A. SUMMARY OF RESULTS
c. Pump input power savings at 50% pump speed vs. 100% pump speed (%):
d. Savings ($) in electrical costs for the pump operating at 50% pump speed vs. 100% pump
speed for one year (assume electricity cost is $0.10/kWh)
Summary page 1 of 2
CE415L REPORT REQUIREMENTS FOR LAB REPORT FOR EXP 7
System A
a. Shut-off TDH, Hshutoff _A(ft) :
System B
c. Shut-off TDH, Hshutoff_B (ft) :
B. GRAPHICAL REQUIREMENTS
Summary page 2 of 2
CE415L REPORT REQUIREMENTS FOR LAB REPORT FOR EXP 7
On the plot, choose a flow rate at about the midpoint of the flow rate range tested and draw a
vertical line to intersect both capacity curves. Note the pressure head corresponding to each of
the two intersection points.
On a single graph, labeled “Experiment 7 Part 6 – Operating Centrifugal Pumps in Parallel”, plot
the following parameters vs. flow rate Q (gpm) for the full range of flow rates tested: