Professional Documents
Culture Documents
Dale Courtney
Program Engineer
NAS Implementation Program
Federal Aviation Administration
800 Independence Avenue SW, 700W
Washington, DC 20591, USA
Email: dale.courtney@faa.gov
David A. Quinet
Program Engineer
Avionics Engineering Center
228 Stocker Center, Ohio University
Athens, Ohio 45701, USA
Email: quinet@bobcat.ent.ohiou.edu
COMPARISON OF GLIDE SLOPE PERFORMANCE
AT A CHALLENGING SITE
SITE
Elevation (feet)
10
0
The area of consideration for a glide slope
installation on the southeast side of the
0
74
75
50
75
75
0
97
00
-10
13
20
26
34
35
10
runway is described as having a truncated
-20
ground plane both laterally and
longitudinally. The runway shoulder -30
gradually slopes downward until about 400 Range (feet - from Threshold)
feet from centerline, and then quickly
Figure 2: Graphical representation of terrain at Columbus.
drops off about 40 feet in elevation. The
terrain in front of the glide slope antenna UPSLOPE OVERVIEW
area gradually slopes downward. This
downward slope continues past the Upslope Description
threshold for about 1500 feet where
elevation is about 25 feet below threshold Transmitting Subsystem. The Upslope
elevation. At this point, the terrain begins Endfire Glide Slope (UEFGS)
to rise upward until about 2400 feet from consists of front, middle, and rear
threshold where elevation is about 18 feet main transmitting antennas along
above threshold elevation. Figure 1 with a single clearance. The front
illustrates the Columbus, GA site looking and rear antennas consist of eight
from the glide slope shelter toward the slotted-cable sections, each 15 feet
approach. Figure 2 is a graphical long with 12 radiating slots in each
representation of a side cut view of the section to produce a 4.0 path angle
terrain toward the approach region. and a very sharp path width. The
rear antenna is positioned to form a
concave shape with a 445-foot
radius. Similarly, the front antenna
forms a convex shape with a 445-
foot radius. These two antennas
are 120-feet long with a separation
distance of 890 feet in the
dimension parallel to the runway.
Table 2: UEFGS Monitor Parameters verses Signals. Figure 3: Recorded monitor and environmental data of upslope
endfire glide slope system.
UPSLOPE EVALUATION
GLIDE SLOPE COMPARISON
The upslope endfire glide slope was
Site Test
installed by the FAA at Columbus, GA in
1997. Work continued from August 1998
System Setup. For comparison purpose,
through March 2001 to optimize the
and to determine if another type of glide
transmitting operation of the upslope
slope would be suitable to provide the
system, develop a monitor system that that
desired service, a site test was performed
properly tracked the performance of the
using an image system on the same side as
transmitting subsystems, and redesign the
the installed upslope. While performing
clearance radiated signal – which resulted
this site test, all three image glide slope
in a single-clearance antenna with integral
systems currently in service in the National
monitoring. In late 2001, optimization and
Airspace System were evaluated.
monitor development work was
Specifically, the null-reference, sideband-
completed. The system still exhibits a
reference, and capture-effect glide slope
close-in path reversal, but was deemed
configurations were tested. A portable
optimized. The transmitting and
glide slope mast was used to mount the
monitoring subsystems are currently
antennas, figure 4 and a Wilcox Mark 1F
operating in a test configuration. The
transmitter with Mark 1C distribution units
system is operating on a non-published,
were placed in a van to drive the antenna
non-localizer paired frequency. The
arrays, figure 5. The site test used the
system is operating to evaluate signal in
same frequency as the upslope system,
space as well as monitor stability. The
329.45 MHz.
intent of this testing is to evaluate the
system for long-term performance, system
stability in a wide range of weather
conditions, and overall maintainability of
the system. Currently, the upslope endfire
glide slope is operating in a test
configuration with monitor data as well as
environmental data being recorded. Figure
3 is recorded data of the upslope endfire
system showing the variation of the
executive monitor parameters with respect
to environmental conditions including
temperature, precipitation, wind speed, and
barometric pressure. Figure 4: Image Glide Slope Test Setup.
upslope system provides for a very smooth
and straight path between ILS Point A and
B, as shown in figure 9. There is,
however, a quick change of path direction,
150 Hz predominance, at ILS point B.
This change of direction as evaluated using
current reversal criteria would qualify as a
path reversal and the location at this point
would determine the minimum altitude to
which coupled approaches would be
authorized. FAA Flight Inspection
determined that coupled approaches would
Figure 5: Image Glide Slope Transmitter and Distribution.
not be authorized below 260 feet AGL.
