Daily Progress Report

As of April 06, 2018


LIST OF PROJECTS

A. BATTERY PROJECTS
1) PBI & RTI STEEL FENCE REPAINTING PROJECT – (On Progress)
2) MCB EMPLOYEE’S LOUNGE – (On progress)
3) PBI Bridge Repainting – (On Progress)

B. SPECIAL PROJECTS
1) AGUS DORMITORY REHABILITATION 2017 PLUMBING WORKS – (waiting for other materials prior to completion)
2) REPAINTING OF COMMON CR (Dorm1 & 2) – (waiting for advise prior to mobilization)
3) SMIP ILOILO STEEL YARD – (waiting for establish F.E.)

C. STORE PROJECTS
1) KFC TANAY – (Pre Fab works already completed)
2) KFC SINDALAN – (Pre Fab works already completed)
3) KFC SAN DIONISIO – (Pre Fab works already completed)
4) KFC CAVITE – (Pre Fab works already completed)

D. FABRICATION INVENTORY
1) CHB Fabrication – (On going)
2) Container Van Inventory (20 & 40 footer)
BATTERY PROJECTS UPDATE
PBI & RTI STEEL FENCE
REPAINTING PROJECT
SITE ACTIVITIES
1.0 Installation of yellow spacer prior to coating
works
2.0 On going top coating of steel fence.

Note:
1. Top coating paint already delivered as per Maam Angel
2. Top coating works started last March 23
Site Plan Reflecting the
Accomplished Portion of Steel
Fence (PBI)
Project Status as of April 6
Other Site Issues & Concerns
1.0 Paint material for RTI still unserved
Site Photos (PBI)
Site Photos (PBI)
Site Photos (PBI)
Site Photos (PBI)
Site Photos (PBI)
Site Photos (PBI)
PBI MCB LOCKER EXPANSION &
EMPLOYEE’S LOUNGE
Site Status (Employee’s Lounge) as
of April 6
Site Activity
“Adjustment of lighting fixture opening at
ceiling already done as of today April 5.
Manpower (3carp)”
Site Pictures
Site Pictures
Site Pictures
Site Status (Locker Expansion) as
of April 6
Manpower
A. Civil
• Mason – 2/2
Site Activity
1. On going installation of Wall Tiles & Tile Trim
2. Installation of Zocalo wall along shower &
door opening
Site Photos
Site Photos
Site Photos
Site Photos
PBI BRIDGE REPAINTING
Project Status as of April 6
Manpower
1. Foreman – 1/1
2. Painter – 7/7
Site Status
Site Photos
Site Photos
Site Photos
Site Photos
Site Photos
STORE PROJECTS UPDATE
KFC TANAY
KFC SINDALAN
KFC SAN DIONISIO
KFC CAVITE CITY
Site Photo
(KFC Cavite 3rd Gen.)
Site Photo
(KFC Tanay, Sindalan & San Dionisio
3rd Gen.)
SPECIAL PROJECTS UPDATE
DORM 1 & 2 COMMON CR
PLUMBING REPAIR
Project Status (Dorm 1 & 2) as of
February 20
Site Issues & concern
“No available manpower as to date”
Iloilo Steel Project
Site Dev’t Status
Site Status
“No site activity until to date”

By April 8 we will start the spreading of


available base coarse at site base on the
established elev. provided by survey team.
Base coarse Inventory (Directly
delivered on site)
1st batch – more or less 18 cubic meter only
2nd batch – more or less 18 cubic meter only
3rd batch – more or less 18 cubic meter only
4th batch – more or less 30 cubic meter only
5th batch – more or less 30 cubic meter only
6th batch – more or less 30 cubic meter only
7th batch – more or less 30 cubic meter only
Site Photos
Site Photos
Site Photos
FABRICATION INVENTORY UPDATE
Precast Fab. Status
Site Activity
1. On going fabrication of precast column, panel & beam for
KFC 3rd Gen.
2. On going fabrication of tobleron post 8’ long for RCA project
CHB Fabrication Inventory as of
February 26
1. CHB # 3” - 940pcs.
2. CHB # 4” - 7035pcs.
3. CHB # 6” Ord. - 3765pcs.
4. CHB # 6” Load Bearing - 310pcs.
5. CHB # 8” - 740pcs.
6. Turf 3-1/2” - 315pcs.
7. Turf 5” - 1840pcs.
8. Diamond 3” - 40pcs.
9. Louver - 900pcs.
CHB Fabrication Inventory as of
February 20
10. Tobleron Post 6’ - 170pcs.
11. Tobleron Post 8’ - 91pcs.
12. Tobleron Post 8’ (RCA Orchids) - 154pcs.
12. RCPipe 18” - 5pcs.
13. RCPipe 24” - 66pcs.
14. RCPipe 30” - 58pcs.
15. RCPipe 36” - 9pcs.
16. RCPipe 42” - 0pcs.
17. RCPipe 48” - 3pcs.
18. L-Block # 4” - 600pcs.
CHB Fabrication Inventory
19. Column Block 12” x 12” - 170pcs.
20. Half CHB 4” - 20pcs.
21. Column L-BLOCK 12” x 12” x 6 - 15pcs.
22. Precast Pipe Duct - 10pcs.
23. Precast Pipe Duct w/ slab - 3pcs.
24. Precast Column 1 - 33pcs.
25. Precast Column 2 - 0pcs.
26. Precast Panel - 255pcs.
27. Precast Beam - 11pcs.
20 & 40 footer CV Inventory
Remaining CV’s as of February 20
1.0 20 footer CV = 12pcs.
2.0 40 footer CV = 3pcs.
20 Footer CV Breakdown
1. Slag Block Fence Balasing Boundary (Genarro Proj.) - 1unit
2. KFC Sto. Tomas - 7units
3. KFC Cabuyao - 8units
4. KFC Solano - 9units
5. KFC Mabalacat - 8units
6. KFC Sta. Cruz, Laguna - 8units
7. KFC Malolos - 7units
8. Qesi (requested by Sir Tim) - 4units
9. Qesi (delivered last February 3, 2018) - 2units
10. Waste Water - 1unit
11. Farm 6 - 1units
12. Central Warehouse - 1units
13. Used as stock Room of PBI Admin Painting Materials - 1unit
14. Qesi new building (stock room for materials) - 1unit
15. Current Stock - 10unit
TOTAL = 69units
40 Footer CV’s
1.0 Motorpool – 2pcs.
2.0 Current Stock of 40 footer – 3pcs.
Total – 5pcs. (3pcs. From BIGHOO)
Thank you!