You are on page 1of 7

ADR: PART 4 CASES Arbitrator Asuncion ruled in favor of private

respondent Roblecor and further declared the


CHUNG FU vs. CA award final and unappealable, pursuant to the
arbitration agreement.
FACTS: Petitioner Chung Fu Industries and private
respondent Roblecor Philippines, Inc. forged a On the other hand, Chung Fu moved to remand the
construction agreement whereby respondent case for further hearing and asked for a
contractor committed to construct and finish on reconsideration of the judgment award claiming
December 31, 1989, petitioner corporation's that Arbitrator Asuncion committed twelve (12)
industrial/factory complex in Tanawan, Tanza, instances of grave error by disregarding the
Cavite for and in consideration of P42,000,000.00. It provisions of the parties' contract. RTC denied
was stipulated therein that the issue(s) shall be petitioner’s motion to remand and granted private
submitted for resolution before a single arbitrator respondent Roblecor’s motion for writ of Execution.
chosen by both parties in the event of disputes CA also denied petitioner’s motion to remand.
arising from the performance of subject contract.
Moreso, Chung Fu and Roblecor entered into two ISSUE:
(2) other ancillary contracts, to wit: one, for the 1. WON the subject arbitration award is beyond the
construction of a dormitory and support facilities; ambit of the court’s power of judicial review
and the other for the installation of electrical, water 2. WON respondent court committed grave abuse
and hydrant systems at the plant site and requiring of discretion
completion thereof one month after civil works
have been finished. HELD:
1. No. It is stated explicitly under Art. 2044 of the
However, respondent Roblecor failed to complete Civil Code that the finality of the arbitrators' award
the work despite the extension of time allowed it by is not absolute and without exceptions. Where the
Chung Fu. Subsequently, the latter had to take over conditions described in Articles 2038, 2039 and
the construction when it had become evident that 2040 applicable to both compromises and
Roblecor was not in a position to fulfill its arbitrations are obtaining, the arbitrators' award
obligation. may be annulled or rescinded. Additionally, under
Sections 24 and 25 of the Arbitration Law, there are
Claiming an unsatisfied account of P10,500,000.00 grounds for vacating, modifying or rescinding an
and unpaid progress billings of P2,370,179.23, arbitrator's award. Thus, if and when the factual
Roblecor filed a petition for Compulsory Arbitration circumstances referred to in the above-cited
before respondent RTC, pursuant to the arbitration provisions are present, judicial review of the award
clause in the construction agreement. Chung Fu is properly warranted.
moved to dismiss the petition and further prayed
for the quashing of the restraining order. In practice nowadays, absent an agreement of the
parties to resolve their disputes via a particular
Subsequent negotiations between the parties mode, it is the regular courts that remain the fora
eventually led to the formulation of an arbitration to resolve such matters. However, the parties may
agreement which includes -- “decision of the opt for recourse to third parties, exercising their
arbitrator shall be final and unappealable , basic freedom to "establish such stipulation,
therefore there shall be no further judicial recourse clauses, terms and conditions as they may deem
if either party disagrees with the whole or any part convenient, provided they are not contrary to law,
of the arbitrator’s award, but can seek judicial morals, good customs, public order or public
assistance for purposes of enforcing of the policy." In such a case, resort to the arbitration
arbitrator’s award. process may be spelled out by them in a contract in
anticipation of disputes that may arise between
The RTC approved the arbitration agreement. The them. Or this may be stipulated in a submission
appointed sole arbitrator is Engr. Asuncion. agreement when they are actually confronted by a
dispute. Whatever be the case, such recourse to an
extrajudicial means of settlement is not intended to
completely deprive the courts of jurisdiction. In fact, special civil action of certiorari, the Court will not
the early cases on arbitration carefully spelled out engage in a review of the facts found nor even of
the prevailing doctrine at the time, thus: ". . . a the law as interpreted or applied by the arbitrator
clause in a contract providing that all matters in unless the supposed errors of fact or of law are so
dispute between the parties shall be referred to patent and gross and prejudicial as to amount to a
arbitrators and to them alone is contrary to public grave abuse of discretion or an exces de pouvoir on
policy and cannot oust the courts of Jurisdiction." the part of the arbitrator." Even decisions of
administrative agencies which are declared "final"
But certainly, the stipulation to refer all future by law are not exempt from judicial review when so
disputes to an arbitrator or to submit an ongoing warranted.
