Professional Documents
Culture Documents
To cite this article: Kazuki Kawamura, Akihiro Ametani & Unnur Stella Gudmundsdottir (2013)
Surge Analysis on a Long Underground Cable System, Journal of International Council on Electrical
Engineering, 3:2, 158-163, DOI: 10.5370/JICEE.2013.3.2.158
†
Kazuki Kawamura*, Akihiro Ametani and Unnur Stella Gudmundsdottir**
Abstract – This paper investigates a basic characteristic of fault surge in a long cable system based
on EMTP simulations. It is made clear from the simulation results that the sheath over-voltage is
higher on a cross-bonded cable than that on a normal-bonded cable. Also, a resonant overvoltage
appears when cables with shunt reactors are disconnected. It becomes clear that the period of the
beat becomes long as the compensation rate increases. From simulations with earth continuity
conductor (ECC), the ECC is effective to reduce an overvoltage in the case of a fault at an overhead
line connected to the cable.
Keywords: Earth continuity conductor (ECC), EMTP simulation, Cross-bonded cable, Shunt
reactor, Underground cable
1. Introduction a resistance (Rg) per major section. Lg are 10μH and Rg are
20 Ω. Also, A 100 Ω is connected to the receiving end of all
Recently, a number of cable projects in the world have the phases for a steady-state condition. Fig. 2 (a) illustrates
increased considerably. For example, A 400kV AC the cable arrangement, and (b) is the physical parameters.
submarine cable connecting Italian mainland and Sardinia The cables are placed in horizontal arrangement with the
Island is under construction[1]. In Denmark, all the 132kV- separation of 0.4m, and 3m below the surface. Fig. 3
150kV overhead lines will be undergrounded by the year illustrates a cross-bonded cable system. An EMTP
2040[2].This paper first carries out EMTP simulations[3,4]- simulation of on the above cable is carried out, when the
[5] in a 154 kV underground cable system to investigate the position of a core to a sheath fault is varied from the
surge characteristic during a core to sheath short circuit sending end to the receiving end.
fault. Then, a comparison of a transient in a normal-bonded
cable with that in a cross-bonded cable, and the effect of a
sheath protection arrester (CCPU) is investigated. Secondly,
EMTP simulations including a shunt reactor is carried out
to investigate the behavior of the resonant over-voltage.
Finally, simulations in a part of 400kV Danish cable
systems with an earth continuity conductor (ECC)[6]-[7],
which is used to reduce the sheath voltage and the earth
potential rise, are carried out.
long. The sheaths are grounded though a lead wire (Lg) and
158
Kazuki Kawamura, Akihiro Ametani and Unnur Stella Gudmundsdottir
2.2 Simulation Results arrester. Fig. 6 shows a simulation result when the sheath is
protected by the arrester or not. Fig. 6(a) is the core over-
Fig. 4 shows a core voltage waveform and Fig. 5 shows voltage waveform, and (b) is the sheath over-voltage
the sheath voltage waveform. Table 1 summarizes the waveform. Table 3 summarizes the maximum sheath over-
maximum core and sheath voltages when the position of a voltages when the position of a core to a sheath fault is
core to a sheath fault is varied from the sending end to the varied from the sending end to the receiving end. There is
receiving end. There is no significant difference of the core no significant difference of the core over-voltages in Fig.
voltage between normal-bonded cable and cross-bonded 8(a). On the other hand, the effect of the arrester is clear in
cable. However, the sheath over-voltage becomes much Fig. 8(b). It is found that the arrester could suppress the
higher in a cross-bonded cable. Table 1 shows that the node sheath over-voltage by 30%.
where the highest voltage appears becomes different
between the normal-bonded and the cross-bonded cables. It Table 1. Maximum voltages [p.u.]
is clear that the maximum core over-voltage appear when a Fault Normal-bonded Cross-bonded
point Core Sheath Core Sheath
fault occurs at the sending end.
