You are on page 1of 15

Engineering Geology 53 (1999) 311–325

Mechanism of creep movement caused by landslide activity and


underground erosion in crystalline schist, Shikoku Island,
southwestern Japan
G. Furuya a,*, K. Sassa a, H. Hiura b, H. Fukuoka a
a Disaster Prevention Research Institute, Kyoto University, Uji, Kyoto 611-0011, Japan
b Faculty of Agriculture, Kochi University, Nankoku, Kochi 783-0093, Japan
Received 3 April 1998; accepted 30 November 1998

Abstract

The mechanism of creep movement of the Zentoku landslide in crystalline schist has not been studied in detail
because of the steepness of the slope, very slow movement, low population density and complex topographic and
geologic characteristics. Sassa et al. (1980: Proc. INTERPRAEVENT 1, 85–106) and Sassa (1984: Proc. 4th
International Symp. on Landslides, Toronto, vol. 2, pp. 179–184; 1985. Geotechnical classification of landslides, Proc.
4th International Conference and Field Workshop on Landslides, Tokyo, pp. 31–40; 1989: Landslide News, Japan
Landslide Society, No. 3, pp. 21–24) monitored landslide movement and groundwater level at the Zentoku landslide
on Shikoku Island, southwestern Japan, and suggested that the mechanism may be caused by underground erosion.
To study the influence of underground erosion at this site, continual monitoring of suspended sediment and water
discharge from a groundwater outlet (i.e. a spring) was implemented. The locations of groundwater flow paths were
determined, as were the amounts of discharged sediment. Slope deformation was monitored by means of a borehole
inclinometer. The conclusions were as follows: (1) the flow paths were found to be on or above the shear zones in
which underground erosion has occurred; (2) in addition to being a result of precipitation and groundwater discharge,
sediment discharge is affected by landslide activity; and (3) the mechanism of creep movement is an interrelated chain
process that combines underground erosion caused by landslide activity with landslide activity caused by underground
erosion. Thus, landslide activity increases erosion susceptibility and transportation of soils within the mass, and
underground erosion causes instability of the landslide mass, in turn.
This mechanism can explain the observed phenomenon that the Zentoku landslide not only moves actively during
heavy rain, but also continues to creep throughout the year. © 1999 Elsevier Science B.V. All rights reserved.

Keywords: Crystalline schist; Erosion; Landslide activity; Monitoring; Sediment discharge

* Corresponding author. Fax: +81-774-384300.


E-mail address: furuya@landslide.dpri.kyoto-u.ac.jp (G. Furuya)

0013-7952/99/$ – see front matter © 1999 Elsevier Science B.V. All rights reserved.
PII: S0 0 1 3 -7 9 5 2 ( 9 8 ) 0 0 08 4 - 2
312 G. Furuya et al. / Engineering Geology 53 (1999) 311–325

Bonnard, 1983; Kronfellner-Kraus, 1980; Sassa


1. Introduction et al., 1980; Sassa, 1984, 1985, 1989). However,
the mechanism of movement, especially in the case
Many landslides occur in areas of crystalline of creep movement of landslides, is not yet well
schists distributed along orogenic zones in Circum- understood. This is partly because landslides in
Pacific and European countries (e.g., Baumer, crystalline schists have more complex topographic
1988; Riemer et al., 1988; Oyagi, 1989; Gillon and and geologic features than those in sedimentary
Hancox, 1992; Noverraz, 1996). Most studies in clays and shales. Many landslides in crystalline
these areas have been carried out as geologic schists have occurred on Shikoku Island, south-
investigations (e.g., Zischinsky, 1966; Mahr and western Japan (Ando and Ohkubo, 1970; Kato
Nemčok, 1977; Chigira, 1984, 1985), laboratory and Hada, 1980; Fujita et al., 1973). The Zentoku
tests ( Yagi et al., 1989), and monitoring (e.g. landslide (Fig. 1), which has a large number of

Fig. 1. Location map and plan of the Zentoku landslide.


