You are on page 1of 8

Facts:

METROPOLITAN CEBU WATER DISTRICT V.


MACTAN ROCK INDUSTRIES (G.R. NO. 172438) Ray Burton Development Corporation (RBDC) and
William Golangco Construction Corporation
Facts: (WGCC) entered into a Contract for the construction
of the Elizabeth Place (Office/Residential
Petitioner Metropolitan Cebu Water District Condominium).
(MCWD), a government-owned and controlled
corporation, entered into a Water Supply Contract WGCC filed a complaint with a request for arbitration
with herein respondent, Mactan Rock Industries, Inc. with the Construction Industry Arbitration
(MRII), wherein the latter would supply MCWD with Commission (CIAC). In its complaint, private
potable water with a minimum guaranteed annual respondent prayed that CIAC render judgment
volume. Respondent filed a complaint against ordering petitioner to pay private respondent the
MCWD with the CIAC citing the arbitration clause of amount of, to wit:
the contract and seeking the reformation of Clause
17 of the Contract or the Price Escalation/De- 1. P24,703,132.44 for the unpaid balance on
Escalation Clause in order to include Capital Cost the contract price;
Recovery in the price escalation formula. MCWD 2. P10,602,670.25 for the unpaid balance on
filed its Answer, including a motion to dismiss the the labor cost adjustment;
complaint on the ground that CIAC had no
jurisdiction over the case, as the contract was not 3. P9,264,503.70 for the unpaid balance of
one for construction or infrastructure. Petitioner then additive works;
filed two petitions before the CA which were both
4. P2,865,615.10 for extended overhead
denied, hence this petition.
expenses;
Issues:
5. P1,395,364.01 for materials cost
(1) Whether or not CIAC may exercise jurisdiction adjustment and trade contractors' utilities
over disputes arising from a water supply contract; expenses;
and if so,
6. P4,835,933.95 for interest charges on
(2) Whether or not CIAC have a jurisdiction over a unpaid overdue billings on labor cost
complaint praying for a reformation of a water supply adjustment and change orders.
contract.
or for a total of Fifty Three Million Six Hundred Sixty-
Ruling: Seven Thousand Two Hundred Nineteen and 45/xx
(P53,667,219.45) and interest charges based on the
(1) The Court finds in the affirmative. The motion for prevailing bank rates on the foregoing amount from
reconsideration was denied by CA and MCWD March 1, 2002 and until such time as the same shall
never appealed the case. Thus, the decision of the be fully paid.
CA became final and executory. The Court has held
time and again that a final and executory judgment, RBDC filed a Motion to Dismiss the aforesaid
no matter how erroneous, cannot be changed even complaint on the ground of lack of jurisdiction. It is
by this Court. The CA affirming the CIAC’s petitioner's contention that the CIAC acquires
jurisdiction and it becoming final, is now beyond the jurisdiction over disputes arising from or connected
jurisdiction of the Court to review or modify, even with construction contracts only when the parties to
supposing for the sake of argument, that it is indeed the contract agree to submit the same to voluntary
erroneous. arbitration.
(2) Where the law does not delineate, neither should In the contract between petitioner and private
we. Neither the provisions of the Civil Code on respondent, petitioner claimed that only disputes by
reformation of contracts nor the law creating CIAC reason of differences in interpretation of the contract
exclude reformation in its jurisdiction. Therefore, documents shall be deemed subject to arbitration.
because the CIAC has been held to have jurisdiction
Issue:
over the contract, it follows that it has jurisdiction to
order the reformation of the contract as well. whether or not CIAC has jurisdiction over the case.
William Golangco Construction Corporation v. Held:
Ray Burton Development Corporation, G.R. No.
