0.083 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Semen Portland Kg 247.000 Err:509
Pasir Beton M3 0.869 Err:509
Kerikil (maks 30 mm) M3 0.999 Err:509
Air Ltr 215.000 M3
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)
Catatan:
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling Factor pasir = 20%
Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!

m, w/c = 0,87
Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509
#VALUE!
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!
A.4.1.1.4 Membuat 1 m3 Lantai kerja beton mutu Fc = 7,4 Mpa (K100), Slump (3-6) cm, w/c = 0,87
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 1.200 OH
Tukang L.02 OH 0.200 OH
Kepala Tukang L.03 OH 0.020 OH
Mandor L.04 OH 0.060 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Semen Portland Kg 230.000 Err:509
Pasir Beton Kg 893.000 Err:509
Kerikil (maks 30 mm) Kg 1027.000 Err:509
Air Ltr 200.000 M3
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)

A.4.1.1.4 Membuat 1 m3 beton mutu Fc=14,5 Mpa (K175), Slump (12±2) cm, w/c = 0,66
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 OH
Tukang L.02 OH 0.275 OH
Kepala Tukang L.03 OH 0.028 OH
Mandor L.04 OH 0.083 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Semen Portland Kg 326.000 Err:509
Pasir Beton Kg 760.000 Err:509
Kerikil (maks 30 mm) Kg 1029.000 Err:509
Air Ltr 215.000 M3
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)
p (3-6) cm, w/c = 0,87
Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509
#VALUE!
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!

, w/c = 0,66
Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509
#VALUE!
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!
A.4.1.1.10 Membuat 1 m3 Lantai kerja beton mutu Fc = 21,7 Mpa (K250), Slump (3-6) cm, w/c = 0,56
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 OH
Tukang L.02 OH 0.275 OH
Kepala Tukang L.03 OH 0.028 OH
Mandor L.04 OH 0.083 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Semen Portland Kg 384.000 Err:509
Pasir Beton Kg 692.000 Err:509
Kerikil (maks 30 mm) Kg 1039.000 Err:509
Air Ltr 215.000 M3
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)

A.4.1.1.17.a Pembesian 10 Kg dengan besi polos


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 OH
Tukang Besi L.02 OH 0.070 OH
Kepala Tukang L.03 OH 0.007 OH
Mandor L.04 OH 0.004 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Besi Beton Polos Kg 10.500 Err:509
Kawat Beton Kg 0.150 Err:509
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)
mp (3-6) cm, w/c = 0,56
Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509
#VALUE!
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!

Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!
A.4.1.1.24 Pemasangan 1 m2 bekisting untuk lantai
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 OH
Tukang L.02 OH 0.330 OH
Kepala Tukang L.03 OH 0.033 OH
Mandor L.04 OH 0.033 Err:509
Jumlah Tenaga Kerja:
B BAHAN
Kayu Kelas III M3 0.040 Err:509
Paku 5-10 cm Kg 0.400 Err:509
Minyak Bekisting Ltr 0.200 Err:509
Balok Kayu Kelas II M3 0.015 Err:509
Plywood tebal 9 mm Lbr 0.350 Err:509
Dolken Kayu Ø 8-10 cm - 400 cm Batang 6.000 Err:509
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.2 Pemasangan 1 m2 plesteran 1 SP : 2 PP tebal 15 mm
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 OH
Tukang L.02 OH 0.150 OH
Kepala Tukang L.03 OH 0.015 OH
Mandor L.04 OH 0.015 Err:509
Jumlah Tenaga Kerja:
B BAHAN
1. PC Kg 10.224 Err:509
2. PP M3 0.020 Err:509
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)
Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!

Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!
A.4.4.2.4 Pemasangan 1 m2 plesteran 1 SP : 4 PP tebal 15 mm
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 OH
Tukang L.02 OH 0.150 OH
Kepala Tukang L.03 OH 0.015 OH
Mandor L.04 OH 0.015 Err:509
Jumlah Tenaga Kerja:
B BAHAN
1. PC Kg 6.240 Err:509
2. PP M3 0.024 Err:509
Jumlah Harga Bahan:
C PERALATAN

Jumlah Harga Alat:


D Jumlah (A + B + C)
E Overhead % Profit 10 % x D:
F Harga Satuan Pekerjaan (D + E)
Jumlah Harga (RP.)

#VALUE!
#VALUE!
#VALUE!
Err:509
#VALUE!

