Time(min)
Motherboard final configuration 50 50
Motherboard post-configuration test 35 35
Power supply assembly 30 30
Power supply test 15 15
I/O interface board assembly 20 20
I/O interface board test 10 10
Bottom Side assembly 110 110
Bottom Side Continuity Test 20 20
Top Side assembly 120 120
Top Side Continuity Test 20 20
Generic Configuration Assembly 20 20
Generic Imaging 25 25
Final Continuity Test 20 20
System Stress Test 25 2880
Customer Configuration 25 25
Customer Imaging 50 50
Final Test 30 30
Outgoing QA 20 20
Packaging 20 20
665 3520
NOTE: Traffic chambers only needs technologist for loading and unloading units. The total time
available will be explained in appendix “x”
Procedure followed to determine the number of each type of equipment that is required
to meet the 2018 forecast demand:
The following formula was used to determine the number of equipment needed:
𝑇𝑜𝑡𝑎𝑙 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑡𝑖𝑚𝑒 𝑋 𝐷𝑒𝑚𝑎𝑛𝑑 𝑓𝑜𝑟𝑒𝑐𝑎𝑠𝑡 2019
# 𝑜𝑓 𝑀𝑎𝑐ℎ𝑖𝑛𝑒𝑠 =
𝑇𝑜𝑡𝑎𝑙 𝑝𝑟𝑜𝑢𝑑𝑐𝑡𝑖𝑜𝑛 𝑡𝑖𝑚𝑒 𝑎𝑣𝑎𝑙𝑖𝑏𝑙𝑒 − 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑐𝑢𝑠ℎ𝑖𝑜𝑛
For traffic chamber, the total production time is found by following a weekly schedule shown in
appendix X. As shown, the total production time available will be 440730 minutes from which 15%
capacity is subtracted from it.