Downtown Parkades - Capital Projects

FY 2006 through 2019

Design & Construct Panel Replacement 2,943,736


Chemeketa Top Deck Assessment 36,278
Elevator Renovations - Chemeketa 258,749
UR Rvrft-Elevator Renovations (Liberty) 119,980
UR Rvrft-Liberty Top Deck renovations 120,737
Liberty - renovations to Stair Nosings and Landings 22,750
Chemeketa - renovations to Stair Nosings and Landings 17,607
URS Facility Site Assessment 19,874
Chemeketa Barrier 7,519
Chemeketa - Roof and Lower Parking Lot Lights 17,726
Chemeketa - Roof renovations (Panels) 58,127
Parkade Exterior Panel Evaluation 13,382
Chemeketa - Design/Construct Panel Reinforcement 9,601
Liberty - Elevator Jack 147,303
Liberty - Top Deck renovations 124,715
Chemeketa - Top Deck 407,922
Marion - Elevators 28,512
Marion - Assessment 12,456
Marion - Brick/Veneer Replacement 19,156
Chemeketa - Cameras 25,499
Marion - Deck Renovations 47,743
Marion - Structural Renovations (stairwells, parapet) 116,740
Chemeketa - Cameras 6,943
Chemeketa - Building System Renovations 367,349
Liberty - Deck Renovations 19,555
Liberty - Stairwell Renovations 91,122
Chemeketa - Elevators 214,110
Chemeketa - Elevators 151,011
Chemeketa - Elevators 287,256
Chemeketa - Elevators 110,210
Chemeketa - South Wall 79,281
Marion - Cameras 48,649
Liberty - Cameras 30,345
Liberty - Elevators 491,473
Chemeketa - Skybridge Renovations 75,653
Chemeketa - Deck Renovations 143,131
Marion - Elevators 439,766
Chemeketa - NW Stair Tower Renovations 50,528
Chemeketa - E Stair Tower Renovations 50,180
Marion - Reseal Roof 75,696
Marion - Lighting Replacement 168,035
Chemeketa - Deck Renovations 50,000
Chemeketa & Liberty - Lighting Replacement 172,623
Marion - Cameras 19,942

7,718,969

Downtown Parkades - Capital Projects


Adopted CIP 2019 through 2023

Liberty - Deck Renovation 165,000


Chemeketa - Deck Renovation 50,000
Chemeketa - Storefront Replacement 421,000
Chemeketa - Top Deck Renovation 125,000
Chemeketa - Expansion Joint renovation 65,000
Liberty - Building System Renovation 110,000
Chemeketa - Exterior Repaint and Awning 450,000
Liberty - Exterior Paint 320,000
Marion - Exterior Masonry Reseal 148,500
Marion - Exterior Paint and CMU Walls 50,000
Marion - Cameras, Fiber Network 90,000
Marion - Storefront and Glass Canopy Replacement 700,000
Marion - Deck Renovations 185,000

2,879,500

Deck renovations - resealing and renovationing concrete decks, slurry sealing, renovation and prevent water penetration, done cyclically on all levels of each parkade
Building system renovations - HVAC, electrical, lighting

Sources of funds - Riverfront - Downtown URA funds as eligible, Parking Funds, Leasehold Funds