TAN THUAN DC SCHEDULE

ID Task List Duration Start FinishHalf 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
M J J A S OND J FMAM J J A S OND J FMAM J J A S OND J FMAM J J A S O
1 Tan Thuan DC 944 days 12/1/2019 12/8/2021
2 1. DC Design 344 days 12/1/2019 21/12/2019
3 Kick-off + Contract Nego + Sign contract 45 days 12/1/2019 25/2/2019
4 Concept design + Budget (Tender) 30 days 26/2/2019 27/3/2019
5 Approval from BOM 7 days 28/3/2019 3/4/2019
6 Schematic Design (Tender) 60 days 4/4/2019 2/6/2019
7 Approval from BOM 7 days 3/6/2019 9/6/2019
8 Detailed design (Tender) 60 days 10/6/2019 8/8/2019
9 Approval from BOM 30 days 9/8/2019 7/9/2019
10 Tender evaluation and award 75 days 8/9/2019 21/11/2019
11 Tender Issue (waiting for reponse from 15 days 8/9/2019 22/9/2019
contractors)
12 Technical Evaluation 60 days 23/9/2019 21/11/2019
13 Commercial Evaluation 30 days 23/10/2019 21/11/2019
14 Approval from BOM (including signing the 30 days 22/11/2019 21/12/2019
contract)
15 2. DC Core Construction 600 days 22/12/2019 12/8/2021
16 Equipment order + Construction + 240 days 22/12/2019 17/8/2020
Commissioning + Certification (Uptime & TVRA)
17 Hand-over + CPC (Certificate of Practical 0 days 17/8/2020 17/8/2020 17/8
Completion)
18 Defect Liability 360 days 18/8/2020 12/8/2021