dispute to one is valid. Being part of a contract
between the parties, it is binding and enforceable in It should be stressed, too, that voluntary
court in case one of them neglects, fails or refuses arbitrators, by the nature of their functions, act in a
to arbitrate. Going a step further, in the event that quasi-judicial capacity. It stands to reason,
they declare their intention to refer their therefore, that their decisions should not be beyond
differences to arbitration first before taking court the scope of the power of judicial review of this
action, this constitutes a condition precedent, such Court.
that where a suit has been instituted prematurely,
the court shall suspend the same and the parties 2. YES, there is a grave abuse of discretion.
shall be directed forthwith to proceed to
arbitration. In the case at bar, petitioners assailed the arbitral
award on the following grounds, most of which
A court action may likewise be proven where the allege error on the part of the arbitrator in granting
arbitrator has not been selected by the parties. compensation for various items which apparently
are disputed by said petitioners. After closely
Under present law, may the parties who agree to studying the list of errors, as well as petitioners’
submit their disputes to arbitration further provide discussion of the same in their Motion to Remand
that the arbitrators' award shall be final, Case For Further Hearing and Reconsideration and
unappealable and executory? Article 2044 of the Opposition to Motion for Confirmation of Award,
Civil Code recognizes the validity of such stipulation, we find that petitioners have amply made out a
thus: Any stipulation that the arbitrators' award or case where the voluntary arbitrator failed to apply
decision shall be final is valid, without prejudice to the terms and provisions of the Construction
Articles 2038, 2039 and 2040. Agreement which forms part of the law applicable
as between the parties, thus committing a grave
Similarly, the Construction Industry Arbitration Law abuse of discretion. Furthermore, in granting
provides that the arbitral award "shall be final and unjustified extra compensation to respondent for
inappealable except on questions of law which shall several items, he exceeded his powers — all of
be appealable to the Supreme Court." which would have constituted ground for vacating
the award under Section 24 (d) of the Arbitration
What if courts refuse or neglect to inquire into the Law.
factual milieu of an arbitrator's award to determine
whether it is in accordance with law or within the But the respondent trial court's refusal to look into
scope of his authority? How may the power of the merits of the case, despite prima facie showing
judicial review be invoked? This is where the proper of the existence of grounds warranting judicial
remedy is certiorari under Rule 65 of the Revised review, effectively deprived petitioners of their
Rules of Court. It is to be borne in mind, however, opportunity to prove or substantiate their
that this action will lie only where a grave abuse of allegations. In so doing, the trial court itself
discretion or an act without or in excess of committed grave abuse of discretion. Likewise, the
jurisdiction on the part of the voluntary arbitrator is appellate court, in not giving due course to the
clearly shown. For "the writ of certiorari is an extra- petition, committed grave abuse of discretion.
ordinary remedy and that certiorari jurisdiction is Respondent courts should not shirk from exercising
not to be equated with appellate jurisdiction. In a their power to review, where under the applicable
laws and jurisprudence, such power may be The CA granted the petition for certiorari, ruling
rightfully exercised; more so where the objections that the CIAC had no jurisdiction over the subject
raised against an arbitration award may properly matter of the case because the parties agreed that
constitute grounds for annulling, vacating or only disputes regarding differences in interpretation
modifying said award under the laws on arbitration. of the contract documents shall be submitted for
arbitration, while the allegations in the complaint
make out a case for collection of sum of money.
WILLIAM GOLANGCO CONSTRUCTION (WGCC) vs.
RAY BURTON DEV’T CORP (RBDC) ISSUE:
1. won the CA acted with grave abuse of discretion
FACTS: Petitioner RBDC and private respondent in failing to dismiss the petition for certiorari filed
WGCC entered into a Contract for the construction by herein respondent, in view of the latter's failure
of the Elizabeth Place (Office/Residential to file a motion for reconsideration of the assailed
Condominium). Private respondent WGCC filed a CIAC Order and for failure to attach to the petition
complaint with a request for arbitration with the the relevant pleadings in CIAC Case No. 13-2002
Construction Industry Arbitration Commission
(CIAC), seeking to collect P53,667,219.45 and 2. WON the the CIAC has jurisdiction over the case
interest charges.
