Detailed

dk;Z dk uke %& पपाटन बपाब्रांच चचेन 745 सचे गपाम अड़ड़ीलपा मचेग पा हपाईवचे तक डड चेन खख द पाई कपारर्य

Item Particular No. L B H Qty. Unit


No.
1 Cutting & clearance of jungle, bushes, shrubs, Ankra /
Ipomoea, Julieflora typna etc. on canals and bunds in dry/
moist /slushy conditions including disposal as per instructions
of the Engineer-in-charge. Cost of wood has been deducted
from rates and thus will be property of contractor after cutting.

67 30.48 16 32674.56 Sqm


Total 32674.56 Sqm
2 Removal of slit/soil/earth, sand, pebbles, malba, debris,
rubbish, stone pebbles & obstruction deposited in canal bed up
to design line grade and sections having design due to
erosion/scour/slips in canal banks/silting with or without
bushes and weeds etc. in dry or moist condition from canal bed
including dewatering,loading unloading and disposal at
suitable place as directed by Engineer in Charge with initial
lead of 50 m and lift upto 1.5 m with proper dressing on canal
bed complete in all respect for depth above30 cms having
Unlined section

67 30.48 (2.70+3.9)/2 0.60 4043.48 Cum

Junior Engineer Assistant Engineer


LMC Sub Div.CAD K.Patan
Abstract of cost

dk;Z dk uke %& पपाटन बपाब्रांच चचेन 745 सचे गपाम अड़ड़ीलपा मचेग पा हपाईवचे तक डड चेन खख द पाई कपारर्य
Item Particular Qty. Rate Unit Amount
No.
1 Cutting & clearance of jungle, bushes, shrubs, Ankra / Ipomoea,
Julieflora typna etc. on canals and bunds in dry/ moist /slushy
conditions including disposal as per instructions of the Engineer-in-
charge. Cost of wood has been deducted from rates and thus will be
property of contractor after cutting. (Rate as per BSR-2011WR Zone
Kota Ch-XII Item No.1 (a) Page No.42)

32674.56 0.50 P.Sqm 16337.28


2 Removal of slit/soil/earth, sand, pebbles, malba, debris, rubbish,
stone pebbles & obstruction deposited in canal bed up to design line
grade and sections having design due to erosion/scour/slips in canal
banks/silting with or without bushes and weeds etc. in dry or moist
condition from canal bed including dewatering,loading unloading and
disposal at suitable place as directed by Engineer in Charge with
initial lead of 50 m and lift upto 1.5 m with proper dressing on canal
bed complete in all respect for depth above30 cms having Unlined
section ( Rate as per BSR-2014WR Zone Kota Ch-V Item No.7( c)
Page No. 14)

4043.48 84.00 P.Cum 339652.32


Total 355989.60
Add 2% Contingency charges 7119.79
G.Total 363109.39
Rs.Lacs in 3.63

Junior Engineer Assistant Engineer


LMC Sub Div.CAD K.Patan
Anaysis of Rates

dk;Z dk uke %& पपाटन बपाब्रांच चचेन 745 सचे गपाम अड़ड़ीलपा मचेग पा हपाईवचे तक डड चेन खख द पाई कपारर्य
Item
No. Particular Rate Unite
1 Cutting & clearance of jungle, bushes, shrubs, Ankra / Ipomoea, Julieflora typna etc. on canals
and bunds in dry/ moist /slushy conditions including disposal as per instructions of the Engineer-
in-charge. Cost of wood has been deducted from rates and thus will be property of contractor
after cutting.
Ordinary
Rate as per BSR-2011WR Zone Kota Ch-XII Item No.1 (a) Page No.42 0.50 Sqm
2 Removal of silt /soil/earth ,sand,pebbles,Malba, debries,rubbish stone pebbles & obstrution
deposited in canal bed up to design line grade and section having design due to erosion
/scour/slips in canal banks /silting with or without busches and weeds etc. in dry or moist
condition from canal bed including dewatering loading unloading and disposal at suitable place
as directed by Engineer in charge with initial lead of 50m and lift up to 1.5m with proper dressing
on canal bed complete in all respect

(a) For depth above 30 cms.


Rate as per BSR-2014 WR Zone Kota Ch-V Item No.7(c) Page No.14
84.00 Per cum
(b) Add Extra for silt clearance is done under water and mud
Rate as per BSR-2014 WR Zone Kota Ch-V Item No.7(d) Page No.14
21.00 Per cum
.
Assistant Engineer
LMC Sub Div.CAD K.Patan Junior Engineer