ISDP Mobile V2R8 Training Materials


(for Subcontractors 30/09/2018)

Edit it and update on 12/09/2018 by Mohammad Jallad m0410487


Contents All in One Delivery

1 Get V2R

2 V2R Menus

3 V2R Operation Instructions

Page 1
How to get the V2R version? All in One Delivery

Two options:

Download V2R8 from w3m.huawei.com

Scan the QR code to download V2R8.

Page 2
Option 1: Upgrade from V2R to V2R8 All in One Delivery
Check the download status in You may also open the app
Download V2R directly by updating After installation, tap on Open to
Notifications. Open the installation by tapping on ISDP Mobile
V1R. open the app.
interface after successful download. on your home screen

Page 3
Option 2: Download V2R8 from W3 All in One Delivery
Check the download status in You may also open the app
Open http://w3m.huawei.com and click After installation, tap on Open to
Notifications. Open the installation by tapping on ISDP Mobile
Download of ISDP Mobile. open the app.
interface after successful download. on your home screen.

Page 4
Option 3: Scan the QR code to download V2R8 All in One Delivery
Open the Version Update interface After login, start downloading
Scan the QR code and open the Tap on Download and enter the
and click the upper-right icon to enlarge and check the progress in
download interface. W3 login interface.
the QR code. Notifications.

Page 5
Contents All in One Delivery

1 Get V2R

2 V2R Menus

3 V2R Operation Instructions

Page 6
V2R menus All in One Delivery

Home

Community

Personal settings

Page 7
V2R menus All in One Delivery
Personal
Home Community
settings

Page 8
Home Project setup:
Tap to enter Common (3): All in One Delivery
the project list  To Do
and select a
 My Issues
project.
 Sites

Tap on a card Tools (11):


and hold your  Clock In/Out
finger on it.  QC/QA
Drag and drop  Acceptance
the card to
 eSurvey
rearrange
cards.  CIAG
 Scan QR
Swipe left to
 Toolkit
delete the
 Offline
card.
 SOS
 Unmanned Air
Personnel (1):
Tap to enter the  Points Rank
Add Module
Others (1):
interface.
 Bonus

Page 9
Community — Cross-project message All in One Delivery

Community

Cross-project
to-do

Instant
message
Tap on a message card
to enter the to-do
interface.

Tap on the gear icon to customize


message types, including:
 Clock-in/out reminder
 To do tasks
 To do issues
 QC/QA message
 Acceptance message

Page 10
Community — Instant message (IM) All in One Delivery

IM supports text input, voice input, voice call, and video call. Automatic translation of 60+ languages is
enabled for text input. IM facilitates communication and location-based issue resolution.
Page 11
Personal settings

Enter the personal setup interface.

Version Update: Check and update to the


latest version , Check the current version
features.

Plugin Version: Check the version No. of


each plugin.

System settings

Feedback: Report IT issues.

Upload Logs: Restart and open debug


Personal settings — Version Update

Current Version must be V2R24 the future one


will be V2R25

In case new version is


available. Tap to download
and install the latest version.

Help you to know what the


Main features for new
version update
Personal settings — Setting

Language setup

Map selection (Baidu Map in China and


Google Map outside China)
Visible on Map : Enable the location
service to upload your coordinate and let
others check your location on the map
(enabled by default).
Clear Cache (when there is not enough
storage)
Yes mean Upload and download will be
Auto when you have WIFI
Yes mean your Network Capacity will be
show.

Check the Privacy Statement.

Change your password.

Leave the app.


Personal settings — Feedback
Users may use this function to submit issues in usage. The feedback will be handled/closed by
dedicated staff.
Contents All in One Delivery

1 Get V2R (lite version)

2 V2R Menus

3 V2R Operation Instructions

Page 16
Operation instructions All in One Delivery

To-Do

My Issues

My Approval

Sites

Page 17
My Space and Card Adding All in One Delivery

More Card can be add or


New feature to just focus on
disable by Huawei team
your space

Page 18
To-Do — Displayed by DU/task/site
Three types of to-do views: DU, site, and task. The DU
view is the default one.