HELD:
Petitioner RBDC filed a Motion to Dismiss the 1. YES. Petitioner is correct that it was grave error
aforesaid complaint on the ground of lack of for the CA to have given due course to respondent's
jurisdiction. It is petitioner's contention that the petition for certiorari despite its failure to attach
CIAC acquires jurisdiction over disputes arising from copies of relevant pleadings in CIAC Case No. 13-
or connected with construction contracts only when 2002. (See Sec. 1, Rule 65, in relation to Sec. 3, Rule
the parties to the contract agree to submit the 46, of the Revised Rules of Court)
same to voluntary arbitration. In the contract
between petitioner and private respondent, The afore-quoted provisions are plain and
petitioner claimed that only disputes by reason of unmistakable. Failure to comply with the
differences in interpretation of the contract requirement that the petition be accompanied by a
documents shall be deemed subject to arbitration. duplicate original or certified true copy of the
judgment, order, resolution or ruling being
Private respondent averred that the claims set forth challenged is sufficient ground for the dismissal of
in the complaint require contract interpretation and said petition.
are thus cognizable by the CIAC pursuant to the
arbitration clause in the construction contract In the present case, herein petitioner strongly
between the parties. Moreover, even assuming that argued against the CA's granting due course to the
the claims do not involve differing contract petition, pointing out that pertinent pleadings have
interpretation, they are still cognizable by the CIAC not been attached to the petition. Herein
as the arbitration clause mandates their direct filing respondent (petitioner before the CA) argued that it
therewith. The CIAC denied RBDC’s motion to did not deem such pleadings or documents
dismiss, saying that the bare agreement to submit a germane to the petition. However, in the CA
construction to dispute to arbitration vests in the Resolution the appellate court itself revealed the
Commission original and exclusive jurisdiction by necessity of such documents by ordering the
virtue of Sec. 4 E.O. No. 1008. submission of copies of pleadings relevant to the
petition. Indeed, such pleadings are necessary for a
Petitioner RBDC filed with the CA a petition for judicious resolution of the issues raised in the
Certiorari and Prohibition contending that CIAC petition and should have been attached thereto. As
acted without or in excess of its jurisdiction when it mandated by the rules, the failure to do so is
issued the questioned order despite the clear sufficient ground for the dismissal of the petition.
showing that there is lack of jurisdiction on the
issue submitted by private respondent for The CA did not give any convincing reason why the
arbitration. rule regarding requirements for filing a petition
should be relaxed in favor of herein respondent. the matter of ascertaining the duties and
Therefore, it was error for the CA to have given due obligations of the parties under their contract all
course to the petition for certiorari despite herein involve interpretation of the provisions of the
respondent's failure to comply with the contract. Therefore, if the parties cannot see eye to
requirements set forth in Section 1, Rule 65, in eye regarding each other’s obligations, i.e., the
relation to Section 3, Rule 46, of the Revised Rules extent of work to be expected from each of the
of Court. parties and the valuation thereof, this is properly a
dispute arising from differences in the
2. YES. Even on the main issue regarding the CIAC's interpretation of the contract.
jurisdiction, the CA erred in ruling that said
arbitration body had no jurisdiction over the Section 4 of Executive Order No. 1008 the CIAC shall
complaint filed by herein petitioner. There is no have original and exclusive jurisdiction over
question that, as provided under Section 4 of disputes arising from, or connected with, contracts
Executive Order No. 1008, also known as the entered into by parties involved in construction in
Construction Industry Arbitration Law, the CIAC has the Philippines and all that is needed for the CIAC to
original and exclusive jurisdiction over disputes acquire jurisdiction is for the parties to agree to
arising from, or connected with, contracts entered submit the same to voluntary arbitration, there can
into by parties involved in construction in the be no other conclusion but that the CIAC had
Philippines and all that is needed for the CIAC to jurisdiction over petitioner's complaint.
acquire jurisdiction is for the parties to agree to
submit the same to voluntary arbitration. Furthermore, Section 1, Article III of the CIAC Rules
of Procedure Governing Construction Arbitration
Nevertheless, respondent insists that the only (CIAC Rules) further provide that [a]n arbitration
disputes it agreed to submit to voluntary arbitration clause in a construction contract or a submission to
are those arising from interpretation of contract arbitration of a construction dispute shall be
documents. It argued that the claims alleged in deemed an agreement to submit an existing or
petitioner's complaint are not disputes arising from future controversy to CIAC jurisdiction,
interpretation of contract documents; hence, the notwithstanding the reference to a different
CIAC cannot assume jurisdiction over the case. – arbitration institution or arbitral body in such
This contention is insubstantial. (see arbitration contract or submission. Thus, even if there is no
clause, 17.1 and 17.2) showing that petitioner previously brought its
claims before a Board of Arbitrators constituted
In gist, the foregoing provisions mean that herein under the terms of the contract, this circumstance
parties agreed to submit disputes arising by reason would not divest the CIAC of jurisdiction.