G. Furuya et al. / Engineering Geology 53 (1999) 311–325 313

homes on it, and is one of the largest crystalline (1) temporary discharge caused by heavy rain; and
schist landslides in Japan, was selected for this (2) continuous discharge throughout the year.
study. Their studies were concerned only with the rela-
Since 1972, movement of the Zentoku landslide tionship between landslide activity and
has been monitored by extensometers, and water underground erosion. Thus, they did not ade-
levels have been monitored by borehole water quately deal with quantitative considerations of
gauges (Sassa et al., 1980; Sassa, 1984, 1985, 1989). the mechanism of creep movement.
From these monitorings, it was pointed out that In this study, the authors have quantitatively
when the peak borehole water level reached a correlated landslide displacement, precipitation,
certain critical level, large movement occurred, sediment and discharge at a groundwater outlet
while when the peak borehole water level did not (i.e. a spring). The existence of eroded soils result-
reach a certain critical level, small movement ing from factors other than precipitation (ground-
occurred (Fig. 2). Sassa (1985, 1989) pointed out water discharge) also has been examined. On the
that the large movement, residual-state sliding, basis of these analyses, a mechanism for creep
occurred when the stress on the slip surface reached movement of landslides in areas of crystalline
the residual-state failure envelope, while small schists has been proposed.
movement, creep, occurred when the stress on the
slip surface did not reach the failure envelope.
Sassa (1985, 1989) explained that creep was caused 2. Brief view of monitoring site
by underground erosion and transportation of the
soils in the surrounding groundwater flow paths. The Zentoku landslide is located in a crystalline
Hiura et al. (1991) and Matsunaga et al. (1993) schist area south of the Median Tectonic Line on
suggested that two types of sediment discharge Shikoku Island (Fig. 1). On the middle and lower
cause underground erosion: parts of slope, the landslide occurs mainly in pelitic
and partially green schist; on the upper slope, the
slide may be in psammitic schist ( Fig. 3). Deeper
shear zones (slip surfaces) have formed at depths
of 30–60 m and shallower ones at 15–20 m. The
shear zones are clayey, but include gravels and
sands. In these zones, rocks have been pro-
gressively crushed and oxidized (they are almost
brown in color). The dip of the bedding is nearly
parallel to the slope; the crushed zones and the
concave shape of the bedrock have been detected
by seismic exploration. The mean slope is ca 28°
the length of the landslide is approximately
1300 m; and the maximum landslide width is
approximately 500 m. Landslides in crystalline
schists on Shikoku Island are known to have a
high frequency of occurrence where the schist is
pelitic, the dip of bedding is nearly parallel to the
slope, and the mean slope is from 25 to 30° (Fujita
et al., 1973, 1976). The Zentoku landslide is one
such as this.
Sliding blocks (Block 1, 2, 3-1, 3-2, 3-3) are
shown in Figs. 1 and 3. The dimensions of these
Fig. 2. Relationship between the peak borehole water level and blocks have been approximated by the following
landslide movement at the Zentoku landslide (Sassa, 1984). means of monitoring and investigation:
314 G. Furuya et al. / Engineering Geology 53 (1999) 311–325

Fig. 3. Geologic cross-section through the Zentoku landslide along the line of extensometers.

(1) Installation of 29 long-span extensometers in tored at Springs 1 to 4 ( Fig. 1). In this paper, the
uninterrupted sequence. results of measurements at only Spring 1 are
(2) Installation of 100 three-dimensional shear presented for the following reasons:
displacement meters transversely across the (1) because Spring 1 is located at the toe of Block
Zentoku landslide to measure three-dimen- 1, it seems that sediment can be transported
sional slope movement (Hiura et al., 1992). along the slip surface (shear zone) of Block 1,
(3) Drilling of 11 boreholes for geologic investiga- which must be related to the landslide activ-
tion and six boreholes for installation of ity; and
inclinometers. (2) because Spring 1 is located near the monitor-
Blocks 1 and 2 have deeper shear zones, while ing points of B2 (extensometer S14) and 4-25
Blocks 3-1, 3-2, 3-3 have shallower shear zones (point of borehole inclinometer measure-
(Furuya et al., 1997). Sometimes these blocks have ment), it is possible to compare landslide
become independently active, sometimes displacement and sediment discharge at
dependently. Spring 1.
Fig. 4 shows the apparatus for monitoring sedi-
ment discharge at Spring 1. The initial type appara-
3. Monitoring of underground erosion and landslide tus used from April 1984 to June 1995 is shown
movement in Fig. 4(a). In using this apparatus, the sediment
transported by groundwater flow through the land-
3.1. Monitoring method for groundwater and slide is collected by a stainless steel pipe and
sediment discharge through groundwater outlets accumulates in the bucket. The accumulated sedi-
ment is removed approximately monthly (except
In the Zentoku landslide, sediment discharge during the winter), and is weighed after being
caused by underground erosion has been moni- dried. Fig. 4(b) shows the improved apparatus,
G. Furuya et al. / Engineering Geology 53 (1999) 311–325 315

gauge located near the line of three-dimensional


shear displacement meters shown by 6 in Fig. 1.

3.2. Monitoring methods for landslide displacement

Displacement of the landslide was monitored by


means of a bolehole inclinometer at bolehole 4-25
(70 m depth; strainer treated) and long-span exten-
someters. The extensometers had automatic, con-
tinually recording systems. However, there was no
completely stable point along the line of extensom-
eters ( Fig. 1). Thus, absolute displacement value
could not be obtained. The left side of Fig. 5 shows
the geologic column and the middle graphs present
monitoring results from the borehole inclinometer
in borehole 4-25. Displacement of borehole 4-25
occurred only at depths shallower than 29.5 m.
Below 29.5 m, the mass was stable. The landslide
mass included three shear zones (shear zones 1–3).
Monitoring was not continuous, occurring at
intervals of one to a few months. Therefore, contin-
ual landslide movement was calculated using a
combination of information obtained from exten-
someters and inclinometers by means of the
following procedure:
(1) Search for the point of minimum movement
Fig. 4. System for catching discharged sediment. along the line of extensometers (Fig. 1) from
the results of cumulated records of 29 sets of
extensometers.
(2) Calculate the relative displacement at S14 near
which has been used since 20 June 1995. Using point B2 by using accumulated movement
this apparatus, sediment, with grain size >1 mm values between the point of minimum move-
accumulates on the metal sieve and is automati- ment and point B2.
cally weighed by a load cell; finer sediment (3) Calculate the composite displacement of shear
(<1 mm in size) accumulates in the bucket. Both zones 1–3 at borehole 4-25 by determining the
parts of the sediment are then combined. To detect square root of the A-axis and B-axis displace-
precise sediment data for periods of <1 month, ment for each monitoring day (see Fig. 5) by
automatic records from a load cell were used. borehole inclinometer.
Groundwater discharge is calculated by the (4) Calculate the displacement of borehole 4-25
following V-notch weir (h=30°) conversion equa- by summing the composite displacements of
tion: these shear zones.
(5) Because monitoring of borehole 4-25 incli-
Q=0.233h2.5, (1) nometer occurs only at intervals of one to a
few months, the displacement value at bore-
in which Q is the groundwater discharge hole 4-25 was calculated by interpolation
( l min−1) and h is the depth of water (cm) mea- based on the assumption that movement of
sured on the V-notch weir. the inclinometer is always proportional to that
Precipitation is monitored by means of a rain of point B2 as measured by the extensometers.
316 G. Furuya et al. / Engineering Geology 53 (1999) 311–325

Fig. 5. Shear zones and groundwater flow paths in borehole 4-25.

4. Relationship between underground erosion and water level was at a depth of 63.69 m. The water
displacement of the landslide mass level in the borehole was monitored at a constant
depth of approximately 63–64 m all year. It seems
4.1. Estimation of groundwater flow paths that the borehole water level did not rise above a
depth of 64 m because of leaking of the water into
Slope failures caused by underground erosion the bedrock fissures. The four peaks of seismic
have been noted by Crozier (1986) and Selby output that are shown as G.W.F. 1–4 in the right-
(1993); however, these authors focused mainly on hand graph of Fig. 5 occurred in borehole 4-25.
erosion of the surface soil layer. In a deep shear These zones of higher seismic output undoubtedly
zone of a landslide mass, groundwater plays an were due to groundwater flow paths G.W.F. 1, 3
important role in landslide movement and and 4, which were located in or above shear zones
underground erosion. Hence, a study was con- 1, 2 and 3. G.W.F. 2 was located above the void
ducted to detect the depth of groundwater flow (13.5–14.35 m). From the geological column, it
using seismic detection. The method of investiga- was found that the lower part of the shear zones
tion was to measure the vibration caused by agreed with the depth of highly weathered rocks
groundwater flowing through the landslide mass (clayey sediment is abundant); the middle or upper
by inserting a seismograph into a borehole (Sassa part of shear zones agreed with the depths of
and Sakata, 1977). The vibration was converted moderately weathered rocks (sands and gravels are
into voltage by an amplifier with calibrated volt- abundant) caused by landslide movement. At
age. The output of the seismograph was calculated G.W.F. 1, 3 and 4, the bases of the groundwater
by comparing the obtained voltage with the cal- flow paths occurred at an impermeable layer of
ibrated voltage. highly weathered rock, because the material of
The right-hand graph of Fig. 5 shows ground- moderately rock is more permeable than the mate-
water flow on 15 August 1996. The seismograph rial of highly weathered rock. Thus, at the perme-
could not be inserted deeper than 40 m because of able layer, the groundwater concentrates and flows,
a bend in the borehole. On 15 August, the borehole and subsequently, erodes particles of rock material
G. Furuya et al. / Engineering Geology 53 (1999) 311–325 317