DU view: Tasks are displayed by DU. Navigate to task


details via: to-do (the DU list) > DU details > task details.

1. Site view: Tasks are displayed by site. Navigate to


task details via: to-do (the site list) > site details >
task details.

2. Task view: Tasks are displayed one by one.


Navigate to task details via: to-do (the task list) >
task details.

3. Search: Go to the search bar on the site view to


search for site to-dos or on the task view to search
for task to-dos. (By site, DU or task)
Site details
To-Do in the site view Site details
SITE

SITE ID
DU-1
Plugin of site
 Basic Information
 Map Task-1
 Offline
DU ID  Clock
Task-2

Plugin of DU

 Property
 Flow
 CIAG
DU-2
 iSupply
 Inventory
 Purchase
 Logistic Task-1
 Issue

Task-2
TASK list
Complete
...
Incomplete
Overdue
Site details — Plugins in the site view
DU details
To-Do in the DU view DU details

DU ID DU

Task-1
Plugin of DU
 Property
 Flow Task-2
 CIAG
 iSupply
 Inventory ...
 Purchase
 Logistic
 Issue

TASK list
Complete
Incomplete
Overdue
Plug-ins under DU
Task details (1)
Task list Task details

Tools — Tools to be integrated are


 View Documents (default)
 Clock In/Out
 Progress (for FTTX / OSP)
 Checklist
 Material scan
 Professional tools
 eSurvey
 QC/QA
Task  Acceptance
execution  WDT/MDT
 iSOP

Basic task
information
Clock in/out Facial Recognition

Failed recognition — Subcon employees go to iResource to change photos for failed recognition

• If facial recognition is set,


you cannot continue to
clock in/out until the
recognition succeeds. A
message of "Failed to
pass Huawei qualification"
will be displayed.

• After the recognition fails,


a message is displayed to
prompt the user on
uploading a correct photo
in iResource.

• Photos on newspapers
and work badges will not
be recognized. Only living The recognition succeeds and
bodies can be recognized. you can continue to clock in/out.
Electronic work
certificate (Head count)
1. The subcon user taps the avatar on
the Me tab to open the electronic work
1 certificate screen.
2. The electronic work certificate
includes the following content.
 Basic info: name, phone, e-
2 mail, certificate type, ID No., and
subcontractor
 Personal skills: job role, job
role skill, work certificate No., skill
level, and validity period.
 Tap the photo in the personal
info section to view an enlarged
photo.
Note: The ID No., photo, and personal
skills will only be displayed for subcon
users registered with real names.
I-Resource photo upload

Check face usage in Clock report


Clock in — New feature
clock-in/out color code management
EHS check with clock in
Task details - Tools (QC)
QC Task List Screen
History tasks:
completed
approval tasks
History tasks: completed
QC tasks

Add type setting of


Site and DU

QC Task: display QC tasks


(CW\TE\OSP\Cutover) to Show filter
be processed by the page when
current user. The user can click
collect data.
The View tab is
displayed only for group
leaders who can only
view the tasks of group
members.

Approve: display approval


tasks (sorted by multi-level
approval and random
approval) to be processed by
the current user.
QC on Review Task List Screen

Tasks in different states


are displayed in bar
chart and pie chart.

The ISSUES tab


displays issues to be
handled and closed by
me.
QC on Review Task List Screen

Displays task execution progress


and review progress

The colored dots indicate


different task status.
Dimmed: Pending check
and Checking
Blue: Pending review and In Filter by business type,
review task status, and
Orange: No pass inspection status
Green: Complete
Red: No pass or batch
rejected in random review

Business type
Offline Downloading of QC Task

This icon and the


Touch this icon to completion time are
download the offline task. displayed when the
downloading is
completed.
QC Offline upload review
QC Offline upload review
QC Per Task

Home tab, To DO , press on Task , touch QC. On the screen that appears, touch a KCP. The check item screen for data collection appears.
Smart QC Feature

Add the status label of an item New UI layout display on the item
Highlight the access to viewing the
on the item page. item list. list. Specify the status of each item.
QC Feature – Photo

You can edit or delete


the photos uploaded to
the server before
approval.

