Daily Progress Report

Date : 14.03.2018
SL Cumulative Quatity Executed till Quantity Cumulative Quatity
Item Scope Quantity Units Remarks
No previous day Executed Executed
Backfilling (Loose By Volgate Cum 256,746.17 340.00 257,086.17
1 20,00,000 m3
Volume) By Dumper Cum 207,520.00 3,500.00 211,020.00
Casting set Nos 2,415.00 - 2,415.00
Shifting Nos 608.00 8.00 616.00
2337 Nos
2 Fencing Pit Excavation Nos 531.00 12.00 543.00
Installation Nos 508.00 12.00 520.00
Barbed Wire Fixing RM 650.00 - 650.00
3 Temporary Road Outside Power Plant 2800 M RM 2,308.00 - 2,308.00
Ballah Piling 90 M RM 60.00 - 60.00
4 Temporary Jetty Sheet Piling 268 Nos Nos 76.00 - 76.00
Filling (Sand Bag) Nos 1,000.00 - 1,000.00