that had been crushed by the landslide activity. At tional to P on the logarithmic diagram, in spite of
G.W.F. 2, the groundwater flow was not found to some scattering. Filled circles represents the results
occur above the voids. Upon the drilling of bore- from April to June 1995, the last part of the
hole 4-25 in 1992, the groundwater path was found longest inactive period between C and D. The
to at the location of the voids because they were distribution of the filled circles data is nearly a
the result of underground erosion. However, the straight line, forming the lower boundary of all
paths of such interconnected voids can be shifted plots. This suggests that sediment discharge in this
upward. Because of the collapse of the void struc- period is affected only by precipitation after a long
ture, the location of the groundwater path had inactive period. Hence, the sediment discharge
likely moved between the time of drilling borehole associated with precipitation can be estimated by
4-25 in 1992 and the time of measurement on 15 the regression line in Eq. (2):
August 1996. W =10−0.83P1.43, (2)
P
in which W is sediment discharge estimated from
P
4.1.1. Ratio of monitored sediment discharge to precipitation (g month−1) and P is the monitored
that estimated from precipitation monthly precipitation (mm month−1).
The infiltration of rainfall causes a reduction of If the sediment discharge in other periods is
shear strength of the landslide mass by raising the greater than the regression line, it is probable that
groundwater level (i.e. increasing pore-water pres- the discharge includes effects other than
sure) and results in increased groundwater flow precipitation.
and underground erosion. Thus, rainfall is an In order to express effects other than precipita-
tion, a new parameter W/W [in which W is the
important effective factor in both landslide move- P
monthly sediment discharge (g month−1) and W
ment and underground erosion. The authors exam- P
is the estimated sediment discharge according to
ined the relationship between landslide displace-
Eq. (2)], termed ‘‘sediment discharge ratio’’ has
ment and amount of eroded sediment associated
been proposed. When W/W =1, the sediment
with precipitation by means of monthly monitoring P
discharge is caused only by rainfall; when
from September 1993 to December 1995. Here, a
W/W >1, the sediment discharge is also affected
parameter D/D (displacement ratio, in which D P
AV by factors other than rainfall; and when
is the monthly displacement and D is the average
AV W/W <1, the discharge of eroded and transported
monthly displacement from September 1993 to P
sediments caused by rainfall is not high enough.
December 1995) is proposed to evaluate landslide Fig. 8 shows the time series of W/W for the
activity. In this examination, monthly displace- P
same monitoring period, including some peak
ment, precipitation and sediment discharge are values of W/W >1. Examining the period of high
taken as the mean amount that occurs in 30 days. P
values of W/W , most of them were noted as
Fig. 6 shows the time series change of monthly P
appearing after the period of peak displacement
displacement and D/D from September 1993 ratio in Fig. 6. The authors compared the displace-
AV
through December 1995. In this figure, D is ments for the active periods (A–E in Fig. 6) with
AV
2.6 mm month−1, and there are five peak values the values of W/W for the same periods, and for
of monthly displacement (A, B, C, D, E ), which P
1, 2 and 3 months afterwards. The displacement
correspond to the peaks of D/D >1. These peak in the active period, A, is the sum of 2-month
AV
periods indicate that the landslide was active. The displacements because activity continued for
other periods, when D/D <1, indicate that the 2 months. The displacements in other active
AV
landslide was inactive. periods (B, C, D, E) are 1-month displacements.
Fig. 7 presents the relationship of monthly sedi- The W/W values that are plotted in Fig. 8 are
ment discharge (W ) to monthly precipitation (P) P
marked by arrows. The results of the comparison
on a logarithmic diagram. In this figure, open are plotted in Fig. 9.
circles represents all monitoring results from Fig. 9 indicates the relationship between the
September 1993 to December 1995. W is propor- displacement during a period of a high level of
318 G. Furuya et al. / Engineering Geology 53 (1999) 311–325

Fig. 6. Change in value of monthly displacement and D/D with time (September 1993–December 1995). Capital letters A–E
AV
represent the most active periods.

landslide activity and the sediment discharge ratio after a high level of landslide activity, the sediment
(W/W ) in the following four periods: open discharge affected by the precipitation considerably
P
squares, for periods of a high level of landslide decreased because the heavy rain had stopped.
activity; filled circles, for a period of 1 month after However, sediment discharge caused by landslide
a high level of landslide activity; crosses, for activity continued at a somewhat consistent rate.
2 months after a high level of landslide activity; The rate of sediment discharge caused by a high
and filled upside-down triangles, for periods of level of landslide activity was relatively higher than
3 months after great landslide activity. According that caused by precipitation. Therefore, most
to this figure, sediment discharge can be classified values of W/W in the first month after high levels
P
into two groups: of landslide activity fell into group A. In the
$ Group A: the sediment discharge ratio is pro- periods of 2 and 3 months after a high level of
portional to landslide displacement during an landslide activity, the sediment discharge caused
active period. by landslide activity gradually decreased; thus, the
$ Group B: the sediment discharge is almost rate of sediment discharge caused by precipitation
independent of landslide displacement. increased relatively, and many W/W values are
P
A high level of landslide activity is commonly plotted in group B. The intersection point of
caused by heavy rain such as during a typhoon. W/W =1 and the inclination line of group A are
P
When heavy rain occurred on the Zentoku land- shown in Fig. 9. This point is called ‘‘critical
slide, a lot of sediment discharge was monitored, displacement’’ (D ). If the displacement is larger
cr
due to the high level of landslide activity. In the than D , the sediment discharge caused by land-
cr
periods of this activity, the sediment discharge was slide activity can be noted.
more dependent on precipitation than on the land-
slide activity because these periods had more pre- 4.1.2. Ratio of monitored sediment discharge to
cipitation than normal periods. Hence, almost all that estimated from groundwater discharge
W/W values for periods of high levels of landslide The correlation shown in Fig. 9 indicates that
P
activity occurred in group B. In the first month landslide activity has an effect on sediment dis-
G. Furuya et al. / Engineering Geology 53 (1999) 311–325 319