Click here then Photo


mode will show as below Prompt when Insta360 uninstalled
in mobile.
click OK to Download it
automatically

The photo is removed from both A new photo is generated


the ISDP Mobile and the web based on your editing and is
system after you delete it. ready for submission.
QC Feature – Photo Remark and NA feature

Photo Remark NA on KCP


QC Feature – Item Copy

Touch … or slide
left to copy a KCP.

On the Copy KCP Touch … or slide left


dialog box that to delete a KCP copy.
appears, rename the
KCP and touch OK.
QC Feature – Item Copy

On the item list screen of


a KCP, touch … or slide
left to copy an item. Touch … or slide left to
delete an item copy.
QC Feature – Photo-taking and Barcode Scanning

Touch to use the


front-facing camera
Touch to take a photo.

Choose scanning mode


when click barcode scan at
first time

Supports multiple scanning


operations. The system separates
codes with a semicolon and removes
duplicate codes.
Quality Online Check AI
 The machine intelligence reviews the QC pictures of site operation quality to replace the massive repetitive
manual review work.
Task publish
Prepare for the operation. QC plan QC task Quality Job execution
DQA Configuration execution result Subcontractor

Task publish
Job data upload
(Photos, etc.)
Online check result
feedback
AI Pass/AI Reject

Intelligent technology
①:
Industrial detection Intelligent
model compression AR technology ②:
Sample generation
Quality
and migration
learning and Online check
location
Job execution relationship
Mobile Offline Review.
Subcontractor understanding
Quality Online Check AI

1 3 4
2
5 6

1. When taking photos,the


Subcontracto Offine Review Function will
rs need install
ISDP Mobile
be available and
APP on their subcontractor can see the
Android real Review results;
phone and 2. If all check items pass,the
config.
project first! result will be green and will
take photo automatically
7
QC Feature – Drone

Screen for Data collection by drone


Site Verify Associated with SQC
QC Feature – Owner Change

4. After a new owner is


2. When a task is created on the mobile 3. Click the owner adjustment designated, the owner will be
1-The task progress is shown on device and the account user is the task section, and open the Adjust written back to the owner
the QC Task interface when ... of a owner, the adjustment icon will appear. Owner interface to select a new adjustment interface. Click
task is clicked, instead of the The user is allowed to click the icon and owner. Searching is supported. Submit to designate a new owner.
scrolling progress. enter the owner adjustment interface.
QC Feature - Submission
1- The system checks whether all required items are

message appears the user cannot continue with the

task.
host, a message is displayed when you exit the
If there is data that is not submitted on the local
operation without completing all required items.
complete after you submit the data. If not, such

2- The system checks whether all required items are complete


after you submit the data. If not, such message appears and the
user can choose to continue or cancel the operation.
QC Feature - Conference Joining and Temporary Conference Creation

Join a booked conference directly.

Create a temporary video conference


on a mobile phone.

Create a temporary voice conference


on a mobile phone.
Issue Management Process – Rectification by Issue Handler

The issue is closed automatically


and no longer displayed on the
ISSUES tab.
The message is also
displayed in Bulletin and will
not be cleared automatically.

If there is an issue pending


handling, you will receive a
message.

Issues Can Be Transferred to


Others from the Mobile

An issue handler can view


issues pending handling on
the ISSUES tab.
Smart QC Feature

For each
time the task
collector taps
on the The AI label is
Remind added to the
Approve item interface
button, the supporting
approver will smart review
receive one on Mobile
reminder in
real time

The Remind Approve button is


added on mobile to manually trigger
reminders
Smart QC Feature

1. Added fields for the quantity to


be collected and for the SN input If 360 3D photo-taking is selected when a standard KCP is associated, all
field on the item interface. videos collected for the item will be judged as 360 videos in the app.

2- The quantity of
materials to be
collected will be
shown on the
item interface.
Users only need
to tick the option.
Task details (3) — Tools (View Documents)
Drone Survey Take a top-view photo
at a specific height.

