MORNITORING PLAN
THE NEXUS PROJECT
3A-3B TON DUC THANG STREET, BEN NGHE WARD, DIST. 1, HCMC

6G1, Ngô Thời Nhiệm, Phường 7, Quận 3, TP. Hồ Chí Minh | [T] (028) 3930 3346 | www.acons.vn
Contents
1.0 Introduction...................................................................................................................... 2
2.0 Basic of method statement...........................................................................................2
3.0 Monitoring purpose.......................................................................................................3
4.0 Technical report............................................................................................................. 3
5.0 Monitoring quantity........................................................................................................4
6.0 Alert Level....................................................................................................................... 6
7.0 Appendices...................................................................................................................... 6

6G1, Ngô Thời Nhiệm, Phường 7, Quận 3, TP. Hồ Chí Minh | [T] (028) 3930 3346 | www.acons.vn
1.0 Introduction
THE NEXUS project is located at 3A-3B Ton Duc Thang Street, Ben Nghe Ward, District 1,
HCM City comprised of three towers:
- Tower 1 (East): 26-storyed Tower for International Grade A Offices
- Tower 2 (West): 35-storyed Tower for International Grade A Offices
- Tower 3 : 40-storyed Tower for International Grade A Offices

On the west side (adjacent to Tower 2), there is an being-constructed metro line along the
basement wall which has a nearest distance, 4.2m, to the outerside of metro line. Retaining wall
for basement excavation work is currently designed to satisfy requiremements of the bored tunel
on both movement and strength in construction and permanent stages. In order to control the
construction work on site in line with design requirements, an extensive monitoring system is
introduced for this project. Geotechnical monitoring works are proposed as follows:
- Lateral displacement of diaphram wall monitoring
- Settlement of ground surface monitoring.
- Settlement of adjacent buildings settlement monitoring
- Settlement of main-building monitoring
- Tilt of main-building monitoring
- Settlement of tunnel monitoring
- Movement of tunnel monitoring
- Movement of soil between tunnel and diaphram wall monitoring
- Piezometer monitoring

The monitoring works will be carried out during construction including:


- Piling / Diaphragm Wall Phase
- Excavation and Basement Construction Phase
- Above Ground Construction Phase
- Post Completion (2 years)

2.0 Basic of method statement

This method statement is prepared on the basic as follows:


 Requirements proposed by the Owner and The Consultant
 Design drawings of the project
 TCVN 9360:2002 "Technical requirements of determining settlement of civil
and industry with high measurement geometry".
 TCVN 9398:2012 “ Survey in construction - Technical requirements”.
 TCVN 8869:2011“Processes measured pore water pressure in the soil”
 TCVN 9381:2012 “Instructions assess the level danger of construction”
 Directive No.07/2007/CT-BXD about increating construction management
mission for Buildings
 Circular No. 39 /2009/TT-BXD Guiding a number of provisions on quality
management of Individual houses";
 Standards for establishing national grid class I, II, III and IV.
 Standard Design for monitoring work at building.
 Hand book on Development & Building works in Railway Protection Zone
(Singapore)
 Code of Practice for Railway Protection (Singapore)

6G1, Ngo Thoi Nhiem Street, Ward 7, District 3, Ho Chi Minh | [T] (028) 3930 3346 | www.acons.vn
Page 2
3.0 Monitoring purpose

No Monitoring item Purpose

1 Lateral displacement of diaphram wall Measuring the horizontal movement of D-wall during
monitoring basement construction.
2 Settlement of ground surface Monitoring settlement of ground surface during
monitoring construction
3 Settlement of adjacent buildings Evaluating, confirming the theory of the design
settlement monitoring solution. At the same time it is also the basis for
making the necessary measures to prevent incidents
that may occur.

4 Settlement of main-building monitoring Evaluating, confirming the theory of the design


solution. At the same time it is also the basis for
making the necessary measures to prevent incidents
that may occur.
5 Tilt of main-building monitoring Evaluating, confirming the theory of the design
solution. At the same time it is also the basis for
making the necessary measures to prevent incidents
that may occur.

6 Settlement of tunnel monitoring Monitoring of possible disturbance to the Metro tunnel


from Nexus construction works to minimize the impact
on tunnel operations
7 Movement of tunnel monitoring Monitoring of possible disturbance to the Metro tunnel
from Nexus construction works to minimize the impact
on tunnel operations
8 Movement of soil between tunnel and Monitoring of possible disturbance to the Metro tunnel
diaphram wall monitoring from Nexus construction works to minimize the impact
on tunnel operations
9 Piezometer monitoring Evaluating, confirming the theory of the design
solution. At the same time it is also the basis for
making the necessary measures to prevent incidents
that may occur.