Fig. 7. Relationship between monthly precipitation and sedi-


ment discharge for each period and assumed value of W . P, Fig. 9. Relationship between the displacement at high landslide
P activity and W/W . (A) Group affected by landslide activity
Monthly precipitation (mm month−1); W, monthly sediment P
discharge (g month−1); W , sediment discharge estimated from and precipitation; (B) group affected by precipitation; D , criti-
P cr
the above regression line (g month−1). cal displacement.

Fig. 8. Change in value of W/W with time (September 1993–December 1995).


P
320 G. Furuya et al. / Engineering Geology 53 (1999) 311–325

Fig. 10. Change in value of weekly displacement and D/D with time (20 June 1995–3 September 1996). Capital letters A–F represent
AV
the most active periods.

charge. The monitoring of groundwater discharge D =0.7 mm week−1 and that two periods of high
AV
has been carried out since 20 June 1995 to deter- levels of landslide activity occurred:
mine better the relationship between landslide (1) from 20 June to 25 July 1995; and
activity and underground erosion. During this (2) on 26 September 1995.
time, the monitoring system of sediment discharge A lesser amount of high landslide activity (the
shown in Fig. 4(b) was improved to a semi-auto- value of D/D is nearly 2) occurred on 24 October
AV
matic procedure. Semi-automatic monitoring of 1995 and 16 July 1996. Slow movement took place
groundwater discharge was carried out at Springs during the other monitoring periods.
1 and 4 ( Fig. 1). The monitoring data from Spring Fig. 11 shows the relationship between weekly
1 were used for analysis because Spring 1 is located sediment discharge W (g week−1) ( logarithmic
close to the key borehole inclinometer 4-25 at the value) and weekly groundwater discharge Q
center of landslide. Data from 20 June 1995 to 3 ( l week−1) ( logarithmic value). Open circles repre-
September 1996 were used. Almost the same sents all monitoring results from 20 June 1995 to
method of analysis to that described in Section 4.2 3 September 1996 in Fig. 10. Filled circles are the
was employed substituting groundwater discharge monitoring results for 28 May to 9 July 1996,
for precipitation. However, the time unit was which was the inactive period that occurred over
changed from months to weeks, that is, weekly a period of ca 8 months after the high level of
sediment discharge W (g week−1), and weekly landslide activity of 24 October 1996 and before
groundwater discharge Q ( l week−1). the high level of landslide activity of 16 July 1996
Fig. 10 shows the time series change of landslide shown in Fig. 10. The line in Fig. 11 presents the
regression of the data shown by the filled circles.
displacement and displacement ratio, D/D (D is
AV The sediment discharge correlates with ground-
the weekly displacement and D is the weekly
AV water discharge as expressed by:
average displacement), from 20 June 1995 to 3
September 1996. This figure indicates that W =10−6.48Q2.00, (3)
Q
G. Furuya et al. / Engineering Geology 53 (1999) 311–325 321