Top Take a photo at a


Measure the
Height View specific height and
height of
Survey Orientatio azimuth.
towers. n Survey

Take photos around a tower


Circle 3D
Take photos Survey
to construct a 3D model of the
Survey
around a tower. tower.
Aerial
Photo
Video 360
Take video records Circle Take a 360° panorama
Survey
around a tower. Survey around the drone.

Detect obstacles between two


Manua Microwave
RF Survey
relays.
l Survey
Take a photo Downtilt
freely under the
control of the
remote control. Take antenna photos
in different angles to
obtain antenna
downtilt data.
Intelligent Combined Survey (1)
Intelligent combined survey combines height survey, 360 survey, circle survey and tower height
confirmation intelligently for better interaction. This survey mode decouples survey process and survey item
template and automatically fills survey data. In this way, survey data can be selected, greatly simplifying
drone operations and improving survey efficiency.

1

Tap Intelligent
combined survey.
Intelligent Combined Survey (2)
Before intelligent combined survey, global parameter setting is required. After the center point is
determined, the drone takes off and climbs at an even speed. After reaching the specified height, you can tap
the camera icon to confirm height. After height confirmation, move to the next operation such as 360 survey,
circle survey, and tower height confirmation as instructed until the survey task is accomplished.

2 Tap Setting for global parameter setting.

Note:
By default, a total of 12 photos can be taken for 360 survey or
circle survey. In climbing, the drone flies at a rate of 0.5 m/s by
default.
Drone Survey – Height Survey (1)
The height of the drone can be measured automatically. To measure the height of a tower or building,
align the crosshair on the screen with the target tower or building.

1 On the Height Survey page, tap to open the Height Survey window.
Tapping
Height Icon Description
Survey will
Indicates the battery level of the drone. If
show all
survey the value is less than 30%, an alert will
functions. be displayed.
Tapping a
survey
Tap this icon to switch the channel.
function to
switch to the
Tap this icon to stop the current survey
correspondi task.
ng survey
task. Indicates the connection status between
the drone and GPS. The green color
indicates a normal connection; otherwise,
the connection is abnormal.
Tap the
upward or Indicates the connection status between
downward
arrow to your mobile phone and remote control.
tune the The green color indicates a normal
height of the connection; otherwise, the connection is
drone. abnormal.
Satellites indicates the number of satellites bound
to the drone.
Controller Power indicates the current battery level.
SD Remaining indicates the remaining capacity of the
SD card.
Drone Survey – Top View (1)
By presetting the tilt of the pan (camera) on the drone, you can take a survey photo at a specific azimuth.
By default, the pan (camera) angle is –90°, that is, in the top view.

1 On the Topview window, tap to open the Top View page.
Drone Survey – Orientation Survey (1)
You can implement special orientation survey by presetting the yaw angle of the drone and the pitch
angle of the drone pan. Valid value range of the pitch angle is [–90°,30°].

1 Tap behind the item requiring orientation survey to open the Orientation Survey window.
Drone Survey – 360 Survey (1)
By presetting an interval angle, you can take a 360° panorama by one tap. The interval angle determines
the number of photos that will be taken in a survey. Specifically, if you want to take 1–6 survey photos, set
the interval angle to 60°; if you want to take 7–8 survey photos, set the interval angle to 45°; if you want to
take 8 or more survey photos, set the interval angle to at least 30°. The more survey photos you want, the
smaller the interval angle, the better the survey performance.
1 Tap behind the item requiring 360 survey to open the 360 Survey window.
Drone Survey – Panorama Survey (1)
The height and pitch angle are preset to achieve panorama survey. The pitch angle is fixed to 30°. A
total of 12 pictures are taken.

