PROJECT CODE - MC 406-B

PROJECT NAME - AL AWABI PSS

PENDING WORK AS ON - 07.07.2018

S.NO LOCATION PENDING WORK START DATE FINISH DATE MATERIAL REQIURMENTS

earth flat work 16.07.18 20.07.18 received

1 Cable cellar room cable tray work 21.07.18 03.08.18 received

light fixing work 04.08.18 07.08.18 waiting for pending material

conciled conduit pipe fixing work 08.07.18 11.07.18 received

plumbing work 08.07.18 10.08.18 received

flexible cable laying for lighting and 22.07.18 25.07.18 received


ac
2 1st floor
light fixing work 26.07.18 31.07.18 waiting for pending material

ac installation work 01.08.18 05.08.18 received


panel erection work 25.07.18 31.07.18 received

3 External area earth flat work 30.06.18 14.07.18 received

west side trench tray work 04.07.18 08.07.2018 received


5 cable trench
south side trench tray work 25.07.18 29.07.18 received

Axillary transformer &


6 capacitor bank erection work 27.07.18 28.07.18 mazoon scope

internal area
7 cable laying 04.08.2018 08.08.2018 material pending
outdoor area

8 pre-commission testing all equipments 1.08.18 09.08.18


MANPOWER REMARKS
REQIURMENTS

3 helper to be need

waiting for plumber

waiting for ac technican


man power required

3 helper to be need

3 helper to be need

civil side foundation


pending

civil side foundation


pending