163582, August 9, 2010
CIAC had jurisdiction over the dispute between To affirm a condition precedent in the construction
herein parties contract, which would effectively suspend the
jurisdiction of the CIAC until compliance therewith,
The CIAC has original and exclusive jurisdiction over would be in conflict with the recognized intention of
disputes arising from, or connected with, contracts the law and rules to automatically vest CIAC with
entered into by parties involved in construction in the jurisdiction over a dispute should the construction
Philippines and all that is needed for the CIAC to contract contain an arbitration clause.
acquire jurisdiction is for the parties to agree to
submit the same to voluntary arbitration. Moreover, the CIAC was created in recognition of
the contribution of the construction industry to
Respondent's contention, that the only disputes it national development goals.
agreed to submit to voluntary arbitration are those
arising from interpretation of contract documents Realizing that delays in the resolution of construction
and it argued that the claims alleged in petitioner's industry disputes would also hold up the
complaint are not disputes arising from interpretation development of the country, Executive Order No.
of contract documents, hence, the CIAC cannot 1008 expressly mandates the CIAC to expeditiously
assume jurisdiction over the case, is tenuous. settle construction industry disputes and, for this
purpose, vests in the CIAC original and exclusive
The contract between herein parties contained an jurisdiction over disputes arising from, or connected
arbitration clause which mean that parties agreed to with, contracts entered into by the parties involved in
submit disputes arising by reason of differences in construction in the Philippines.
interpretation of the contract to a Board of Arbitrators
the composition of which is mutually agreed upon by Thus, there is no question that in this case, the CIAC
the parties, and, as a last resort, any other dispute properly took cognizance of petitioner's complaint as
which had not been resolved by the Board of it had jurisdiction over the same.
Arbitrators shall be submitted to the Construction
Arbitration Authority created by the government, STRONGHOLD INSURANCE COMPANY v. SPS.
which is no other than the CIAC. RUNE AND LEA STROEM, GR No. 204689, 2015-
01-21
Moreover, other matters not dealt with by provisions
of the contract or by special agreements shall be Facts:
governed by provisions of the Construction Industry This case involves the proper invocation of the
Arbitration Law, or Executive Order No. 1008. Construction Industry Arbitration Committee's
Petitioner's claims that it is entitled to payment for (CIAC) jurisdiction through an arbitration clause in a
several items under their contract, which claims are, construction contract.
in turn, refuted by respondent, involves a "dispute Spouses Rune and Lea Stroem (Spouses Stroem)
arising from differences in interpretation of the entered into an Owners-Contractor Agreement[4]
contract. with Asis-Leif & Company, Inc. (Asis-Leif) for the
Under Section 1, Article III of the CIAC Rules, an construction of a two-storey house on the lot owned
arbitration clause in a construction contract shall be by Spouses Stroem.
deemed as an agreement to submit an existing or Antipolo, Rizal
future controversy to CIAC jurisdiction,
"notwithstanding the reference to a different Asis-Leif secured Performance Bond No.
arbitration institution or arbitral body in such contract LP/G(13)83056 in the amount of P4,500,000.00
x x x." Elementary is the rule that when laws or rules from Stronghold Insurance Company, Inc.
are clear, it is incumbent on the court to apply them. (Stronghold).
When the law (or rule) is unambiguous and
Stronghold and Asis-Leif, through Ms. Ma. Cynthia
unequivocal, application, not interpretation thereof,
Asis-Leif,... bound themselves jointly and severally
is imperative.
to pay the Spouses Stroem the agreed amount in the
It bears to emphasize that the mere existence of an event that the construction project is not completed
arbitration clause in the construction contract is
Asis-Leif failed to finish the project on time despite
considered by law as an agreement by the parties to
repeated demands of the Spouses Stroem
submit existing or future controversies between
them to CIAC jurisdiction, without any qualification Spouses Stroem subsequently rescinded the
or condition precedent. agreement.
Appraiser Asian Appraisal Company, Inc.'s to a construction contract and, therefore, falls under
evaluation resulted in the following percentage of the exclusive jurisdiction of the CIAC.
completion
The issues for consideration are:
On April 5, 2001, Stronghold sent a letter to Asis-Leif
requesting that the company settle its obligations (1)
with the Spouses Stroem. No response was Whether the dispute involves a construction
received from Asis-Leif. contract;
Spouses Stroem filed a Complaint (with Prayer for (2)
Preliminary Attachment)[13] for breach of contract
and for sum of money with a claim for damages Whether the CIAC has exclusive jurisdiction over the
against Asis-Leif, Ms. Cynthia Asis-Leif, and controversy between the parties;
Stronghold.
(3)
Only Stronghold was served summons.