1 On the Panorama Survey page, tap .


Drone Survey – Manual Survey (1)
You can take a photo under the control of the remote control. The remote control can freely make
the drone take off, lift, decline, and move (forward, backward, upward, and downward), and make the
pan on the drone rotate. You can view photos on the mobile app client. This mode enables free
operations but also requires high skills.
1 On the Manual Survey window, tap to open the Manual Survey window.
Drone Survey – Circle Survey (1)
By presetting an interval angle and radius, you can take photos around a tower.
1 Tap behind the item requiring circle survey to open the Circle Survey window.

Indicates the
progress. Taking
4/12 as an example,
it means that a total
of 12 photos need
to be taken, four of
which has been
taken.
Drone Survey – Video Circle Survey (1)
You can implement video circle survey by presetting the height to decline and circle radius. Based
on the obtained video records, the tower condition on the site can be viewed. When the drone
declines to the specified height, the number of recording times is automatically calculated based on
the drone's flight height and the preset height to decline.
1 On the Video Circle Survey window, tap . The Video Circle Survey window is displayed.
Drone Survey – 3D Survey – Manual Survey (1)
By presetting a downtilt and a radius, you can fly the drone around a tower to take sets of photos for
constructing a 3D model of the tower. By default, the angle interval is 15° and downtilt is 30°.

1 On the 3D Survey page, tap to open the 3D survey window.


Drone Survey – Microwave Survey (1)
Set the start height, start elevation, end height, end elevation, and latitude/longitude for survey. The
drone will fly along the line connecting the vertices of two towers and takes photos when reaching the
destination. The drone will stop if encountering any obstacle on the line.

1 Tap survey behind the item requiring microwave survey to open the Microwave Survey window.
Drone Survey –RF Survey_Intellect Count (1)
Antenna photos in different angles (left front, right front, right, left, and front) are taken and automatically
sent back to the ISDP eSurvey TSS web client for further photo processing and automatic antenna downtilt
calculation. RF downtilt measurement can be performed in two modes: Manual and Auto.
The following uses the Manual mode as an example to describe the measurement procedure:
1
Tap behind the item requiring RF Survey_Intellect Count to open the RF Survey_Intellect Count
window.

Tap Auto
to switch to
the Manual
mode.
Drone Survey – RF Survey_Lineation Count (1)
Based on photos taken on the left or right of antennas, you can obtain the downtilt of antennas by
drawing a line along the tower.
On the RF Survey_Lineation Count page, tap to open the RF Survey_Lineation Count
1
window.
Uploading/Downloading Survey Data (1)
After finishing all survey data collection tasks, you can download survey photos and upload them to
ISDP eSurvey TSS for further processing.

Tap this icon


to
download all
survey photos.

Note:
Tap this icon to upload
survey Water marks of azimuth and height where the downloaded
data to ISDP eSurvey TSS
photos are taken will be added by default.
for further processing.
You can exit download whenever you want.
If survey data to be uploaded involves only photos, the item
type must be image.
Task details (4) — Task execution (Complete)

 Feedback about survey


and QC tasks cannot
be given until they are
approved. The system
will return the approval
feedback to ISDP.
Task details (5) — Task execution (Camera)

Photos are integrated in


real time to ISDP.
Task details (7) — Modifying the owner and plan

Modify owner

Modify plan
Operation instructions All in One Delivery

To-Do

My Issues

My Approval

Sites

Page 74
Create Issue All in One Delivery

Page 75
My Issues
Operation instructions All in One Delivery

To-Do

My Issues

My Approval

Sites

Page 77
My Approval
One View

One Action

One Platform

One Input
Operation instructions All in One Delivery

To-Do

My Issues

My Approval

Sites

Page 79
Sites

Tap on the site line to open the site


detail page.
Site — Navigation and street view
Offline Mode : Team leader before visit the site

1. TL received Task under To DO


Phone must have Wi-Fi or data 3G,4G. Then follow below to activated offline mode per sites. So every sites to
repeat same (by site not by visit)
Offline Mode : Team leader on site visit the site

2. On site Step
Below to be follow every visit as clock and QC daily task not Site task. It’s show when you open ISDP
again no network available. (Make sure you will never log out from ISDP otherwise no network then can’t log in )

