You are on page 1of 8

Strip Foundations The foundation runs under all the

loadbearing walls.

In this example this includes the external


walls……

A typical modern detached house will,


where possible, sit on strip foundations.
Providing the ground is suitable, this is
and the internal walls
the simplest and cheapest form of
foundation.

next
The drawing on the left shows a
foundation plan superimposed on the
house plan. As stated on the previous
page, the foundation supports all the
loadbearing walls. This includes the
external cavity walls (275mm wide),
and the internal walls (100mm wide).
The internal walls are loadbearing
because they help support the 1st
floor joists. All the upstairs internal
walls are non loadbearing - this is the
norm in modern houses.

In modern construction foundations


are invariably formed in concrete.
This is usually brought onto the site
ready mixed; - but first the
foundations must be excavated.

next
Once the the topsoil has been removed (and
levels reduced if necessary), the
foundation can be set-out by surveyors or
engineers. The graphic on the left shows
the foundation plan superimposed over the
site.

The line of the foundations can be


highlighted using hydrated lime -
here the trench centre line is being
marked. On some sites you will find
both sides of the trench marked.
Digger buckets are available in
various widths to suit specific
trenches.

next
Machine excavation is the norm. Keeping the
trenches straight and keeping the dig the
right depth is harder than it looks. Boning rods
and various types of Level ensure the latter
(see next page).

Foundation width depends on building load and


ground type. Here, the load is not more than
40 kN per metre run, and the ground is firm
clay. Hence the foundation width is 450mm.

Part of table only

next
Site rail Getting the right depth….

Establish site rails at known


level, say ‘X’ metres. If Boning
Boning rod rod is 1.50 metres long, then
depth of trench is ‘X’ minus
1.50metres.

Site rail

Correct depth can be


checked with a Level
and staff.

next
When trenches have been excavated they
should be checked for ‘square’ etc - mistakes
can be expensive once the concrete has been
poured.

The trenches should be cleaned out and


‘bottomed-up’ (cleaned out and loose material
removed), ready for Building Control
inspection.

Provision may have to be made for services


which need to cross the trench - this depends
on whether it is a traditional strip foundation
or trench fill. In traditional strip foundations
the services usually cross the trench above
duct
the concrete - in trench fill they cross
through it.

next
Traditional strip

Trench fill

next
This is a simple cross section at A - A. The
section shows the two external walls and one
internal wall. Note that the internal wall is a
single leaf of blockwork (100mm wide). In
theory the width of the foundation width can
A A sometimes be less for these internal walls. In
practice, it’s sometimes easier and cheaper to
provide a bit of extra concrete rather than
waste time changing the digger bucket.

End

You might also like