ORIENTE

1.05 RESANES Rendimiento (UND/día) 25.00 UND:m2 Precio S/. S/. 51.58 S/. 69.63
───────────────────────────────────────────────────────── ──────────────────────────── ───────────────
Item Descripción Cuadrilla Und P.Unit Cantidad Total
───────────────────────────────────────────────────────── ──────────────────────────── ───────────────
1 Capataz 0.10 h S/. 26.38 0.03 S/. 0.84
2 Operario 1.00 h S/. 19.59 0.32 S/. 6.27
3 Peon 1.00 h S/. 14.78 0.32 S/. 4.73
4 Herramientas Manuales %MO S/. 11.84 3% S/. 0.36
5 Andamios metálicos 0.75 día S/. 20.00 0.20 S/. 4.00
S/. 16.20 S/. 21.87
6 Arena fina m3 S/. 44.90 0.08 S/. 3.66
7 Cemento Portland Tipo I bol S/. 33.57 0.73 S/. 24.44
8 Agua m3 S/. 9.00 0.02 S/. 0.20
S/. 28.30 S/. 38.21
16 Flete %MA S/. 28.30 25% S/. 7.08
S/. 7.08 S/. 9.55

NORTE
1.06 CERRAR ESCALERAS Rendimiento (UND/día) 20.00 UND:m2 Precio S/. S/. 52.41 S/. 70.75
───────────────────────────────────────────────────────── ──────────────────────────── ───────────────
Item Descripción Cuadrilla Und P.Unit Cantidad Total
───────────────────────────────────────────────────────── ──────────────────────────── ───────────────
1 Capataz 0.10 h S/. 26.38 0.04 S/. 1.06
2 Operario 1.00 h S/. 19.59 0.32 S/. 6.27
3 Peon 1.00 h S/. 14.78 0.32 S/. 4.73
4 Herramientas Manuales %MO S/. 12.05 3% S/. 0.36
5 Andamios metálicos 0.75 día S/. 20.00 0.20 S/. 4.00
S/. 16.42 S/. 22.16
6 Arena fina m3 S/. 44.90 0.08 S/. 3.66
7 Cemento Portland Tipo I bol S/. 33.57 0.73 S/. 24.44
8 Agua m3 S/. 9.00 0.02 S/. 0.20
9 Madera cedro p2 S/. 10.50 0.0075 S/. 0.08
8 sikaflex Gln S/. 27.30 0.0150 S/. 0.41
S/. 28.79 S/. 38.87
16 Flete %MA S/. 28.79 25% S/. 7.20
S/. 7.20 S/. 9.72

OCCIDENTE
1.02.01 NUEVAS ESCALERAS Rendimiento (UND/día) 20.00 UND:m2 Precio S/. S/. 52.41 70.75
───────────────────────────────────────────────────────── ──────────────────────────── ───────────────
Item Descripción Cuadrilla Und P.Unit Cantidad Total
───────────────────────────────────────────────────────── ──────────────────────────── ───────────────
1 Capataz 0.10 h S/. 26.38 0.04 S/. 1.06
2 Operario 1.00 h S/. 19.59 0.32 S/. 6.27
3 Peon 1.00 h S/. 14.78 0.32 S/. 4.73
4 Herramientas Manuales %MO S/. 12.05 3% S/. 0.36
5 Andamios metálicos 0.75 día S/. 20.00 0.20 S/. 4.00
S/. 16.42 S/. 22.16

6 Arena fina m3 S/. 44.90 0.08


S/. 3.66
7 Cemento Portland Tipo I bol S/. 33.57 0.73
S/. 24.44
8 Agua m3 S/. 9.00 0.02
S/. 0.20
9 Madera cedro p2 S/. 10.50 0.0075S/. 0.08
sikaflex Gln S/. 27.30 0.0150S/. 0.41
S/. 28.79 S/. 38.87
16 Flete %MA S/. 28.79 25% S/. 7.20
S/. 7.20 S/. 9.72

PRECIO UNITARIO POR LAS TRES TRIBUNAS


2.00.01 PASARELA Rendimiento (UND/día) 20.00 UND:m2 Precio S/. S/. 51.24 69.17
───────────────────────────────────────────────────────── ──────────────────────────── ───────────────
Item Descripción Cuadrilla Und P.Unit Cantidad Total
───────────────────────────────────────────────────────── ──────────────────────────── ───────────────
1 Capataz 0.10 h S/. 26.38 0.04 S/. 1.06
2 Operario 1.00 h S/. 19.59 0.40 S/. 7.84
4 Peon 1.00 h S/. 14.78 0.40 S/. 5.91
5 Herramientas Manuales %MO S/. 14.80 3% S/. 0.44
S/. 15.25 S/. 20.58
6 Arena fina m3 S/. 44.90 0.08 S/. 3.66
7 Cemento Portland Tipo I bol S/. 33.57 0.73 S/. 24.44
8 Agua m3 S/. 9.00 0.02 S/. 0.20
9 Madera cedro p2 S/. 10.50 0.0075 S/. 0.08
sikaflex Gln S/. 27.30 0.0150 S/. 0.41
S/. 28.79 S/. 38.87
10 Flete %MA S/. 28.79 25% S/. 7.20
S/. 7.20 S/. 9.72