83
Team leader on site

3. QC collection
Make sure you will press Save before going to next task
Team leader on site

4. Clock in/Out
After you done form QC or clock will show you offline submission mode
Team leader after site

5. After Network available


a) Go to ( TO – DO ) press same task and press submit for QC . Then go to clock report to check your clock already
gone on system.
b) You can go to offline card and check upload there must don’t have and blue or red colour as blue mean still need to
upload and red mean they try upload but issue still there.
Project team Check result

1. Before TL have network then Huawei Project team can’t find any record on system . But after TL have
network and all offline was upload to server then Project team can find all info with same time TL capture
on site. In this case the live monitoring not affect but will be delay

Same Clock in/out time and date which capture by TL , even photo water mark with same time and date
Project team Check result

2. QC result also match with capture time


Issue experience
Category Issue Description Solution
65% From Team reach site after 9.30a.m
Project set Notification every two hour to remind you to clock out
Clock in/Out not on time and this is affecting work target and 75%
and Make plan in advance then can be on site at 8.00a.m
from Team forget to clock out
One account use to clock in multiple site in Don’t share your account with someone Face Recognition is online now and system will allow only
same time else as this cause issue match person to clock in/out
Clock in/out 50% from the team press cancel on when EHS task create for the basic daily work and it’s measure with
EHS clock in not used
become to EHS template clock in company KPI result
EHS KCP was complete on photo but on Team do the inspection with full EHS Huawei QC/SE will Audit site Randomly and if like this case
site is not there equipment then they borrow to other site found then company will be under punishment.
Clock in/out under Task tab not under site Project team to disable the feature for ISDP clock under Site or
Wrong clock in/out rules
or DU-ID or home page clock DU-ID and leave it under Task
EHS Clock in template is online team must complete before any
Team Start work then by the end they start Team clock at 8.30 but EHS inspection
work start , FSC team phone call is online now and SLA is
using EHS QC done at 11.00a.m
15min
SLA for work is two days then team
in QC-TE they complete EHS item in first complete EHS in first day but second day Item copy function is online team need to use same QC task
day but not doing in next day they don't do it again or they upload new just copy new Template and add on the name the date
EHS High Risk photo under same item
and EHS Team start work at 8.00 a.m. and the SLA
Normal for the site is three hours they upload EHS FSC phone call is online and Task SLA for reviewing is 15min
EHS reject but work already done
at 11 a.m. then EHS reject but in actual for EHS team need to call them before any work done
face site complete
Notification feature is online and TL can get it on his phone.
Photo reject due to not following the rules Subcontractor payment to be Automatic connect with QC. If
EHS reject but never fix again
and TL never fix it again Item not done or Reject then system will block the payment
automatically
Issue experience

Category Issue Description Solution


Team take photo on time but FSC team not Team need to make sure press submit bottom not just save it in
Item done but not review on system
approve it every KCP , also Task status is viewing on the QC/QA GU
Checking the template just two item photo Different scope have different template if you start find a lot of
A lot of NA
taken and the rest put as NA item not related call FSC team to verify
QC template connect with task , QC template will be directly
Site Related to Wireless scope but team
Wrong Template use it showing as per Scope . If you find any issue stop QC and call
use FTTS template
FSC team directly
QC
QC template has two section one for EHS If the Work was just related to EHS not to quality then you need
EHS done but Quality not , Quality done but
other for Quality , Team complete just one to make sure you will do QC-EHS not QC-TE and just complete
EHS not
part as per his scope for the day EHS part
Every Task for subcontractor required QC tools so if you going
Subcontractor complete the actual end date
to site it's mean QC must be done if the work related just for
Task done but QC not done at all on Roll out plan but QC not done as they
material collection or material return from site then must do QC-
think it's not required
EHS at least .. No QC task no Payment
Daily Monitoring for progress for Quality and EHS

 Expert team for each project and Rep. office monitoring the status and KPI
Daily Monitoring for progress for EHS high Risk
Open Discussion
All in One Delivery
One View

One Action

One Plan One Platform

Thank You!
One Input
One Result
Building A Better Connected World.