Professional Documents
Culture Documents
PURPOSE
● PROJECT CODE : AGM-OM-CO-003
□ For Review
● PROJECT NAME : ANGAMOS THERMOELECTRIC
POWER PLANT ■ For Approval
Owner:
Contractor:
Doc. No. : 5PG-0104-00
Project Work Instruction (PWI) Rev. : A
Installation of Tripper Gallery
Page : 2 OF 14
REVISION SUMMARY
Reviewed:
Doc. No. : 5PG-0104-00
Project Work Instruction (PWI) Rev. : A
Installation of Tripper Gallery
Page : 3 OF 14
TABLE OF CONTENTS
Section Description
1 Purpose
(목적)
2 Scope
(적용 범위)
3 Responsibility
(책임)
4 References
(참조 사항)
5 Work Instruction (작업 절차)
5.1 지상 조립장 위치
5.2 Ground Assembly (지상 조립)
5.3 Welding for Lifting Stiffener
5.4 Lifting Equipment
5.5 Lifting of Tripper Gallery
6 Attachment (첨부)
Doc. No. : 5PG-0104-00
Project Work Instruction (PWI) Rev. : A
Installation of Tripper Gallery
Page : 4 OF 14
1. Purpose (목적)
3. Responsibility (책임)
3.1 현장소장은, 공사일정에 기준한 공사 및 시운전의 완료는 물론 본 PWI 의 승인 및
실행의 책임이 있다
Site Manager is responsible for approval and implementation of this Project Work
Instruction as well as completion of construction and commissioning work of the
project based on the project schedule.
Project Quality Manager is responsible for quality assurance & control program
related with the installation work of this Project Work Instruction under the
consultation of Quality Department of Head Office.
Doc. No. : 5PG-0104-00
Project Work Instruction (PWI) Rev. : A
Installation of Tripper Gallery
Page : 5 OF 14
4. References
4.1 Related Drawings
- Triper Gallery Plan & Detail dwg
4.2 Related Project Work Instruction and Documents
- General Welding (PWI : 5PG-0104-002)
- Visual Inspection (PWI : 5PG-0109-005)
b) BB-DB Line
1) Girder : 6 pcs
2) Post : 9 pcs
3) V.B : 8 pcs
4) Girth : 24 pcs
5) Total Weight : 24.681 ton
b) Detail DWG
1) Plate 652x332x20t : 4 sh’ts x 4each
2) Plate 652x144x12t : 6 sh’ts x 4each
3) See attached DWG
Doc. No. : 5PG-0104-00
Project Work Instruction (PWI) Rev. : A
Installation of Tripper Gallery
Page : 8 OF 14
b) 낙하물 유무 상태 점검
Doc. No. : 5PG-0104-00
Project Work Instruction (PWI) Rev. : A
Installation of Tripper Gallery
Page : 10 OF 14
g) 지반상태 점검
Check condition of ground
b) 비상 스톱 S/W 작동상태
Condition of emergency switch
b) 인양절차 교육
Induction of rigging procedure
Main lifting should be executed by 400 ton crane and tail lifting crane should be
selected by situation of field. Once tripper gallery is ready to lift, tripper gallery
should be lifted from the ground following a sign of signal man.
Tail lifting crane should lift both bottom side of tripper gallery using two cranes.
5.5.3 Master Boom Angle 을 65° 로 유지하고 Jib Angle 를 조종하여 Tripper Gallery 을
T/G Control Building 높이 이상으로 인양 후, Tripper Gallery(BB-DB Line)을 시계방
향으로 회전 후 Jib Boom Angle 을 조종하여 설치한다
Maintain angle of main boom at 65°and control angle of jib boom to locate right
position of tripper gallery over main control building. Once tripper gallery is lifted
over main control building, turn it clockwise and move the 400 ton crane which is
lifted Tripper Gallery (BB-DB Line) to the direction of BB-DB line to assemble the
Tripper Gallery on exist column.
Attachment 3 : 3D view
Doc. No. : 5PG-0104-00
Project Work Instruction (PWI) Rev. : A
Installation of Tripper Gallery
Page : 13 OF 14
Doc. No. : 5PG-0104-00
Project Work Instruction (PWI) Rev. : A
Installation of Tripper Gallery
Page : 14 OF 14