Whether the Regional Trial Court should have
Regional Trial Court rendered a judgment in favor of dismissed the petition outright as required by law
the Spouses Stroem. and jurisprudence and referred the matter to the
CIAC; and
The trial court ordered Stronghold to pay the
Spouses Stroem ?4,500,000.00 with 6% legal (4)
interest from the time of first demand
Whether petitioner Stronghold Insurance Company,
Both Stronghold and the Spouses Stroem appealed Inc. is liable under Performance Bond No.
to the Court of Appeals. LP/G(13)83056.
The Court of Appeals affirmed with modification the (a)
trial court's Decision. It increased the amount of
Whether petitioner Stronghold Insurance Company,
attorney's fees to ?50,000.00.
Inc. is only liable as to the extent of any additional
On March 20, 2013, this court required the Spouses cost for the completion of the project due to any
Stroem to submit their Comment on the Petition. increase in prices for labor and materials.
Stronghold argues that the trial court did not acquire (b)
jurisdiction over the case and, therefore, the Court of
Whether the case involves ordinary suretyship or
Appeals committed reversible error when it upheld
corporate suretyship.
the Decision of the Regional Trial Court... he lower
courts should have dismissed the... case in view of On forum-shopping
the arbitration clause in the agreement
On arbitration and the CIAC's jurisdiction
Moreover, "the stipulations in said Agreement are
part and parcel of the conditions in the bond. Were What is at issue in this case is the parties'
it not for such stipulations in said agreement, agreement, or lack thereof, to submit the case to
[Stronghold] would not have agreed to issue a bond arbitration. Respondents argue that petitioner is not
in favor of the Spouses Stroem. a party to the arbitration agreement. Petitioner did
not consent to arbitration. It is only respondent and
On the other hand, the Spouses Stroem argue that
Stronghold committed forum shopping warranting Asis-Leif that may invoke the arbitration clause in the
dismissal of the case. contract.

According to the Spouses Stroem, Stronghold Ruling:


deliberately committed forum shopping when it filed this court resolves to deny the Petition.
the present petition despite the... pendency of the
Spouses Stroem's Motion for Partial Records show that petitioner received a copy of the
Reconsideration of the Court of Appeals Decision Decision of the Court of Appeals on December 5,
dated November 20, 2012. 2012.
Issues: Petitioner did not file a Motion for Reconsideration of
the assailed Decision.
The main issue here is whether the dispute liability
of a surety under a performance bond is... connected It filed before this court a Motion for Extension of
Time To File Petition for Review Petitioner, thus, cannot invoke the jurisdiction of the
CIAC.
Respondents filed their Motion for Partial
Reconsideration of the Court of Appeals Decision on where a surety in a construction contract actively
December 11, 2012. participates in a collection suit, it is estopped from
raising jurisdiction later.
Respondents alleged in their Comment that as early
as January 9, 2013, petitioner received a copy of the Assuming that petitioner is privy to the construction
Court of Appeals' Resolution requiring Comment on agreement, we cannot allow petitioner to invoke
the Motion for Partial Reconsideration... petitioner arbitration at this late... stage of the proceedings
did not disclose in its since to do so would go against the law's goal of
prompt resolution of cases in the construction
Verification and Certification Against Forum industry.
Shopping the pendency of respondents' Motion for
Partial Reconsideration. petition is DENied
Indeed, petitioner is guilty of forum shopping. Principles:
Petitioner failed to carry out its duty of promptly There is forum shopping when: as a result of an
informing this court of any pending action or adverse opinion in one forum, a party seeks a
proceeding before this court, the Court of Appeals, favorable opinion (other than by appeal or certiorari)
or any other tribunal or agency. This court cannot in another.
countenance petitioner's disregard of the rules.
The principle applies not only with respect to suits
On this basis, this case should be dismissed filed in the courts but also in connection with
litigations commenced in the... courts while an
Petitioner... raised the issue of lack of jurisdiction in administrative proceeding is pending... elements of
view of an arbitration agreement for the first time. forum-shopping: "(a) identity of parties, or at least
Petitioner and respondents recognize that CIAC has such parties as represent the same interests in both
jurisdiction over disputes arising from the actions; (b) identity of rights asserted and reliefs
agreement. prayed for, the reliefs being founded on the same
facts; and (c) the identity... with respect to the two
This court, however, cannot apply the ruling in preceding particulars in the two cases is such that
Prudential to the present case. Several factors any judgment rendered in the pending cases,
militate against petitioner's claim. regardless of which party is successful, amount to
res judicata in the other case."