Err:509
Err:509
Err:509

Rp -
#VALUE!
#VALUE!
#VALUE!
DAFTAR HARGA UPAH, BAHAN DAN PERALATAN

NO. URAIAN SATUAN HARGA

I DAFTAR TENAGA KERJA


1 Mandor OH Rp 80,000.00
2 Tukang OH Rp 85,000.00
3 Kepala Tukang OH Rp 100,000.00
4 Pekerja OH Rp 55,000.00

II DAFTAR HARGA BAHAN


1 Air M3 Rp 100.00
2 Batu Kali/Gunung M3 Rp 146,000.00
3 Pasir Beton m3 Rp 150,000.00
4 Pasir Pasang M3 Rp 160,000.00
5 Semen PC (zak = 40 kg) Zak Rp 52,000.00
6 Semen/PC (1 Kg) Kg Rp 1,300.00

C. DAFTAR PERALATAN
1 Concrete Mixer Hari Rp 50,000.00

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP

Rizki Maulana
Direktur
JADWAL WAKTU PELAKSANAAN
Nama Penawar CV.MENARA ACEH GROUP
Nama Paket : PENINGKATAN SALURAN SEKUNDER JARINGAN IRIGASI D.I. KRUENG KALA (22 HA) KEC. LHOONG
Kode Paket

BOBOT RENCANA PELAKSANAAN


No URAIAN PEKERJAAN VOL SAT. RENCANA BULAN I BULAN II BULAN III KET.
(%) 1 2 3 4 1 2 3 4 1 2 3 4

I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 1.00 Ls 1,000,000.0 1,000,000.0 0.34% 0.34% 100.0%
2 Uitzet/Pemasangan Profil 1.00 Ls 1,500,000.0 1,500,000.0 0.51% 0.51%
3 Sewa Pondok Kerja/ Gudang 1.00 Ls 3,000,000.0 3,000,000.0 1.01% 1.01%
4 Papan Nama Proyek 1.00 Unit 800,000.0 800,000.0 0.27% 0.27%

II PEKERJAAN EMBUNG
1 Galian Tanah (MP) 119.72 M3 39,000.0 4,669,080.0 1.58% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 50.0%
2 Pasangan Batu 1 : 4 232.75 M3 807,675.0 187,986,356.3 63.47% 9.07% 9.07% 9.07% 9.07% 9.07% 9.07% 9.07%
3 Plesteran 1 : 3 1,511.20 M2 63,000.0 95,205,600.0 32.15% 5.36% 5.36% 5.36% 5.36% 5.36% 5.36%

III PEKERJAAN LAIN-LAIN


1 Administrasi dan Dokumentasi 1.00 Ls 2,000,000.0 2,000,000.0 0.68% 0.34% 0.34% 0.0%

TOTAL BOBOT 296,161,036.25 100.00%

PROGRES RENCANA MINGGUAN (%) 2.465% 9.331% 9.331% 9.331% 9.331% 14.688% 14.688% 14.426% 5.358% 5.358% 5.358% 0.338%

PROGRES RENCANA KUMULATIF MINGGUAN (%) 2.465% 11.795% 21.126% 30.456% 39.787% 54.475% 69.164% 83.589% 88.947% 94.305% 99.662% 100.000%

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP

Rizki Maulana
Direktur
ANALISA TEKNIK
KEGIATAN : REHABILITASI DAN PENINGKATAN JARINGAN IRIGASI (DAK)
PEKERJAAN : PENINGKATAN SALURAN SEKUNDER JARINGAN IRIGASI D.I. KRUENG KALA (22 HA) KEC. LHOONG
LOKASI : KEC. LHOONG - KAB. ACEH BESAR
TAHUN ANGGARAN: 2016

BAHAN TENAGA KERJA PRODUKTIVITAS MASA PELAKSANAAN


NO URAIAN PEKERJAAN VOLUME SAT Koef. Prod. HARI Minggu
KETERANGAN
BAHAN Vol. Sat. Jenis Jlh

I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 1.000 Ls Tidak Ada bahan Pekerja 2 1
Mandor 1

2 Uitzet/Pemasangan Profil 1.000 Ls Tidak Ada bahan Pekerja 1 1


Mandor 1

3 Sewa Pondok Kerja/ Gudang 1.000 Ls Tidak Ada bahan 2

4 Papan Nama Proyek 1.000 Unit Kayu M3 Pekerja 1 1


paku Kg

1 Galian Tanah (MP) 119.720 M3 Tidak Ada bahan Pekerja 2 0.5630 3.55 33.701 6 Disesuaikan dengan
Mandor 1 pek. Psangan batu