4.0 Technical report


Monitoring results will be sent via email to all parties in the same day at 9pm. Technical report of
each 2 monitoring cycles will be submitted. Content of the short report includes:
- Monitoring results
- Layout of benchmarks and monitoring marks
- Conclusions and recommendations

Monitoring report will be sent by email to all parties after 1 date. Content report consists:
- Basic for the report
- Monitoring purpose
- Content, scope of works and monitoring method
- Monitoring result
- Conclusions and recommendations

6G1, Ngo Thoi Nhiem Street, Ward 7, District 3, Ho Chi Minh | [T] (028) 3930 3346 | www.acons.vn
Page 3
- Layout of benchmarks and monitoring marks
- Statistic tables, charts, adjustment results

5.0 Monitoring quantity

No. Work Description Unit Quantity Remark

I INSTALLATION

Will use 03 benchmarks


1 Supplying and Installing benchmark Mark 3 that installed in TON DUC
THANG museum.

2 Supplying and Installing neighbour building Mark 06


settlement mark
3 Supplying and Installing ground settlement Mark 28 + Using nail
mark
4 Supplying and Installing mainbuilding Mark
settlement mark
Tower 1 Mark 12
Tower 2 Mark 11
5 Supplying and Installing mainbuilding Mark
inclination mark
Tower 1 Mark 16 + Using tape prism.
+ Using tape prism to
Tower 2 Mark 40 installation at 3, 6, 9, 12,
15, 18, 21, 24, 27, 30
floor
Tower 2 Mark 4 Using optical prism to
installation at roof floor
+ 12 points in where INC 1,
2, 3, 4, 6, 7,9 will
installed at S1 DW; INC 10,
6 11, 12 will installed at S2
Installing Inclinometer for D-wall
DW; INC5 will installed at
S3 DW; INC8 will installed
at S1a.

'Using casing of Sanlien


- Taiwan, quanlify standard
Supplying Inclinometer Casing m 414 of manufacture being
design to quanlity for
SLOPE INDICATOR.

Supplying Coupling Nos 136


Supplying Cap Nos 24
Installing and Grouting m 414

6G1, Ngo Thoi Nhiem Street, Ward 7, District 3, Ho Chi Minh | [T] (028) 3930 3346 | www.acons.vn
Page 4
Making protective box Nos 12
Installing Piezometer
Drilling D110mm hole in soil m 300 10 points,30m depth
Supplying Piezometer sensors and Nos 10
cables
Installing and Grouting m 300
Making protective box Nos 10
7 Tilt/Vibration Sensors to monitor tunnel
movement

Tilt/Vibration Sensors Nos 9 3 per section

Repeater Mark 4 Between sensors and


station (Ba Son)

Comms module Mark 1 Comms to internet

8 Settle marker to monitor tunnel movement Mark 5

II MONITORING

1 Neighbour building settlement Cycle 180 + Monitoring in 450 days, 3


cycles/week.
2 Ground settlement Cycle 180 + Monitoring in 450 days, 3
cycles/week.
3 Inclinometer Cycle 120 + Monitoring in 450 days, 2
cycles/week.
4 Piezometer Cycle 120 + Monitoring in 450 days, 2
cycles/week.
5 Mainbuildig settlement
TOWER 1
At B1,3, 6, 9, 12, 15, 18,
Suppers Structure Phase Cycle 10 21, 24, 26 floor
Finishing building and used stage Cycle 04 3 month/ 1 cycle
TOWER 2
At B1,3, 6, 9, 12, 15, 18,
Suppers Structure Phase Cycle 12 21, 24, 27, 30 floor and
roof floor
Finishing building and used stage Cycle 04 3 month/ 1 cycle
6 Mainbuilding inclination
TOWER 1
At 3, 6, 9, 12, 15, 18, 21,
Suppers Structure Phase Cycle 09 24, 26 floor
Finishing building and used stage Cycle 04 3 month/ 1 cycle

6G1, Ngo Thoi Nhiem Street, Ward 7, District 3, Ho Chi Minh | [T] (028) 3930 3346 | www.acons.vn
Page 5
TOWER 2
At 3, 6, 9, 12, 15, 18, 21,
Suppers Structure Phase Cycle 11 24, 27, 30 floor and roof
floor
Finishing building and used stage Cycle 04 3 month/ 1 cycle

Note:The monitoring frequency and quantity can be adjusted up to the collected data or
schedule construction of project

6.0 Alert Level

Level
Monitorsing Item Warning Level Alert Level Suspension Level

Displacement of D.Wall Zone A 10mm 13mm 15mm


Zone B 45mm 60mm 90mm
Settlement of adjacent building 28mm 32mm 40mm

Ground settlement Zone A 10mm 13mm 15mm


Zone B 32mm 42mm 68mm
Groundwater drawdown outsite the site 1.00m 1.50m

Note: See detail on ground instrumentation monitoring plan

7.0 Appendices
A1: Ground Instrumentation monitoring plan
A2: Sensor location