Company Address DAILY PROGRESS REPORT

T: F:

Project Information

Project Name Caltex Station Site Development Works Project No. 001
Town Km 36 SLEX Southbound, Mamplasan, Binan, Laguna Date 15-Dec-17
Contractor Lego Builders Day of Week Friday

Weather Number of Resources (Personnel & Major Equipment)


Weather Clear Personnel Major Plant and Equipment
Temp >30C

TOTAL PERSONNEL
Wind Light

TOTAL PLANT
Humidity Low

Electrician
Carpenter
Foreman

Plumber
Mason

Labor
Contractor / Subcontractors Hours
Lego Builders Inc. 8 2 7 1 1 17 28 0

Location / Area Activity / Description of Work Quantity %Prog


Road 3 and 4 inner Curb and Gutter plain cement finishing 50 m 100 %
Road 2 and 4 junction near STP Backfill and Compaction %
Road 3 outer Curb and Gutter formwork installation %
Road 4 inner Curb and Gutter base coarse laying %
STP walls Formworks %

Hinderance / Effect to Normal Progress (weather, accidents, breakdowns, delays, etc)


1. Submission and approval of additional work areas 2. Delivery of formwork materials for STP 3. Delivery of electrical manhole covers
prior to concreting of PCCP at road 2 and 4 junction

Material Deliveries Official Visitors


Supplier Description Qty Name Surname Representing Time
JC Delos Reyes Lego Builders Inc
Base Coarse Supplier

Report prepared by
Name Surname Position / Title
Henry Florendo Project Manager

This Daily Report was generated using an http://www.online-templatestore.com template.


Plaint cement finish on curb and gutters

Backfill and compaction at road 2 and 4


junction