of differences in interpretation of the contract to a
Board of Arbitrators the composition of which is It bears to emphasize that the mere existence of an
mutually agreed upon by the parties, and, as a last arbitration clause in the construction contract is
resort, any other dispute which had not been considered by law as an agreement by the parties to
resolved by the Board of Arbitrators shall be submit existing or future controversies between
submitted to the Construction Arbitration Authority them to CIAC jurisdiction, without any qualification
created by the government, which is no other than or condition precedent. To affirm a condition
the CIAC. Moreover, other matters not dealt with precedent in the construction contract, which
by provisions of the contract or by special would effectively suspend the jurisdiction of the
agreements shall be governed by provisions of the CIAC until compliance therewith, would be in
Construction Industry Arbitration Law, or Executive conflict with the recognized intention of the law
Order No. 1008. and rules to automatically vest CIAC with
jurisdiction over a dispute should the construction
The Court finds that petitioner's claims that it is contract contain an arbitration clause.
entitled to payment for several items under their
contract, which claims are, in turn, refuted by Moreover, the CIAC was created in recognition of
respondent, involves a dispute arising from the contribution of the construction industry to
differences in interpretation of the contract. Verily, national development goals. Realizing that delays in
the resolution of construction industry disputes The CA explained that the CIAC Revised Rules of
would also hold up the development of the country, Procedure stated that the agreement to arbitrate
Executive Order No. 1008 expressly mandates the need not be signed by the parties; that the consent
CIAC to expeditiously settle construction industry to submit to voluntary arbitration was not
disputes and, for this purpose, vests in the CIAC necessary in view of the arbitration clause
original and exclusive jurisdiction over disputes contained in the Contract of Service; and that
arising from, or connected with, contracts entered Federal's contention that its former counsel's act of
into by the parties involved in construction in the manifesting its consent to the arbitration stipulated
Philippines. in the draft Contract of Service did not bind it was
inconsequential on the issue of jurisdiction.

FEDERAL BUILDERS, INC vs. POWER FACTORS, INC ISSUE: WON the CA erred in upholding CIAC's
jurisdiction over the present case; and
FACTS: Federal, the general contractor of the
Bullion Mall under a construction agreement with HELD:
Bullion Investment and Development Corporation CIAC had jurisdiction. The need to establish a
(BIDC). Federal engaged respondent Power Factors proper arbitral machinery to settle disputes
Inc. (Power) as its subcontractor for the electric expeditiously was recognized by the Government in
works at the Bullion Mall and the Precinct Building. order to promote and maintain the development of
the country's construction industry. With such
Power demanded the Federal for the unpaid recognition came the creation of the CIAC through
amount for work done by Power for the Bullion Mall Executive Order No. 1008 (E.O. No. 1008), a.k.a
and the Precinct Building which answered that its Construction Industry Arbitration Law.
outstanding balance of P11.444,658.97 should be
addressed directly to BIDC. Nonetheless, Power Section 4 of E.O. No. 1008 provides: The CIAC shall
made several demands on Federal to no avail. have original and exclusive jurisdiction over
disputes arising from, or connected with, contracts
The Power filed a request for arbitration in the CIAC entered into by parties involved in construction in
invoking the arbitration clause of the Contract of the Philippines, whether the dispute arises before
Service reading as follows: ARBITRATION or after the completion of the contract, or after the
COMMITTEE - Construction Industry Arbitration abandonment or breach thereof. These disputes
Commission (CIAC) which shall have original and may involve government or private contracts. For
exclusive jurisdiction over the aforementioned the Board to acquire jurisdiction, the parties to a
disputes between the parties. dispute must agree to submit the same to voluntary
arbitration. x x x
Federal moved to dismiss the case on the ground
that CIAC had no jurisdiction over the case Under the CIAC Revised Rules of Procedure
inasmuch as the Contract of Service between Governing Construction Arbitration (CIAC Revised
Federal and Power had been a mere draft that was Rules), all that is required for the CIAC to acquire
never finalized or signed by the parties. Federal jurisdiction is for the parties of any construction
contended that in the absence of the agreement for contract to agree to submit their dispute to
arbitration, the CIAC had no jurisdiction to hear and arbitration.
decide the case.
