Professional Documents
Culture Documents
In order to determine the percentage of the overhead of the maintenance operation from
that of the direct cost of maintenance activities and the total maintenance costs, the annual
work load quantities of maintenance activities that each District can perform with its capacity
and the annual overhead expenses, assuming the new reform study will be implemented, are
carefully estimated.
In this option, the direct and the overhead cost of all maintenance operation is computed
only for operational cost of equipment.
The overheads of Districts are tried to be identified and analyzed in different categories
as follow:
For the purpose of determining the proportions of the common head office overhead
for Districts & Projects, the total direct cost of Districts & Projects that they can perform
with their capacity are collected.
We have tried to calculate the direct cost of each respective district and come up
with the following analysis.
The total amount of budget allocated to perform the maintenance works of the
federal network per year =130,000,000 birr
The total amount of budget allocated to perform emergency
maintenance works per year =60,000,000 birr
The total direct cost would be = 0.65*(130,000,000+60,000,000)
123,500,000
Here, since salaries of Central Garage technicians which amounts Birr 1,724,000
are included in the Head office Overhead, it has to be deducted from direct cost of Districts
and Projects with the proportion 55% and 45% respectively.
Therefore, the proportion thereby to determine the contribution of common head office
overhead in to the District overhead will be:
= 122,551,800
203,065,800
= 0.60
Thus, the portion of common head office overhead that could go to the Districts will be:
= 0.6 * 12,772,900
= 7,663,740
Thus, surcharge rate of overhead or percentage of total Districts' overhead cost from
that of total direct cost of Districts is :
= 51,466,240 * 100
122,551,800
= 42%
Meaning that the total unit cost of each maintenance activity will be increased by 42%
so that it could include the total overhead of the maintenance operation.
= 51,466,240 + 122,551,800
= 174,018,040
The percentage of total overhead cost from that of total amount of maintenance operation is :
= 51,466,240 * 100
174,018,040
= 30%
Assuming the percentage of total overhead cost from that of total amount of construction
projects to be half of the maintenance overhead
= 30%
Profit Margin
By taking commercialization concept into account,it is neccessaary to add some profits on the unit price
There is no any empirical formula to calculate the amount of profit and may vary depending on the demand
and competition in the buisness of free market.However,based on practice we suggest the profit to be 10%
of the total cost.
Ethiopian Roads Authority
Cost Summary
No. Description Total Overhead Cost
Total 12,772,898
***As the necessary steps toward client /contractor split have been completed ,the required budget
for District Engineering Division would be allocated from different source( the capital budget)
Head office overhead cost estimation
10,308,489
Head Office Overhead Cost Estimation
Support Giving Equipment Operational and Total Cost
13 District Engineering Service Station Wagon ( 4 x 4 ) 1 37.18 69.42 3 600 223,080 416,520
Branch Pick Up ( 4 x 4 ) 3 33.87 61.30 4 800 812,880 1,471,200
Sub Total 1,035,960 1,887,720
Total 773,000
( Summary )
Item No Descreption Amount
Total 12,772,898
9,640,485 12,392,104