we could not calculate W/W because the bucket,


Q
the water tank and the V-notch weir were frozen.
To check whether or not the unknown factor
was a result of the landslide activity, a comparison
was made between the displacement during active
periods and the value of W/W . The high landslide
Q
activity periods in Fig. 10 occurred from 20 June
to 25 July 1995 and on 26 September 1995. Activity
from 20 June to 25 July 1995 was caused by heavy
rain during the rainy season. Usually a period of
landslide activity due to heavy rainfall terminated
within 2 weeks after the rain ended. Each fortnight
for A, B, C, D and E are regarded as one group
of landslide activity. On 26 September 1995, F was
caused by the typhoon No. 24 ( T9524). The arrow
from A in Fig. 12 is an example of the comparison
between the displacement of period A (see Fig. 10)
and log(W/W ). The serial numbers (0–7) in this
Q
figure are the number of weeks after landslide
activity ‘‘A’’ from 20 to 27 June 1995.
Fig. 13 shows the distribution of log(W/W )
Q
from 5 to 7 weeks after high landslide activity
against its displacement. In this figure, the open
circles are for 5 weeks, the filled diamonds are for
Fig. 11. Relationship between weekly discharge, sediment dis- 6 weeks and open upside-down triangles is for
charge, assumed values of W . Q, Weekly groundwater
Q 7 weeks after high levels of landslide activity. When
discharge (l week−1); W, weekly sediment discharge the displacement is larger than D and
(g week−1); W , sediment discharge estimated from above cr
Q log(W/W )>0, the displacements of high levels of
regression line (g week−1). Q
landslide activity (A–F ) are proportional to
log(W/W ) from 5 to 7 weeks. Notably, the scatter
Q
in which W is the sediment discharge estimated of data for 6 weeks after high levels of landslide
Q
from the groundwater discharge (g week−1) and activity is very small. These results mean that,
Q is the groundwater discharge ( l week−1) moni- when the displacement exceeded a certain critical
tored weekly. Thus, the effect of the landslide value, the sediment discharge was caused by land-
activity can be evaluated by W/W , as well as by slide activity. These considerations correspond to
Q
W/W . the presumption presented in Section 4.2. Thus, it
P
Fig. 12 shows the time series change of W/W has been proved that the eroded and transported
Q
( logarithmic value). In this figure, large values of sediments are mainly the result of landslide
log (W/W ) occur in the left side of the figure for activity.
Q
the first half of all monitoring periods (i.e. from
18 July to 19 December 1995). In the right half of
the figure, the values of log(W/W ) occuring from 5. Mechanism of landslide movement caused by
Q
13 February to 3 September 1996. It seems landslide activity and underground erosion
that some unknown factor causes sediment dis-
charge to a greater amount than groundwater Sassa (1984, 1985, 1989) has proposed that
discharge does in the first half of all monitoring creep movement at the Zentoku landslide is caused
periods. From 26 December 1995 to 9 January by underground erosion. It would be expected that
1996 and from 23 January to 13 February 1996, if underground erosion were to continue for a long
322 G. Furuya et al. / Engineering Geology 53 (1999) 311–325

Fig. 12. Change in value of log(W/W ) with time (20 June 1995–3 September 1996). W/W , Sediment discharge ratio for ground-
Q Q
water discharge.

period of time, the amount of erosion-prone mate-


rial being removed would decrease and the creep
movement would gradually terminate. However, it
has been shown that creep has continued at the
Zentoku landslide (Sassa, 1984; Furuya et al.,
1997). It is insufficient to explain this movement
alone as an effect of the underground erosion.
Consequently, it can be hypothesized that the
movement mechanism is not the only process of
underground erosion that causes landslide activity,
but also that there is some other process.
Fig. 14 illustrates the overall mechanism of a
landslide in crystalline schist as studied at the
Zentoku landslide; this mechanism includes two
interrelated processes. On the left of this figure the
process of landslide activity caused by
underground erosion is shown, which has been
previously proposed by Sassa (1984, 1985, 1989).
The soils and other fine materials surrounding the
groundwater flow path are eroded and transported
by groundwater flows. Thus, the voids tend to
enlarge there, which makes the landslide mass
unstable. Hence, landslide activity (creep move-
ment) occurs. On the right in Fig. 14 is shown the
process of underground erosion caused by the
Fig. 13. Relationship between displacement during periods of landslide activity, as indicated by the results of
high levels of landslide activity and log(W/W ) for the period
Q this study. The fine-grained materials are produced
of 5–7 weeks after this activity. W/W , Sediment discharge ratio
Q by disturbance and mechanical weathering of geo-
for groundwater discharge; D , critical displacement; r, correla-
cr
tion coefficient. logic materials in the shear zone due to the land-
G. Furuya et al. / Engineering Geology 53 (1999) 311–325 323

the sediment affected by high levels of land-


slide activity. Especially, the sediment dis-
charge ratio in the period of 1–2 months (from
5 to 7 weeks) after a high level of landslide
activity is proportional to the landslide dis-
placement. Greater landslide activity caused
greater sediment discharge.
Therefore, creep movement of this landslide in
crystalline schist has occurred over a long period
of time as the result of two interactive processes:
(1) landslide activity that produced fine-grained
materials; and
(2) underground erosion of these materials by
groundwater, which in the landslide mass
helped to cause the landslide activity.