The contractual stipulations in this case and in
Prudential are different Rule 42, Section 2[45] in relation to Rule 45, Section
4 of the Rules of Court mandates petitioner to submit
This court in Prudential held that the construction
a Certification Against Forum Shopping and
contract expressly incorporated the performance
promptly inform this court about the pendency of any
bond into the contract.[79] In the present case,
similar action or proceeding before other courts or...
Article 7 of the Owners-Contractor Agreement
tribunals.
merely stated that a performance bond shall be...
issued in favor of respondents, in which case The rule's purpose is to deter the unethical practice
petitioner and Asis-Leif Builders and/or Ms. Ma. of pursuing simultaneous remedies in different
Cynthia Asis-Leif shall pay P4,500,000.00 in the forums, which "wreaks havoc upon orderly judicial
event that Asis-Leif fails to perform its duty under the procedure."
Owners-Contractor Agreement.
Failure to comply with the rule is a sufficient ground
Consequently, the... performance bond merely for the... dismissal of the petition... u]ltimately, what
referenced the contract entered into by respondents is truly important to consider in determining whether
and Asis-Leif, which pertained to Asis-Leif's duty to forum-shopping exists or not is the vexation caused
construct a two-storey residence building with attic, the courts and parties-litigant by a party who asks
pool, and landscaping over respondents' property different courts and/or administrative agencies to
rule on the same or related causes... and/or to grant
Owners-Contractor Agreement that the arbitration
the same or substantially the same reliefs, in the
clause is found.
process creating the possibility of conflicting
Not being a party to the construction agreement, decisions being rendered by the different fora upon
petitioner cannot invoke the arbitration clause. the same issue.
Generally, parties may not raise issues for the first doubtful ones that sense which may result from all of
time on appeal.[50] Such practice is violative of the them taken jointly
rules and due process and is frowned upon by the
courts. However, it is also well-settled that 365 SCRA, 697, G.R. No. 141897 September 24,
jurisdiction can never be waived or... acquired by 2001 METRO CONSTRUCTION, INC., petitioner,
estoppel.[51] Jurisdiction is conferred by the vs. CHATHAM PROPERTIES, INC., respondent.
Constitution or by law.[52] "Lack of jurisdiction of the
court over an action or the subject matter of an FACTS:
action cannot be cured by the silence, by Respondent Chatham Properties, Inc. (CHATHAM)
acquiescence, or... even by express consent of the and petitioner Metro Construction, Inc. (MCI)
parties. entered into a contract for the construction of a multi-
In Heunghwa Industry Co., Ltd., v. DJ Builders storey building known as the Chatham House.
Corporation,[55] this court held that "there are two In April 1998, MCI sought to collect from CHATHAM
acts which may vest the CIAC with jurisdiction over a sum of money for unpaid progress billings and
a construction dispute. One is the presence of an other charges and instituted a request for
arbitration clause in a construction... contract, and adjudication of its claims with the CIAC. The
the other is the agreement by the parties to submit preliminary conference before the CIAC started in
the dispute to the CIAC."... when a dispute arises June 1998 and was concluded a month after with the
from a construction contract, the CIAC has exclusive signing of the Terms of Reference (TOR) of the
and original jurisdiction. Case.
This court has previously held that a performance In the meantime, the TOR was amended and
bond, which is meant "to guarantee the supply of finalized on 19 August 1998. The facts, as admitted
labor, materials, tools, equipment, and necessary by the parties before the CIAC and incorporated in
supervision to complete the project[,]"[59] is the original TOR, are as follows :
significantly and substantially connected to the
construction... contract and, therefore, falls under 1. On 21 April 1994, the parties formally
the jurisdiction of the CIAC entered into a contract for the construction of the
"Chatham House" . . . for the contract price of price
Prudential Guarantee and Assurance Inc. v. Anscor of P50,000,000.00
Land, Inc.
2. On 12 July 1994, a Supplemental Contract
Although not the construction contract itself, the was executed by and between the parties whereby
performance bond is deemed as an associate of the CHATHAM authorized MCI to procure in behalf of
main construction contract that it cannot be the former materials, equipment, etc.
separated or severed from its principal.
