You are on page 1of 14

RABIGH II PROJECT

GS Construction Arabia Co., Ltd


INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

U/G TEST PACKAGE FOR


FIRE WATER PIPELINE

TEST PKG # TP-UO1-C210-FW-0064-1

RABIGH II – PROJECT
INTERCONNECTING UO1 PKG.
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

INFORMATION SHEET

Test Package No: TP-UO1-C230-FW-0064-1

 System Description : Fire Water System


 Sub system : N/A
 Area : NU – Road HJ and Road 47
 Design Pressure : 16.7 Kgf /cm²g
 Operating Temp : 27ºC
 Service : Fire Water Supply
 Test Pressure : 25.05 Kgf /cm²g
(24.57 Bar / 356.29 Psi)
 Test Medium : Potable Water / Well Water
 Type of Test : Hydrostatic Test
 Lay-up : Flushing
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

Test Package No- TP-UO1-C230-FW-0065


TABLE OF CONTENTS
Applicable
Section Description Remarks
Yes No
Flow Chart

1.0 Hydrotest Procedure


1.1 SATIP - Hydrostatic Testing of On-Plot Piping SATIP-A-004-02
1.2 Approved Hydrotest Procedure
1.3 Safety – Saudi Aramco General Instruction
G.I – 2.102
Manual
2.0 General Information
2.1 Test Package Information Sheet
2.2 Pressure Test Symbol
2.3 Line Index
2.4 Line List Included
2.5 P & ID / GA Drawing
2.6 Isometric Drawing
2.7 Summary Joint Inspection Report
2.8 Blind Flange List
3.0 Test Medium
3.1 Verify Test Medium for Hydrotesting SAIC-A-2008
3.2 Water Chemistry Report SATR-A-2014

4.0 Pre-Test Inspection of Punch Listing

4.1 Pre-Test Punch Listing of On-Plot Piping SAIC-A-2010


4.2 Pre-Test Punch List Form SATR-A-2011
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

Test Package No- TP-UO1-C230-FW-0065


TABLE OF CONTENTS
Applicable
Section Description Remarks
Yes No
5.0 QA / QC Documentation
5.1 Flange Joint Assembly Inspection Report SAIC-L-2014
5.2 Internal Cleanliness / Flushing report SAIC-L-2017
5.3 Inspection of Pressure Test Preparation SAIC-A-2011
5.4 Pressure Gauge Calibration Report SATR-A-2002
5.5 Pressure Relief Valve Calibration Report SATR-A-2006
5.6 Pressure Recorder Calibration Report (If Any) SATR-A-2004
5.7 Test Manifold Hydro Test Report SATR-A-2001
5.8 Verify Test Equipment SAIC-A-2009
6.0 Filling and Pressurization
6.1 Test Pressure Record Sheet
6.2 Inspection of Filling and Pressurization SAIC-A-2015
7.0 Pressure Test
7.1 Pressure Test Report SATR-A-2001
7.2 Visual Inspection at Test Pressure SAIC-A-2015
Depressurization and Disposal of Hydrotest
7.3 SAIC-A-2017
Water
8.0 Final Piping Punch Listing

Final Piping Punch Listing


8.1 SAIC-L-2022
(Piping Re-Instatement)

8.2 Re-Instatement Checklist Form SATR-L-2011


RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

FLOW CHART
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

TEST PACKAGE No.- TP-UO1-C230-FW-0065

Test Package Preparation Contractor Company


Engineering Construction QC QC

Initial Punch Listing


Contractor Company Company
Construction QC PMT QC

Clear "A" Items


Contractor Company Company
Construction QC PMT QC

Company Punch List


Contractor Company Company
Construction QC PMT QC

Clear Company 'A' Items/Test


Release Contractor Company Company
Construction QC PMT QC

Contractor Company Company


Release for Testing
Construction QC PMT QC

Pressure Testing
Contractor Company Company
Construction QC PMT QC

Drain / Cleanliness/ Drying


Contractor Company Company
Construction QC PMT QC

Lay- Up
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

Contractor Company Company


Construction QC PMT QC

RE-Instatement
Contractor Company Company
Construction QC PMT QC

Final Inspection
Contractor Company Company
Construction QC PMT QC

1.0 Hydrotest Procedure


1.1- SATIP - Hydrostatic Testing of On-Plot Piping
1.2- Approved Hydrotest Procedure
1.3- Safety – Saudi Aramco General Instruction Manual
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

2.0 General Information


2.1- Test Package Information Sheet
2.2- Pressure Test Symbol
2.3- Line Index
2.4- List of Lines Included
2.5- P & ID / GA Plan Drawing
2.6- Isometric Drawing
2.7- Summary of Joint Inspection Report
2.8- Blind Flange List
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

3.0 Test Medium


3.1 - Verify Test Medium for Hydrotesting
3.2 - Water Chemistry Report
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

Pre-Test Inspection of
4.0
Punch Listing
4.1 - Pre-Test Punch Listing of On-Plot Piping
4.2 - Pre-Test Punch List Form
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

5.0 QA / QC Documentation
5.1 - Inspection of Bolted Flange Joint Assembly
5.2 - Internal Cleanliness / Flushing report
5.3 - Inspection of Pressure Test Preparation
5.4 - Calibration Test Report – Pressure Gauge
5.5 - Calibration Test Report – Pressure Relief Valve
5.6 - Calibration Test Report – Pressure Recorder
(If Any)
5.7 - Test Manifold Hydro Test Certificate
5.8 - Verify Test Equipment
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

6.0 Filling & Pressurization


6.1- Test Pressure Record Sheet
6.2- Inspection of Filling and Pressurization
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

7.0 Pressure Test


7.1 - Pressure Test Report
7.2 - Visual Inspection at Test Pressure
Depressurization and Disposal of Hydrotest
7.3 -
Water
RABIGH II PROJECT
GS Construction Arabia Co., Ltd
INTERCONECTING
PACKAGE (UO1) GSCA JOB NO. 111580
CONTRACTNO. 6600028401(IK)

8.0 Final Piping Punch Listing


Final Piping Punch Listing
8.1 -
(Piping Re-Instatement)
8.2 - Re-Instatement Checklist Form