Professional Documents
Culture Documents
Chen Jianping
Group Leader
Relay Protection Dept., Power Dispatching
Center, YNPG.
Self-Introduction
Profile:
Leader of relay settings calculation
group in Relay Protection Dept. of
Yunnan Power Dispatching Center,
now is responsible of relay settings
Chen Jianping
calculation, relay settings checking
and relay calculation management
Yunnan, Kunming for the power system of 220kV and
+86 18313774382
591779338@qq.com
above in YNPG.
1
2/26/2019
2
2/26/2019
1)Selectivity
2)Sensitivity
3)Speedability
4)Reliability
1) Selectivity
3
2/26/2019
2) Sensitivity
xs max
xs min
3)Speedability
4
2/26/2019
4) Reliability
10
5
2/26/2019
Selectivity
Relay
Setting Sensitivity
Speedability
11
1
Basic relay setting principles
Part
1. Four characteristics of relay protection
2. Basic relay setting principles
12
6
2/26/2019
1)Concept of cooperation
《220kV~750kV电网继电保护装置运行整定规程》(行标)
《Setting guide for 220 kV~750kV power system protection equipment 》
13
1)Concept of cooperation
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG》
14
7
2/26/2019
1)Concept of cooperation
Complete cooperation
It means that the two adjacent protections can
cooperate both in protection range and action time, that is,
the selectivity requirement is met.
k
I
Z set1
II
t Z set 1
III
Z set 1
t1III
t2III
15
1)Concept of cooperation
Incomplete cooperation
It means that the two adjacent protections can just
cooperate in action time, but not in protection range.
k
I
Z set 1
II
t Z set 1
III
Z set 1
t1III
t2III
t1II
t2II t3II
t1I t2I t3I
16
8
2/26/2019
1)Concept of cooperation
No cooperation
It means that the two adjacent protections can't
cooperate both in protection range and action time, that is,
the selectivity requirement cannot be met.
k
I
Z set1
II
t Z set 1
III
Z set 1
t1III
t2III
17
2)Basic principles
《220kV~750kV电网继电保护装置运行整定规程》(行标)
《Setting guide for 220 kV~500kV power system protection equipment 》
18
9
2/26/2019
2)Basic principles
《220kV~750kV电网继电保护装置运行整定规程》(行标)
《Setting guide for 220 kV~500kV power system protection equipment 》
19
20
10
2/26/2019
21
1)Operation characteristic
M
1QF 2QF
N
Id:The differential current, it's the sum
k1 k2
I d IM IN
K I r IM IN
I dz I d I dz
Ir I d K Ir
22
11
2/26/2019
2)Setting Principles
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
23
2)Setting Principles
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
24
12
2/26/2019
1. Differential Protection(87)
2. Distance Protection(21)
3. Zero-sequence Overcurrent Protection(50/51G)
25
Z1 Z s Z m , Z 2 Z1 , Z 0 Z s 2Z m
26
13
2/26/2019
1)Configuration
Stage 1 Stage 1
Stage 2 Stage 2
Stage 3 Stage 3
27
2)Operation characteristic
1
Z set
2
28
14
2/26/2019
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Stage 1
(1)Stage 1 should reliably escape the grounding fault
on the opposite side busbar of this line;
(2)For the line below 5 km, in order to prevent wrong
tripping when fault outside this line, stage 1 should be
disabled;
(3)For the line below 20km, the reliability coefficient K
should be set according to the following formula:
5
K k 0.7 1
L
29
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Stage 2
(1)Stage 2 should guarantee sufficient sensitivity of
metal grounding fault on the opposite side busbar of this line;
(2)Stage 2 should consider cooperation with adjacent
line protections,to cooperate with stage 1,pilot protection
or stage 2 of the next line;
(3)The protection range of stage 2 should generally
not exceed the other side busbars of adjacent transformers .
30
15
2/26/2019
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Stage 3
(1)Stage 3 should guarantee sufficient sensitivity of
metal grounding fault on the opposite side busbar of this line;
(2)Stage 3 should consider cooperation with adjacent
line protections,to cooperate with stage 2 or stage 3 of the
next line;
(3)Stage 3 should consider escape the minimum load
impedence of this line;
(4)Stage 3 should consider escape power swing, its
time setting should be larger than 2s.