M11-1A 2.059/M32C1C 0.068/M11S1A 2.066/M22C1C 0.363/M12S1A
M12-1A 2.009/ M32C1C 0.067/M11S1A 2.011/M22C1C 0.534/M13S1B
M13-1A 1.999/M32C1C 0.067/M11S1A 1.994/M11C1C 0.396/M22S1A
M21-1A 1.970/M32C1C 0.066/M11S1A 1.899/M11C1C 0.358/M12S1C
M31-1A 1.889/M22C1C 0.061/M11S1A 1.828/M11C1C 0.336/M32S1B
M41-1A 1.817/M32C1C 0.059/M11S1A 1.711/M11C1C 0.332/M33S1A
M51-1A 1.749/M22C1C 0.057/M11S1A 1.613/M11C1C 0.310/M52S1B
M53-1A 1.712/M22C1C 0.055/M11S1A 1.575/M22C1C 0.223/M42S1C
M61-1A 1.690/M32C1C 0.055/M11S1A 1.557/M13C1C 0.261/M52S1B
voltage [kV]
0 0
5 7900.0 100.0
6 8400.0 1000.0
7 8800.0 2000.0
-300 -300 8 9800.0 10000.0
0 0.25 0.5 0 0.25 0.5
time [ms] time [ms] 9 11000.0 20000.0
10 12000.0 50000.0
(a) Normal-bonded cable (b) Cross-bonded cable
300 70
Fig. 4. Simulation results of a core voltage.
voltage [kv]
voltage [kv]
70 70 0 0
without arrester without arrester
arrester arrester
voltage [kV]
voltage [kV]
0 0 -300 -70
0 1 2 0 0.125 0.25
time [ms] time [ms]
-70 -70
(a) Core voltage (b) Sheath voltage
0 0.25 0.5 0 0.25 0.5
time [ms] time [ms]
(a) Normal-bonded cable (b) Cross-bonded cable Fig .6. Simulation result with an arrester by EMTP.
Fig. 5 Simulation results of a sheath voltage Table 3. Maximum sheath voltages in a double circuit
cross-bonded cable [p.u.]
The maximum core over-voltage reaches 260kV in Fig. 4. Fault point without arrester arrester
M11-1A 0.363 / M12S1A 0.283 / M13S1B
This value is less than the insulation level of a 154kV cable M12-1A 0534 / M13S1B 0.194 / M13S1B
system. However, the maximum sheath over-voltage M13-1A 0.396 / M22S1A 0.342 / M22S1B
reaches 60 kV. This result exceeds the sheath insulation M21-1A 0.358 / M12S1C 0.236 / M13S1A
M31-1A 0.336 / M32S1B 0.331 / M32S1A
level[8]. Thus, it is necessary to reduce the over-voltage. A M41-1A 0.332 / M33S1A 0.328 / M33S1A
simulation with an arrester for the sheath protection is M51-1A 0.310 / M52S1B 0.314 / M43S1A
carried out. Table 2 summarizes I-V characteristics of the M53-1A 0.223 / M42S1C 0.242 / M52S1B
M61-1A 0.261 / M52S1B 0.276 / M53S1A
159
Surge Analysis on a Long Underground Cable System
100 50
Voltage 「kV]
Voltage 「kV]
0
2π LC , ‐200
‐300 ‐150
0 0.2 0.4 0.6 0.8 1 0 0.2 0.4 0.6 0.8 1
time [s] time [s]
Fig. 8 shows cable arrangement and parameters. (a) Circuit breaker voltage (b) Sending end core voltage
(i)Compensation rate 100%
3.2 Simulated results
300 150
200
Voltage 「kV]
Voltage 「kV]
‐100 ‐50
200
‐50
‐100
160
Kazuki Kawamura, Akihiro Ametani and Unnur Stella Gudmundsdottir
R=0 0.34167
0.34167
A
R=0 bonded point, the major section and the receiving end. The
time of fault occurrence is : at peak, zero and between
A 13.54648 V
V 13.54648
CB_source
CB_source
BRK2A
Timed
Breaker
Logic
Open@t0
zero and peak. Both single-phase and three-phase faults are
Shunt reactor 50 MVAr
Breaker Breaker
BRKA Logic Logic
A
V
BRK2B
Open@t0 Open@t0
Timed Timed
0 .3
0 .3
0 .3
0 .3
Timed
Breaker
BRKC Logic
The sheath voltage between phases to the ground are
1 0 .0 5 2
1 0 .0 5 2
1 0 .0 5 2
Open@t0
1 0 .0 5 2
1 0 .0 5 2
1 0 .0 5 2
CB_shuntreactor
CB_shuntreactor
calculated.