3. Under Section I.04 of the Supplemental
The Performance Bond is significantly and Contract, the total amount of procurement and
substantially connected to the... construction transportation cost[s] and expenses which may be
contract that there can be no doubt it is the CIAC, reimbursed by MCI from CHATHAM shall not
under Section 4 of EO No. 1008, which has exceed the amount of P75, 000,000.00.
jurisdiction over any dispute arising from or
connected with it. 4. In the course of the construction, Change
Orders No. 1, 4, 8A, 11, 12 and 13 were
It is settled that the surety's solidary obligation for the implemented,
performance of the principal debtor's obligation is
indirect and merely secondary.[73] Nevertheless, 5. CHATHAM reimbursed MCI the amount of
the surety's liability to the "creditor or promisee of the P60,000.00 corresponding to bonuses advanced to
principal is said to be direct,... primary and absolute; its workers by the latter for the 14th, 16th, and 17th
in other words, he is directly and equally bound with floors.
the principal.
6. CHATHAM's payments to MCI totaled
'complementary-contracts-construed-together' P104,875,792.37, representing payments for
doctrine... an accessory contract must be read in its portions of MCI's progress billings and x x x
entirety and together with the principal agreement." additional charges..
ART. 1374. The various stipulations of a contract In the resolution of these issues, the CIAC
shall be interpreted together, attributing to the discovered significant data, which were not evident
or explicit in the documents and records but Court of Appeals, and whether appeals from CISC
otherwise revealed or elicited during the hearings, awards are no longer confined to questions of law.
which the CIAC deemed material and relevant to the
complete adjudication of the case Through Circular No. 1-91, the Supreme Court
intended to establish a uniform procedure for the
The CIAC disposed of the specific money claims by review of the final orders or decisions of the Court of
either granting or reducing them. On Issue No. 9, Tax Appeals and other quasi judicial. The Circular
i.e., whether CHATHAM failed to complete and/or designated the Court of Appeals as the reviewing
deliver the project within the approved completion body to resolve questions of fact or of law or mixed
period and, if so, whether CHATHAM is liable for questions of fact and law.
liquidated damages and how much.
It is clear that Circular No. 1-91 covers the CIAC. In
the first place, it is a quasi judicial agency. In the
second place, the language of Section 1 of Circular
CIAC rendered Judgment in favor of the Claimant No. 1-91 emphasizes the obvious inclusion of the
[MCI] directing Respondent [CHATHAM] to pay CIAC even if it is not named in the enumeration of
Claimant [MCI] the net sum of SIXTEEN MILLION quasi-judicial agencies. In sum, under Circular No.
ONE HUNDRED TWENTY SIX THOUSAND NINE 1-91, appeals from the arbitral awards of the CIAC
HUNDRED TWENTY TWO & 91/100 may be brought to the Court of Appeals, and not to
(16,126,922.91) PESOS. Impugning the decision of the Supreme Court alone. The grounds for the
the CIAC, CHATHAM instituted a petition for review appeal are likewise broadened to include appeals on
with the Court of Appeals questions of facts and appeals involving mixed
questions of fact and law

In upholding the decision of the CIAC, the Court of


Appeals confirmed the jurisprudential principle that The jurisdiction of the Court of Appeals over appeals
absent any showing of arbitrariness, the CIAC's from final orders or decisions of the CIAC is further
findings as an administrative agency and quasi fortified by the amendments to B.P. Blg. 129, as
judicial body should not only be accorded great introduced by RA. No. 7902. With the amendments,
respect but also given the stamp of finality. However the Court of Appeals is vested with appellate
the Court of Appeals found exception in the CIAC's jurisdiction over all final judgments, decisions,
disquisition of Issue No.9 on the matter of liquidated resolutions, orders or awards of Regional Trial
damages. Courts and quasi-judicial agencies,
ISSUE: instrumentalities, boards or commissions, except
"those within the appellate jurisdiction of the
WON under existing law and rules the Court of Supreme Court in accordance with the Constitution,
Appeals can also review findings of facts of the the Labor Code of the Philippines under Presidential
Construction Industry Arbitration Commission Decree No. 442, as amended, the provisions of this
(CIAC) Act, and of subparagraph (1) of the third paragraph
and subparagraph (4) of the fourth paragraph of
HELD:
Section 17 of the Judiciary Act of 1948.".
