COAL CRUSHING PLANT 750 TPH Section :

JEMBAYAN - SAMARINDA Date :


EAST KALIMANTAN Test No. :
Start SMU :
Finish SMU :

PERFORMANCE TEST RECORDS FEEDER

Temperatur ( ˚C ) Vibration Condition


1.DRIVE UNITS Remarks
Input Output (mm/s) OK /Not OK
1,1 Motor Time for Checking :
1,2 Gearbox Time load :
1,3 Fluid Coupling Load :
1,4 Brake Capacity :
1,5 Oil leak / Body
1,6 Chain M630-250
1,7 Bushing
1,8 Dragbar
1,9 Housing Bearing Tail
2 Housing Bearing Drive

Record by,
PT.JASA LAKSA UTAMA PT. ADHIYAKSA PT. ALAM JAYA BARA PRATAMA

( ) ( ) ( )
Section :
Date :
COAL CRUSHING PLANT 750 TPH Test No. :
JEMBAYAN - SAMARINDA Start SMU :
EAST KALIMANTAN Finish SMU :

COMISIONING TEST RECORDS FEEDER

Inspection Result
1.DRIVE UNITS DESCRIPTION QTY UNIT Remarks
OK NOT OK
1,1 Motor SIEMENS 75 kW 1 Set Time for Checking :
KUMERA TDM 4450-
1,2 Gearbox 1 Set Time load :
H2-250-LA
1,3 Coupling - - - Load :
1,4 V- Belt - - - Capacity :
1,5 Oil leak / Body ISO VG 220 220 L
1,6 Chain M630-250 Pitch - 250 70 m
1,7 Bushing 140 Pcs
1,8 Dragbar 35 set
1,9 Housing Bearing Tail Tail - 23028 CC/W33 2 set Grease Type Mobile xhp -222
2 Housing Bearing Drive Drive - 23144 CC/W33 2 set Grease Type Mobile xhp -222
2,1 Take Up device As Thread - 30 2 set

Record by,
PT.JASA LAKSA UTAMA PT. ADHIYAKSA PT. ALAM JAYA BARA PRATAMA

( ) ( ) ( )