31
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Stage 1
(1)Stage 1 should reliably escape the grounding fault
on the opposite side busbar of this line;
(2)For the line below 5 km, in order to prevent wrong
tripping when fault outside this line, stage 1 should be
disabled;
(3)For the line below 20km, the reliability coefficient K
should be set according to the following formula:
5
K k 0.8 1
L
32
16
2/26/2019
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Stage 2
(1)Stage 2 should guarantee sufficient sensitivity of
metal grounding fault on the opposite side busbar of this line;
(2)Stage 2 should consider cooperation with adjacent
line protections,to cooperate with stage 1,pilot protection
or stage 2 of the next line;
(3)The protection range of stage 2 should generally
not exceed the other side busbars of adjacent transformers .
33
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Stage 3
(1)Stage 3 should consider cooperation with adjacent
line protections,to cooperate with stage 2 or stage 3 of the
next line;
(2)Stage 3 should consider escape the minimum load
impedence of this line;
(3)Stage 3 should consider escape power swing, its
time setting should be larger than 2s.
34
17
2/26/2019
3)Setting Principles
I
Z set 1
t Z setII 1
III
Z set 1
t1III
t2III
35
1. Differential Protection(87)
2. Distance Protection(21)
3. Zero-sequence Overcurrent Protection(50/51G)
36
18
2/26/2019
T1 A k B T2
I 01 I 02
U0
U A0 U B0
I0
Ir 3 I0
U r 3U 0 r 0 3U 0
37
1)Configuration
38
19
2/26/2019
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Define Time
(1)To guarantee sufficient sensitivity of metal
grounding fault on the opposite side busbar of this line;
(2) To cooperate with pilot protection, define time
stage ,or stage 2 of ground distance protection of the next
lines;
(3)To escape the other side busbars of adjacent
transformers ;
(4)To escape the zero sequence current of
discrepancy state.
39
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Inverse Time
(1)Adopt IEC normal inverse time characteristic;
0.14
t(I0 ) I 0 0.02
Tp
( ) 1
Ip
40
20
2/26/2019
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Stage 1:
(1)To guarantee sufficient sensitivity of metal
grounding fault on the opposite side busbar of this line;
(2) To cooperate with pilot protection, stage 1 ,or
stage 2 of ground distance protection of the next lines;
(3)To escape the other side busbars of adjacent
transformers ;
(4)To escape the zero sequence current of
discrepancy state.
41
《南方电网220kV~500kV系统继电保护整定计算规程》
《Setting guide for 220 kV~500kV power system protection equipment of CSG 》
Stage 2:
(1)To escape the maximum unbalanced current in
maximum load state;
(2)Reliably start when high resistance ground fault
happened in this line, and the primary value should not be
larger than 300A, the secondary value should not be smaller
than 0.08In.
(3)To cooperate with stage 1 or stage 2 of the next
lines.
42
21
2/26/2019
2)Setting Principles
t1Ⅱ tⅡ
2
tⅠ t tⅠ t tⅠ
1 2 3
t1Ⅱ
t t Ⅱ
2
tⅠ
1 tⅠ2 tⅠ3
43
44
22
2/26/2019
1. Basic considerations
45
46
23
2/26/2019
L-3 T-3
T-1 T-2 I II
L-1 L-2
G1 I II I II
T-4
III L-4
I f I II LD
IG1 xn1 L1
xn 2
V
G1
V
L1
G2
47
jX III
Positive sequence IG 1a (1) IL1a (1) I fa (1)
Z LD
equivalent circuit E1
VG1a (1) VL1a (1) V fa (1)
jX G2(1)
E2
jX G1(2) jX T1 jX L1 jX L 2 jX I jX II jX L 4 jX T4
jX III
Negative sequence IG 1a (2) IL1a (2) I fa (2)
jX G2(2) Z LD
equivalent circuit
VG1a (2) VL1a (2) V fa (2)
48
24
2/26/2019
49
50
25
2/26/2019
51
52
26
2/26/2019
53
54
27
2/26/2019
55
56
28
2/26/2019
1. Basic considerations
57
58
29
2/26/2019
Side A Side B
FO.LocID 7012 FO.LocID 1072
FO.RmtID 1072 FO.RmtID 7012
59
ZL
(1)Protection at the scheduled break
EM , Z M
I k
EN , Z N
point should not be controlled by power
UM
U0
I
swing blocking.
(2)Fast trip protection that escaping the
EM EN
I ZM
60
30
2/26/2019
1 K k Z AB K k K b Z KZ 2
II I
Z KZ
61
62
31
2/26/2019
Thank you!
63
32