The portable mast was located 232 feet Endfire Glide Slope. The endfire system
offset from the runway centerline and was installed before the upslope and
setback 877 feet, resulting in a Threshold currently commissioned capture-effect
Crossing Height of 50 feet with a 3 path system. A review of past measurements
angle. This location was next to the was performed and included in this paper
existing shelter. The antenna heights were for completeness. The endfire system
established to obtain a 3 path angle. In allows for adjustment of support pedestals
the cases of the sideband and null- to shape the path. Attempts were made to
reference, the theoretical heights were set do this, but in all cases the structure
since the structure roughness from the roughness remained out of tolerance
multipath biased the angle and limited time because of reflections. The level run had
did not allow multiple adjustments. Table significant steps, which resulted in higher
3 contains the final antenna heights and than normal sideband power to obtain the
offsets used in the site test for the three desired path width. By using the mean
glide slope configurations evaluated. width method, the sideband power was
reduced significantly for the structure
roughness to be within tolerance.
Image Glide Slopes. After the test
configuration was setup and aligned using
Antenna Null-Reference Sideband- Capture-Effect
Reference standard phasing procedures, level run
Height Offset Height Offset Height Offset measurements were performed on each
(ft) (in) (ft) (in) (ft) (in)
Lower 13.76 12.77 6.92 7.84 13.67 7.84 configuration to measure the width,
Middle N/A N/A N/A N/A 27.42 0 symmetry, structure angle, and path angle
Upper 27.52 0 20.61 0 41.83 (22.56)
on centerline and at the edges of both sides
Table 3: Antenna Positions of Glide Slope Configurations of the localizer course (tilt). For the null-
Tested.
reference, sideband-reference, and
Test Results standard endfire, the level runs exhibited
steps in the vertical proportional guidance
Upslope Endfire Glide Slope. Since the sector which was caused by the upsloping
upslope had previously been optimized for terrain under the approach path as seen in
the test, periodic measurements were figure 2. Only the upslope and capture-
performed on this system prior to any effect systems showed a linear glide slope
setup of the image systems. These results crossing, indicating reflections from the
include verification of the proportional terrain are minimized with the below-path
guidance sector, approach, and transverse cancellation provided by these two
structure. These results showed no systems. The sideband power was not
difference to previous measurements adjusted to tighten the width since with
collected in August 2001. In fact, the previous tests, the endfire indicated that
the single point method of evaluating the
width would give broader than normal
widths resulting in more roughness. The
sideband powers used for the site test were
set for typical values used in sites with
adequate ground planes.
150 Hz Tilt
Path Angle
Symmetry
90 Hz Tilt
Structure
Width
( )
( )
( )
( )
(%)
9 0 H z C D I (u A ) 1 5 0 H z
Glide Slope Performance Comparison
Sideband-Reference 65 79
Ougtd Modeling (CSG) Level Runs
Capture-Effect 22 16
Standard Endfire 42 59 -600
Upslope Endfire 14 4.9 -500
-400
-300
Table 6: Comparison between measured and theoretical -200
roughness factor. -100
0
100
Modeling Results 200
300
0 1 2 3 4 5
Theoretical vertical sideband radiation Elevation Angle (deg.)
patterns for each of the glide slope systems
considered are plotted in figure 12. This CEGS SBR NR
figure compares relative sideband
amplitude verses elevation for the glide Figure 13: Modeled vertical performance of image glide slopes
tested.
slope systems evaluated.
150H z
Glide Slope Performance Comparison
T he o r e t ic a l Side ba nd E le v a t io n P a t t e r n C o mpa r is o n
OUGTD Modeling (CSG) Approach
(3 de gr e e G lide Slo pe )
40
20
C D I (u A )
#;
0
-20
(
-40
-60
#‚ -80
-100
90 H z
#¥
-120
0 1 2 3 4
#È
Distance From Threshold (nmi)
#ì CEGS SBR NR
(
Figure 14: Modeled approach performance of image glide
E le v a t io n A ngle (de gr e e s )
slopes tested.
150 H Z
REFERENCES
Table 8: Summary of modeling results for vertical performance.
1. United States Standard Flight
As seen by figure 15, the characteristics of Inspection Manual, FAA Order
the path are similar to those measured. 8200.1A
Further investigation has indicated that this 2. Maintenance of Instrument Landing
is caused by the large separation between System (ILS) Facilities, FAA Order
the antennas and is caused by the power 6750.49A
imbalance with the receiver in the near 3. Johnson, John H. and Dr. Richard H.
field of the antenna system. McFarland, “Experimental Assessment
of the Use of an Upslope Model of the
CONCLUSION Endfire Glide Slope System for
Improving Course Quality at
Based on the site testing of five glide slope Columbus, Georgia”, TM 91-36,
configurations at a challenging site, one Avionics Engineering Center, Ohio
with limited terrain along the approach University, Athens, Ohio, August 1991
path as well as laterally, the following 4. McFarland, Richard H. and Jamie S.
conclusions are reached: Edwards, “Investigation of Path
Roughness with the Endfire Glide
1. Glide Slope systems with Slope Serving Runway 5 at the
cancellation of the course signal at Columbus, Georgia Airport”, TM 91-
low elevations provide for a 52, Avionics Engineering Center, Ohio
smoother glide path. University, Athens, Ohio, January 1992
2. To obtain satisfactory performance
throughout the service area, the
capture-effect principal should be
used in both the vertical and
horizontal planes.
3. The performance obtained from the
various system types is consistent
with the modeling and the glide
slope selection criteria contained in
siting orders.