6. Conclusions

The mechanism of creep movement caused by


landslide activity and underground erosion in crys-
talline schist is proposed; the Zentoku landslide,
Shikoku Island, serves as an example. This mecha-
nism is based on the results of:
Fig. 14. Chain interrelationship of processes of erosion and (1) measurements of sediment discharge from
landslide movement in the Zentoku landslide. groundwater outlets (springs);
(2) measurement of landslide activity; and
slide activity. Erosion susceptibility inside the (3) investigation of the groundwater flow (paths)
landslide mass increases. The latter process is within the landslide.
supported by the following facts: The conclusions are as follows:
(1) Fukuoka (1991) carried out ring-shear tests (1) Groundwater flow exists in and above shear
on samples of material from the Zentoku zones in the landslide because the bases of
landslide under a normal pressure of 294 kPa. these zones are highly weathered, clayey and
These tests indicated that, as shear displace- impermeable. Because of this groundwater
ment increases, the degree of grain crushing flow, underground erosion occurs in and above
also increases. The depth of the shear zone at the shear zones.
the Zentoku landslide (Block 1) is >20 m. It (2) Erosion and transportation of sediments are
is reasonable to believe that crushing of the caused not only by the effects of precipitation
rocks due to the weight of the landslide mass and resulting groundwater discharge, but also
occurs in the shear zone. by the effects of landslide activity. In particu-
(2) Seismic investigation has revealed that lar, there is a proportional relationship
groundwater flow paths exist in and above the between landslide displacement during high
shear zones. The rocks have been crushed into levels of landslide activity and the sediment
fine-grained particles due to the landslide discharge ratio (W/W or W/W ) for periods
P Q
activity and these particles were eroded from of 1–2 months (from 5 to 7 weeks) after high
the mass along the groundwater paths. levels of landslide activity. This relationship
(3) Sediment discharge from an outlet of the indicates that erosion susceptibility is
groundwater path (i.e. at a spring) included increased by landslide activity.
324 G. Furuya et al. / Engineering Geology 53 (1999) 311–325

