WEEKLY STATUS REPORT

Company Name Arcadis WEEK OF


Project Name Hilton Saigon Hotel 2/26/2018 through

TASKS COMPLETED
1. Stage Deliverables Presentation for ID F&B, ID Public Area, Interior Lighting, Landscape
2. Coordination of interior ceiling heights between ID and MEP
3. Superstructure Coordination and L1M setting out Plan Review
4. Landscape/ Architecture/ Structural Coordination
5. Wall Types Presentation
6. Review of all material boards for Interior Design

TASKS IN PROGRESS
1 Review of Acoustic Requirements for the whole project
2 Meeting minutes and action list for SDM05
3 Review of the resubmission of security workflow and drawings
4 Value Engineering for Interior Design
5 Close out of Kitchen Budget with 3 costs from CKP (ARC to discuss with CKP)
6

TASKS TO BEGIN NEXT WEEK


1 Review of Security Proposals
2 Coordination Meeting between Acoustics, MEP and Architecture
3
4
5
6

TASKS SLIPPING URGENT ISSUES


1. Close out of Gensler's DD Set and Sign off from
1 the client

2. Client confirmation on BOH ID works