N o rre a d a le n
N o rre a d a le n
Timed
N o rre a d a le n
Breaker
0 .1
Logic
T je le
T je le
BRKSR_2A
Timed Open@t0
Bus1 Bus2
Breaker
Logic Timed
BRKSR_1A Breaker
Open@t0
0 .1
BRKSR_2B Logic
Timed Open@t0
Breaker
Logic Timed
161
Surge Analysis on a Long Underground Cable System
For the unsymmetrical fault, the ECC is more effective. overhead line, the decreasing rate of the sheath voltage is
ECC can reduce the sheath over voltage to the ground in low. Therefore, ECC is more effective when a fault occurs
case O-M-1 and Case O-B-1,when a fault occurs at zero on an overhead line than that on a cable. The other cases of
voltage, but the over voltage is very small. faults on a cable show no high the over-voltage. Therefore,
when a fault occurs at the cable, the ECC is not necessary.
40
30
Cross1SC_without ECC
40
30
Cross1SC_with ECC If ECC will be installed in a cable system, it is most cost
20 20 effective to install an ECC near to an overhead line.
Voltage [kV]
Voltage [kV]
10 10
0 0
‐10 ‐10
90
‐20 ‐20
80
‐30 ‐30
0 0.05 0.1 0.15 0.2 0.25 0 0.05 0.1 0.15 0.2 0.25 70
time [s] time [s] 60
Voltage [kV]
(a) ECC (b) No ECC 50
40
30 ECC
Fig. 13. The sheath voltage waveform. 20 Without ECC
10
0
45
40
35
30 Location
Voltage [kV]
25
20
15 ECC
Case C-M-1 (Fault at the sending end)
10
45
Without ECC
5 40
0 35
30
Voltage [kV]
25
20
Location ECC
15
10
Case O-M-1 5
Without ECC
70 0
60
50
Voltage [kV]
40 Location
30
20
ECC Case C-M-1(Fault at the receiving end)
Without ECC
10
0 Fig. 15. The simulation over voltage rate (Fault at the Cable).
162
Kazuki Kawamura, Akihiro Ametani and Unnur Stella Gudmundsdottir
investigated when a fault occurs in a system composed of Akihiro Ametani received Ph.D.
overhead lines and underground cables. From the degree from UMIST, Manchester, U.K.,
investigations in the paper, the following remarks have in 1973. He was with UMIST from
been obtained.
1971 to 1974, and with Bonneville
1. The sheath over-voltage is higher on a cross-bonded
Power Administration for summers
cable than that on a normal-bonded cable. Also, a sheath
from 1976 to 1981, and developed
protection arrester (CCPU) reduces the sheath over voltage
EMTP. He has been a Professor at
less than a sheath insulation level.
Doshisha University since 1985. He was a Visiting
2. A resonant overvoltage appears when cables are
Professor at the Catholic University of Leaven, Belgium in
disconnected. The period of the beat becomes long as the
1988. He was the Director of the Science and Engineering
compensation rate of a shunt reactor increases.
Institute of Doshisha University from Apr. 1996 to Mar.
3. It becomes clear that the ECC is more effective when a
1998, and the Dean of Library and Computer/Information
fault occurs at the overhead line than at the cable.
Center of the same University from Apr. 1998 to Mar. 2001.
4. If ECC is installed in a cable system, the ECC should
Dr. Ametani is a chartered engineer in the U.K., a
be installed at both the sending and receiving ends of the
distinguished member of CIGRE, and a fellow of both
cable.
IEEE and IET.
163