(3) Active landslide movement causes disturbance Fujita, T., Hirano, M., Hada, S., 1976. The structural control
and crushing of rocks into erodible and trans- of landslides in the Kawai area, Tokushima Prefecture, Shi-
koku. J. Jap. Landslide Soc. 13 (1), 25–36 (in Japanese).
portable material in the shear zones. Fukuoka, H., 1991. Variation of the friction angle of granular
(4) The mechanism of creep movement in this materials in the high-speed high-stress ring shear apparatus:
landslide in crystalline schist is an interrelated influence of re-orientation, alignment and crushing of grains
chain process consisting of underground ero- during shear. Bull. Disaster Prevention Res. Inst. Kyoto
sion caused by landslide activity and landslide Univ. 41 (Part 4), 243–279.
Furuya, G., Sassa, K., Fukuoka, H., Hiura, H., 1997. The rela-
activity caused by underground erosion. The tionship between underground erosion and landslide move-
interrelationship of these two processes is the ment in a crystalline schist landslide, Zentoku, Tokushima,
reason why landslides of this type have contin- Japan. J. Jap. Landslide Soc. 34 (2), 9–16 (in Japanese).
ued to move for many years, and are not Gillon, M.D., Hancox, G.T., 1992. Cromwell Gorge landslides:
easily stabilized. a general overview. In: Bell, D. ( Ed.), Proc. 6th Int. Symp.
Landslides, Christchurch, vol. 2, Balkema, Rotterdam,
pp. 83–102.
Acknowledgments Hiura, H., Sassa, K., Fukuoka, H., 1991. On the mechanism
of a crystalline schist landslide: landslide movement and the
The authors wish to thank the Yoshino River underground erosion. In: The Soviet-China-Japan Symp.
Sabo Work Office of the Ministry of Construction and Field Workshop on Natural Disasters, Shanhai, Lanch-
Japan for its cooperation in monitoring the zou, Urumgi, Alma-ata, Dushanbe and Kazselezashchita,
U.S.S.R, pp. 21–30.
Zentoku landslide. The efforts of Mr Kin-ichiro Hiura, H., Sassa, K., Fukuoka, H., 1992. Monitoring system
Mukai and Mr Michifumi Mukai, who have been of a crystalline schist landslide—three dimensional displace-
engaged in this monitoring and the maintenance ment meters and underground erosion. In: Bell, D. ( Ed.),
of the monitoring apparatus for several years, are Proc. 6th International. Symp. on Landslides, Christchurch,
especially appreciated. vol. 2, Balkema, Rotterdam, pp. 1141–1146.
Kato, J., Hada, S., 1980. Landslide of the Yoshino-gawa water
system and its geological aspects. Research Reports of Kochi
University, Natural Science, 28, pp. 127—140 (in Japanese).
References Kronfellner-Kraus, G., 1980. Neue Untersuchungser gebnisse
in Wildbachen: Der Talzuschub in Abhangigkeit von Nied-
Ando, T., Ohkubo, T., 1970. Remarks on landslides in crystal- erschlagen. Proc. INTERPRAEVENT 1980, Bad Ischl,
line schist areas, Tokushima Prefecture, Shikoku. Bull. Geol. vol. 1, Forschungsgesellschaft für vorbeugende Hochwasser
Surv. Japan 21 (7), 1–42.(in Japanese) bekämpfung, Klagenfurt, pp. 179–192.
Baumer, A., 1988. Three rock slides in the southern Swiss Alps. Mahr, T., Nemčok, A., 1977. Deep-seated creep deformations
In: Bonnard, C. ( Ed.), Proc. 5th International Symp. on in the crystalline cores of the Tatry Mts. Bull. Int. Assoc.
Landslides, Lausanne, vol. 2, Balkema, Rotterdam, Eng. Geol. 16, 104–106.
pp. 1307–1311. Matsunaga, M., Hiura, H., Sassa, K., 1993. Observation of the
Bonnard, C., 1983. Determination of slow landslide activity by movement of ‘‘Zentoku’’ landslide: fluctuation of the eroded
multidisciplinary measurement techniques. In: Kovari, K. and transported sediment. Bull. Kochi Univ. Forests 20,
( Ed.), International Symp. on Field Measurements in 21–31(in Japanese).
Geomechanics, Zurich, Balkema, Rotterdam, pp. 619–638. Noverraz, F., 1996. Sagging or deep-seated creep: Fiction or
Chigira, M., 1984. Mass rock creep of crystalline schist (Part reality? In: Senneset, K. (Ed.), Proc. 7th International Symp.
1): the relationship between geological structures and land- on Landslides, Trondheim, vol. 2. A.A. Balkema, Rotter-
slide topographies in the Sambagawa terrain in the Kanto dam, pp. 821–828.
mountainous land. J. Jap. Soc. Eng. Geol. 25 (4), 32–44 Oyagi, N., 1989. Geological and economic extent of landslides
(in Japanese). in Japan and Korea. In: Brabb, E., Harrod, B. ( Eds.), Proc.
Chigira, M., 1985. Mass rock creep of crystalline schist (Part of 28th International Geological Congress, Washington, DC.
2): minor structures formed by mass rock creep. J. Jap. Soc. A.A. Balkema, Rotterdam, pp. 289–302.
Eng. Geol. 26 (2), 25–79 (in Japanese). Riemer, W., Locher, T., Nunez, I., 1988. Mechanics of deep
Crozier, M.J., 1986. Landslides: Causes, Consequences and seated mass movements in metamorphic rocks of the Ecuad-
Environment. Croom Helm, Australia, p. 252. orian Andes. In: Bonnard, C. (Ed.), Proc. 5th International
Fujita, T., Ando, N., Tanaka, K., Hakamada, N., 1973. Study Symp. on Landslides, Lausanne, vol. 1, Balkema, Rotter-
of landslides in crystalline schist areas, Tokushima Prefec- dam, pp. 307–310.
ture, Japan. J. Jap. Soc. Eng. Geol. 14 (1), (2), 65–69 (in Sassa, K., 1984. Monitoring of a crystalline schist landslide:
Japanese). compressive creep affected by ‘‘underground erosion’’. In:
G. Furuya et al. / Engineering Geology 53 (1999) 311–325 325

Proc. 4th International Symp. on Landslides, Toronto, mechanism of a crystalline schist landslide ‘‘Zentoku’’ in
vol. 2, Univ. Toronto Press, Downsview, pp. 179–184. Japan. Proc. INTERPRAEVENT 1980, Bad Ischl, vol. 1,
Sassa, K., 1985. Geotechnical classification of landslides. In: Forschungsgesellschaft für vorbeugende Hochwasser
Proc. 4th International Conference and Field Workshop on bekämpfung, Klagenfurt, pp. 85–106.
Landslides, Tokyo, Japanese Landslide Society, pp. 31–40. Selby, M.J., 1993. Hillslope Materials and Processes, 2nd ed.
Sassa, K., 1989. Geotechnical classification of landslides. Land- Oxford University Press, Oxford, p. 451.
slide News, Japan Landslide Society, No. 3, pp. 21–24. Yagi, N., Enoki, M., Yatabe, R., 1989. A prediction method
Sassa, K., Sakata, D., 1977. Measurement of the ground water on displacement of fractured zone landslide. J. Geotechnical
velocity using seismic detector. In: 5th Japanese Symp. on Eng. 406 (III–11), 53–60 (in Japanese).
Rock Mechanics, Tokyo, Japan Society of Civil Engineers, Zischinsky, U., 1966. On the deformation of high slopes. In:
pp. 13–18 (in Japanese). Proc. 1st Congress International Society for Rock Mechan-
Sassa, K., Takei, A., Kobashi, S., 1980. The movement and the ics, Lisbon, Bertrand, vol. 2, pp. 179–185.

You might also like