2 Pasangan Batu 1 : 4 232.750 M3 Batu belah/ Gunung 279.300 m3 Pekerja 10


Pasir Pasang 121.030 m3 Tukang 5 0.9000 5.56 41.895 7
Semen PC (1 kg) 37,938.250 Kg Kepala Tukang 1
Mandor 1

3 Plesteran 1 : 3 1,511.200 M2 Pasir Pasang 45.336 m3 Pekerja 16


Semen PC (1 kg) 11,751.091 Kg Tukang 8 0.1920 41.67 36.269 6
Kepala Tukang 1

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP

Rizki Maulana
Direktur
JADWAL PENGGUNAAN BAHAN/MATERIAL
Nama Penawar CV.MENARA ACEH GROUP
Nama Paket : PENINGKATAN SALURAN SEKUNDER JARINGAN IRIGASI D.I. KRUENG KALA (22 HA) KEC. LHOONG
Kode Paket

JADWAL PENGGUNAAN BAHAN/MATERIAL


No NAMA MATERIAL JUMLAH SATUAN BULAN I BULAN II BULAN III
1 2 3 4 1 2 3 4 1 2 3 4

II PEKERJAAN EMBUNG
2 Pasangan Batu 1 : 4 232.75 M3
Batu belah/ Gunung 279.30 m3
Pasir Pasang 121.03 m3
Semen PC (1 kg) 37,938.25 Kg

3 Plesteran 1 : 3 1,511.20 M2
Pasir Pasang 45.34 m3
Semen PC (1 kg) 11,751.09 Kg

Banda Aceh, 15 Agustus 2016


CV. MENARA ACEH GROUP

Rizki Maulana
Direktur
PRODUKTIVITAS ALAT BERAT
(GALIAN TANAH BERLUMPUR)

NO URAIAN KODE KOEF SATUAN KET

I ASUMSI
1 Jam Kerja Efektif Tk 7 Jam
2 Faktor Pengembangan Fk 1.250
3 Tahapan Kerja
a. Excavator menggali tanah berlumpur di lokasi
pekerjaan, kemudian diletakkan disekitar daerah galian

II ALAT
a Excavator
Kapasitas Bucket V 0.800 m3
Faktor Bucket Fb 0.800
Faktor Efisiensi Alat Fa 0.600

Waktu Siklus Ts.1 0.750 Menit


Menggali, swing dan membuang disekitar daerah galian T.1 0.583 Menit
Swing kembali dan lain-lain T.2 0.167 Menit
Ts.1 0.750 Menit

Kap. Produksi/jam = (V x Fb x Fa x 60) / (Ts. 1 x Fk) Q.1 24.576 m3/ jam

Koefisiensi Alat / m3 = 1 / Q.1 0.041 jam


PRODUKTIVITAS ALAT BERAT
(TIMBUNAN TANAH HASIL GALIAN DIPADATKAN)

NO URAIAN KODE KOEF SATUAN KET

I ASUMSI
1 Jam kerja efektif per hari Tk 7 Jam
2 Faktor pengembangan tanah Fk 1.250
3 Faktor tanah lepas Fk1
4 Tahapan Kerja
a. Tanah hasil galian dengan menggunakan alat excavator
dilakukan pemadatan dengan menggunakan vibrator
roller

II ALAT
a. Vibrator Roller
Lebar drum W1 1.480 m
Kecepatan maju / mundur V 4.000 Km/Jam
Tebal pemadatan H 0.300 m
Jumlah lintasan N 8.000 Kali
Efisiensi kerja E 0.600 Baik

Lebar efektif = 2,20 m - 0,20 m W 1.000 m

Produksi/jam = (W x V x H x 1000 x E) / N Q5 90.000 m3/jam

Koefisien Alat/m3 = 1 / Q5 0.011 jam

III TENAGA
Produksi / hari = Tk x Q5 Q.1' 630.000 m3/hari
Kebutuhan tenaga
- Pekerja P 3.000 Orang
- Mandor M 1.000 Orang

Koefisien Tenaga / m3
- Pekerja : (Tk x P) : Q.1' 0.033 Jam
- Mandor : (Tk x M) : Q.1' 0.011 Jam