EO. No. 1008 vest upon the CIAC original and
In view of all the foregoing, The Supreme Court
exclusive jurisdiction over disputes arising from, or
rejects MCI's submission that Circular No. 1-91, B.P.
connected with, contracts entered into by parties
Blg. 129, as amended by RA. 7902, Revised
involved in construction in the Philippines, whether
Administrative Circular 1-95, and Rule 43 of the
the dispute arises before or after the completion of
1997 Rules of Civil Procedure failed to efficaciously
the contract, or after the abandonment or breach
modify the provision on appeals in E.O. No. 1008.
thereof. By express provision of Section 19 thereof,
the arbitral award of the CIAC is final and
unappealable, except on questions of law, which are
appealable to the Supreme Court.
The parties, however, disagree on whether the
subsequent Supreme Court issuances on appellate
procedure and R.A. No. 7902 removed from the
Supreme Court its appellate jurisdiction in Section
19 of E.O. No. 1008 and vested the same in the
NATIONAL IRRIGATION ADMINISTRATION Hence, the present Petition for Certiorari and
(NIA), petitioner, vs. HONORABLE COURT OF Prohibition with urgent prayer for Temporary
APPEALS (4th Division), CONSTRUCTION Restraining Order and Writ of Preliminary Injunction.
INDUSTRY ARBITRATION COMMISSION, and
HYDRO RESOURCES CONTRACTORS ISSUE:
CORPORATION, respondents. 318 SCRA 255, Whether or not CIAC has jurisdiction to hear and try
G.R. 129169 the dispute between the parties?
FACTS: ARGUMENTS:
In a competitive bidding held by Petitioner NIA, Petitioner NIA alleged that CIAC has no jurisdiction
Hydro Resources Contractors Corporation to hear and try the dispute between the parties as
(HYDRO) was awarded Contract for the construction EO No. 1008 had no retroactive effect. It contended
of the main civil works of the Magat River Multi- that there was no agreement with Respondent
Purpose Project. HYDRO to submit the dispute to CIAC for arbitration
The contract provided that Respondent HYDRO considering that the construction contract was
would be paid partly in Philippine pesos and partly in executed in 1978 and the project completed in 1982,
U.S. dollars. Respondent HYDRO substantially whereas the Construction Industry Arbitration Law
completed the works under the contract in 1982 and creating CIAC was signed only in 1985; and that
final acceptance by Petitioner NIA was made in while they have agreed to arbitration as a mode of
1984. settlement of disputes, they could not have
contemplated submission of their disputes to CIAC.
Respondent HYDRO thereafter determined that it
still had an account receivable from Petitioner NIA Petitioner NIA further argued that records show that
representing the dollar rate differential of the price it had not voluntarily submitted itself to arbitration by
escalation for the contract. CIAC.

After unsuccessfully pursuing its case with Petitioner Petitioner NIA contended that the CIAC did not
NIA, Respondent HYDRO filed with the CIAC a acquire jurisdiction over the dispute since it was only
Request for Adjudication of the aforesaid claim. Respondent HYDRO that requested for arbitration.
Petitioner NIA filed its Answer wherein it questioned It asserts that to acquire jurisdiction over a case, as
the jurisdiction of the CIAC alleging lack of cause of provided under E.O. 1008, the request for arbitration
action, laches and estoppel in view of Respondent filed with CIAC should be made by both parties, and
HYDRO’s alleged failure to avail of its right to submit hence the request by one party is not enough.
the dispute to arbitration within the prescribed period RULING:
as provided in the contract.
YES. Contrary to the claim of Petitioner NIA, the
Later, Petitioner NIA filed a Motion to Dismiss CIAC has jurisdiction over the controversy. The
alleging lack of jurisdiction over the disputes. The instant Petition is DISMISSED for lack of merit.
arbitral body constituted by both parties issued an
order which deferred the determination of the Motion RATIO DECIDENDI:
to Dismiss and resolved to proceed with the hearing
EO No. 1008, otherwise known as the “Construction
of the case on the merits as the grounds cited by
Industry Arbitration Law” which was promulgated on
Petitioner NIA did not seem to be “indubitable.”