Also, Section 2.3 of the CIAC Revised
The CIAC set the case for hearing, and directing that Rules states that the agreement may be reflected in
Federal's motion to dismiss be resolved after the an arbitration clause in their contract or by
reception of evidence of the parties. Federal did not subsequently agreeing to submit their dispute to
thereafter participate in the proceedings until the voluntary arbitration. The CIAC Revised Rules
CIAC rendered the Final Award. clarifies, however, that the agreement of the parties
to submit their dispute to arbitration need not be
CA affirmed CIAC’s decision but with modification as signed or be formally agreed upon in the contract
to the amounts due to Power.
because it can also be in the form of other modes of Moreover, a contract does not need to be in writing
communication in writing. in order to be obligatory and effective unless the
law specifically requires so.
(see Sec. 4.1, 4.1.1 4.1.2, RULE 4)
Pursuant to Article 135618 and Article 135719 of
The liberal application of procedural rules as to the the Civil Code, contracts shall be obligatory in
form by which the agreement is embodied is the whatever form they may have been entered into,
objective of the CIAC Revised Rules. Such liberality provided that all the essential requisites for their
conforms to the letter and spirit of E.O. No. 1008 validity are present. Indeed, there was a contract
itself which emphasizes that the modes of voluntary between Federal and Power even if the Contract of
dispute resolution like arbitration are always Service was unsigned. Such contract was obligatory
preferred because they settle disputes in a speedy and binding between them by virtue of all the
and amicable manner. They likewise help in essential elements for a valid contract being
alleviating or unclogging the judicial dockets. Verily, present.
E.O. No. 1008 recognizes that the expeditious
resolution of construction disputes will promote a It clearly appears that the works promised to be
healthy partnership between the Government and done by Power were already executed albeit still
the private sector as well as aid in the continuous incomplete; that Federal paid Power ₱l ,000,000.00
growth of the country considering that the representing the originally proposed downpayment,
construction industry provides employment to a and the latter accepted the payment; and that the
large segment of the national labor force aside from subject of their dispute concerned only the
its being a leading contributor to the gross national amounts still due to Power.
product.
With the parties having no issues on the provisions
The jurisdiction of the CIAC is over the dispute, not or parts of the Contract of Service other than that
over the contract between the parties. Section 2.1, pertaining to the downpayment that Federal was
Rule 2 of the CIAC Revised Rules particularly supposed to pay, Federal could not validly insist on
specifies that the CIAC has original and exclusive the lack of a contract in order to defeat the
jurisdiction over construction disputes, whether jurisdiction of the CIAC. As earlier pointed out, the
such disputes arise from or are merely connected CIAC Revised Rules specifically allows any written
with the construction contracts entered into by mode of communication to show the parties' intent
parties, and whether such disputes arise before or or agreement to submit to arbitration their present
after the completion of the contracts. Accordingly, or future disputes arising from or connected with
the execution of the contracts and the effect of the their contract.
agreement to submit to arbitration are different
matters, and the signing or non-signing of one does The agreement contemplated in the CIAC Revised
not necessarily affect the other. In other words, the Rules to vest jurisdiction of the CIAC over the
formalities of the contract have nothing to do with parties' dispute is not necessarily an arbitration
the jurisdiction of the CIAC. clause to be contained only in a signed and finalized
construction contract. The agreement could also be
Federal contends that there was no mutual consent in a separate agreement, or any other form of
and no meeting of the minds between it and Power written communication, as long as their intent to
as to the operation and binding effect of the submit their dispute to arbitration is clear. The fact
arbitration clause because they had rejected the that a contract was signed by both parties has
draft service contract. - The contention of Federal nothing to do with the jurisdiction of the CIAC, and
deserves no consideration. this is the explanation why the CIAC Revised Rules
itself expressly provides that the written
Under Article 1318 of the Civil Code, a valid communication or agreement need not be signed
contract should have the following essential by the parties.
elements, namely: (a) consent of the contracting
parties; (b) object certain that is the subject matter Although the agreement to submit to arbitration
of the contract; and (c) cause or consideration. has been expressly required to be in writing and
signed by the parties therein by Section 422 of
Republic Act No. 876 (Arbitration Law), the
requirement is conspicuously absent from the CIAC
Revised Rules, which even expressly allows such
agreement not to be signed by the parties therein.
Consistent with the policy of encouraging
alternative dispute resolution methods, therefore,
any doubt should be resolved in favor of arbitration.
In this connection, the CA correctly observed that
the act of Atty. Albano in manifesting that Federal
had agreed to the form of arbitration was
unnecessary and inconsequential considering the
recognition of the value of the Contract of Service
despite its being an unsigned draft.

You might also like