Submittal Transmittal

Detailed, Grouped by Each Number

LC3 (R-15-085-BF-0) Project # RUH-CP-1502


Tel: Fax:

Date: 3/26/2017 Reference Number: 0956

Transmitted To: Hadi Omar Harb Transmitted By: Stephen Stannard


SSEM AECOM
P.O. Box 6341 P.O. Box 58729
Al Rashid Tower, 5th Floor 4 Floor, Tower 4, Tatweer Tower
Al Ma'athar Street 11515 Riyadh
11442 Riyadh Tel:
Tel: 4625511 Fax:
Fax: 4627804

Qty Submittal Package No Description Due Date Package Action


1 0120 - 013300 - D1 - 2 Method Statement for Formworks, Rebars, 4/3/2017 Reviewed -
Cast-In-Situ Concrete(Pouring, Embedments, Exceptions Noted
Curing)

Transmitted For Delivered Via Tracking Number


Review Hand

Items Qty Description Notes Item Action


001 Method Statement for Reviewed - Exceptions
Formworks, Rebars, Noted
Cast-In-Situ Concrete(Pouring,
Embedments, Curing)

Cc: Company Name Contact Name Copies Notes

Remarks

Reviewed; Exceptions Noted, Resubmission Required.

1. Page 4 Equipment – Add “concrete truck mixer” on the equipment list.


2. Page 7 Formworks
a. Arrange sequence of works from preparation of formworks, installation and removal.
b. Indicate that design of formworks for critical concrete construction shall be submitted for review.
c. Include and specify materials type to be used for forms including accessories.
d. Include formworks tolerances specified and mentioned in ACI 117.
e. Include provision of 20mm chamfer on all exposed edges of concrete structure.
f. Indicate that form tying device will not be embedded in the concrete
3. Page 9 Steel Reinforcement
a. Include and specify reinforcing steel types and accessories.
b. Indicate minimum steel cover as per ACI 318 Section 7.7.
c. Include spacing of ties at intersections.

Prolog Converge Printed on: 3/26/2017 Prolog KKIA Page 1


Submittal Transmittal
Detailed, Grouped by Each Number

d. Specify that the detail of reinforcement will be in accordance with ACI SP-66 or equivalent.
4. Page 9 Anchor Bolt and Embedded Item
a. Include and specify types of anchor bolts, embedded items and accessories.
5. Page 10 Concrete Pouring
a. Check spelling of “Concrete”
b. Include Civil QC Inspector to check the truck delivery note to establish that the correct type of concrete has been
delivered.
c. Mention involvement of third party technician to include it duty and responsibility.
d. Include location where concrete samples are to be taken.
e. Sampling of concrete shall be using a cylinder not a cube.
f. Frequency of concrete cylinder sampling shall be every 110 cubic meter or fraction thereof per day and every type of
concrete.
g. Indicate minimum and maximum concrete slumo and temperature.
h. Indicate that concrete shall be use within 90 minutes after water has been added at the plant. Tampering of mix by
adding water will not be allowed.
i. Indicate maximum layer thickness of placed concrete.
j. Indicate maximum drop of concrete.
k. Indicate that use of bagger mixer is not allowed.
6. Page 11 Stripping of Formworks
a. Indicate duration of form removal as per ACI 347.
7. Include section for surface preparation and moisture test prior to bitumen coat application.

Regards,

Signature Signed Date

Prolog Converge Printed on: 3/26/2017 Prolog KKIA Page 2