Total Costo Directo 241,482.01 26,634.94 54,260.01 - 80,894.95 26,966.67 53,879.06 - 80,845.73 26,414.28 53,327.05 - 79,741.33
Total Costo Indirecto 33.83% 81,691.99 26,958.36 26,958.36 27,775.28
COSTO TOTAL DE OBRA 323,174.00 107,853.30 107,804.09 107,516.60
% AVANCE MENSUAL 33.50% 33.48% 33.02%
% AVANCE ACUMULADO 33.50% 66.98% 100.00%