WELL DRILLING AT RANG AYAN


2018 ADDITIONAL INFORMATION/NOTES

ID WORK DESCRIPTION QTY UNIT


DW DEEP WELL DRILLING (LABOR ONLY)
DW Mobilization of one drilling unit 1 ls
DW Site Preparation and equipment setting 1 ls
DW Drilling of pithole 200 m
DW Geophysical Borehole Logging (Electric resistivity) 1 ls
DW Water Conductivity Test 200 m
DW Reaming of pilothole 200 m
DW Installation of blank casing & screens 200 m
DW Furnishing and installation of casing centralizer every 20m interval 10 pcs
DW Furnishing and installation of gravel packing 150 m
DW Development by backwashing 12 hrs
DW Treatment of Well sodium hexametaphosphate 1 ls
DW Development by high pressure water jetting 12 hrs
DW Development by air-lifting 12 hrs
DW Development by surging & bailing out of sediments 12 hrs
DW Step-drawdown pumping test 8 hrs 4step @ 2hr/step
DW Continuous constant discharge rate pumping test 72 hrs
DW Furnishing and installation of local clay seal 1 ls
DW Cement Grouting 50 m
DW Furnishing and install well head cap, gravel fill pipe and water level sounding tube 1 ls
DW Well Disinfection 1 ls
DW Demobilization and cleanup of well site 1 ls

Prepared by:

ENGR. MARIA GRECILLE M. MENDOZA


Cost Engineer