4 February 1985, vests upon CIAC original and
Petitioner NIA filed a Motion for Reconsideration of exclusive jurisdiction over disputes arising from, or
the aforesaid Order. CIAC in denying the Motion for connected with contracts entered into by parties
Reconsideration ruled that it has jurisdiction over the involved in construction in the Philippines, whether
Respondent HYDRO’s claim over Petitioner NIA the dispute arises before or after the completion of
pursuant to E.O 1008 and that the hearing should the contract, or after the abandonment or breach
proceed as scheduled. thereof.
CIAC then rendered a decision in the main case in The disputes may involve government or private
favor of Respondent HYDRO. Petitioner NIA filed contracts. For the Board to acquire jurisdiction, the
with the CA an Original Action of Certiorari and parties to a dispute must agree to submit the same
Prohibition with prayer for Restraining Order and/or to voluntary arbitration.
Injunction which dismissed the same.
The complaint of Respondent HYDRO against
Petitioner NIA on the basis of the contract executed
between them was filed on 7 December 1994, during to enter into a submission agreement before
the effectivity of E.O. No. 1008. the claimant may invoke the jurisdiction of
CIAC.
Hence, it is well within the jurisdiction of CIAC. The
jurisdiction of a court is determined by the law in Under the present Rules of Procedure, for a
force at the time of the commencement of the action. particular construction contract to fall within the
jurisdiction of CIAC, it is merely required that the
Petitioner NIA’s argument that CIAC had no parties agree to submit the same to voluntary
jurisdiction to arbitrate on contract which preceded arbitration.
its existence is untenable.
Unlike in the original version of Section 1, as applied
E.O. 1008 is clear that the CIAC has jurisdiction over in the Tesco case, the law as it now stands does not
all disputes arising from or connected with provide that the parties should agree to submit
construction contract whether the dispute arises disputes arising from their agreement specifically to
BEFORE or AFTER the completion of the contract. the CIAC for the latter to acquire jurisdiction over the
Thus, the date the parties entered into a contract and same.
the date of completion of the same, even if these Rather, it is plain and clear that as long as the parties
occurred before the constitution of the CIAC, did not agree to submit to voluntary arbitration, regardless
automatically divest the CIAC of jurisdiction as long of what forum they may choose, their agreement will
as the dispute submitted for arbitration arose after fall within the jurisdiction of the CIAC, such that,
the constitution of the CIAC. Stated differently, the even if they specifically choose another forum, the
jurisdiction of CIAC is over the dispute, not the parties will not be precluded from electing to submit
contract; and the instant dispute having arisen when their dispute before the CIAC because this right has
CIAC was already constituted, the arbitral board was been vested upon each party by law, i.e., E.O. No.
actually exercising current, not retroactive, 1008.
jurisdiction.
Moreover, it is undeniable that Petitioner NIA agreed
It is undisputed that the contracts between to submit the dispute for arbitration to the CIAC.
Respondent HYDRO and Petitioner NIA contained
an arbitration clause wherein they agreed to submit Petitioner NIA through its counsel actively
to arbitration any dispute between them that may participated in the arbitration proceedings by filing
arise before or after the termination of the an Answer with Counterclaim, as well as its
agreement. compliance wherein it nominated arbitrators to the
proposed panel, participating in the deliberations on,
Consequently, the claim of Respondent HYDRO and the formulation of, the Terms of Reference of
having arisen from the contract is arbitrable. the arbitration proceeding, and examining the
Petitioner NIA’s reliance with the ruling on the case documents submitted by Respondent HYDRO after
of Tesco Services Incorporated v. Vera, is Petitioner NIA asked for the originals of the said
misplaced. documents.
The 1988 CIAC Rules of Procedure which were
applied by this Court in the Tesco case had been
duly amended by CIAC Resolutions No. 2-91 and 3-
93, Section 1 of Article III of which read as follows:
Submission to CIAC Jurisdiction — An
arbitration clause in a construction contract
or a submission to arbitration of a
construction contract or a submission to
arbitration of a construction dispute shall be
deemed an agreement to submit an existing
or future controversy to CIAC jurisdiction,
notwithstanding the reference to a different
arbitration institution or arbitral body in such
contract or submission.
When a contract contains a clause for the
submission of a future controversy to
arbitration, it is not necessary for the parties

You might also like