Activity ID Activity Name Activity BCWS BCWP ACWP
Status
qp0625 qp A.Ş
qp06 qp Constructure
thesis.last qp Aura (SON- indexler)
thesis.last.D&E Design and Engineering
A1000 Start Dormitory Building Completed $0.00 $0.00 $0.00
Construction
A1001 Investigation of Field Completed $3,760.00 $3,760.00 $3,760.00
A1002 Assemble Technical Data and Completed $500.00 $500.00 $700.00
Equipment
A1003 Review Technical Data and Completed $0.00 $0.00 $0.00
Equipment
A1004 Architectural Drawings Completed $3,600.00 $3,600.00 $3,600.00
A1005 Structural Calculations Completed $3,600.00 $3,600.00 $3,600.00
A1006 Electrical Project Drawing Completed $3,600.00 $3,600.00 $3,600.00
A1007 Mechanical Project Drawing Completed $3,600.00 $3,600.00 $3,600.00
A1008 Review and Approve Design Completed $480.00 $480.00 $480.00
thesis.last.FOUNDT Foundation
A1050 Begining of Building Construction Completed $0.00 $0.00 $0.00
A1060 Site Preparation Completed $720.00 $720.00 $680.00
A1070 Excavation Completed $1,040.00 $1,040.00 $1,400.00
A1071 Jet-Grout Completed $770.00 $770.00 $980.00
A1073 Evaluation of Axes Completed $640.00 $640.00 $544.00
A1080 Installment Underground Water Completed $360.00 $360.00 $360.00
Pipes
© Primavera Systems, Inc. Page 1 of 14
qp Aura (SON- indexler) Project Start 08-Apr-19
Report Date 24-May-19 03:47 Project Finish 09-Sep-19
WBS
Activity ID Activity Name Activity BCWS BCWP ACWP
Status
thesis.last.STRCT Structure
A1150 Begin Structure Phase Completed $0.00 $0.00 $0.00
A1160 Ground-floor Formwork Completed $3,840.00 $3,840.00 $3,644.00
A1170 Ground-floor Reinforcements Completed $7,840.00 $7,840.00 $9,440.00
A1180 Groundfloor Concrete Casting Completed $1,540.00 $1,540.00 $1,472.00
A1181 Demolding Ground-floor Formwork Completed $352.00 $352.00 $352.00
WBS
Activity ID Activity Name Activity BCWS BCWP ACWP
Status
thesis.last.MECHAN.PLUMP&ELEC.CMMNCTN
Communicaton Network
A1740 Installment of Infrastructure of Not Started $0.00 $0.00 $0.00
Telephone Network
A1750 Installment of Infrastructure of Not Started $0.00 $0.00 $0.00
Internet Network
WBS
Activity ID Activity Name Activity BCWS BCWP ACWP
Status
thesis.last.EXT.WORK.ROOF
Roof
A1440 Roof-floor Slab İsolation Not Started $0.00 $0.00 $0.00
A1450 Roof-floor Formwork Scaffolding Not Started $0.00 $0.00 $0.00
A1460 Roof Membraine installment Not Started $0.00 $0.00 $0.00
A1470 Roof Tiling Works Not Started $0.00 $0.00 $0.00
thesis.last.EXT.WORK.DOOR
Doors and Windows
WNDWS
A1489 Procuremnt of Door(Exterior-Metal) Not Started $0.00 $0.00 $0.00
and Windows
WBS
Activity ID Activity Name Activity BCWS BCWP ACWP
Status
thesis.last.EXT.WORK.FCD
Facade Works
A1500 Scaffolding Not Started $0.00 $0.00 $0.00
A1501 Isolation Installment Not Started $0.00 $0.00 $0.00
A1510 Plastering Not Started $0.00 $0.00 $0.00
A1520 Paint Not Started $0.00 $0.00 $0.00
WBS
Activity ID Activity Name Activity BCWS BCWP ACWP
Status
thesis.last.INT Paint
WORKS.PAINT
A1590 Interior Plastering Not Started $0.00 $0.00 $0.00
A1600 Interior Wall Paint Not Started $0.00 $0.00 $0.00
thesis.last.INT Carpentry
WORKS.CRPTY
A1610 Kitchen Cupboard Prepare Not Started $0.00 $0.00 $0.00
A1620 Kitchen Cupboard Installment Not Started $0.00 $0.00 $0.00
A1760 Installement of Interior Doors Not Started $0.00 $0.00 $0.00
WBS
Activity ID Activity Name Activity BCWS BCWP ACWP
Status