PROPOSED HANGER AND OFFICE DEVELOPMENT FOR JEDIDIAH AIR NIGERIA LIMITED

ID TaskTask Name Duration Start Finish Predecessors Resource Names


Mode Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019
Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 PROPOSED HANGER AND OFFICE 145 days Wed Tue
DEVELOPMENT FOR JEDIDIAH AIR 07/11/18 28/05/19
NIGERIA LIMITED
2 Mobilization of Works 16 days Wed 07/11/18
Wed 28/11/18
3 Mobilisation of Site Containers 2 days Wed 07/11/18Thu 08/11/18
4 Preperation of Site Offices and 5 days Thu Wed 3
Dormitories 08/11/18 14/11/18
5 Mobilisation of Concrete 15 days Thu Wed 4
Batching Plant 08/11/18 28/11/18
6 Mobilisation of Warehouse and 4 days Wed Mon 4
Site Equipment 14/11/18 19/11/18
7 Temporary Electric, Water and 2 days Wed Thu 3
Generator Connections 14/11/18 15/11/18
8 Civil Works/Foundation 64 days Wed 21/11/18
Mon 18/02/19
9 Site Preparation 5 days Wed 21/11/18Tue 27/11/183
10 Excavation and Earthwork 10 days Wed 28/11/18Tue 11/12/189
11 Disposal of excavated material 5 days Wed 05/12/18Tue 11/12/1810FF
12 Surface Treatment 2 days Wed 12/12/18Thu 13/12/1811
13 Reinforcement 8 days Wed 12/12/18Fri 21/12/18 11
14 10 days Mon 24/12/18Fri 04/01/19 13 End of the Year Break End of the Year Break
15 Reinforcement 7 days Mon 07/01/19Tue 15/01/1914
16 FormWork 10 days Wed 16/01/19Tue 29/01/1915
17 Concrete Work 3 days Wed 30/01/19Fri 01/02/19 16
18 Block Work 10 days Mon 04/02/19Fri 15/02/19 17
19 Imported Filling around 2 days Fri 15/02/19 Mon 18
Foundation 18/02/19
20 Steel Erection 30 days Mon 18/02/19
Fri 29/03/19
21 Steel Works 30 days Mon 18/02/19Fri 29/03/19 18
22 Drainage, Manhole and Catch Pit 32 days Wed 27/03/19
Thu 09/05/19
23 Excavation and Earthwork 5 days Wed 27/03/19Tue 02/04/1921FS-15 days
24 Disposal of excavated material 2 days Wed 03/04/19Thu 04/04/1923
25 Imported Filling around 2 days Fri 05/04/19 Mon 24
Foundation 08/04/19
26 Surface Treatment 2 days Tue 09/04/19Wed 10/04/1925
27 Reinforcement 15 days Fri 05/04/19 Thu 25/04/1924
28 FormWork 10 days Fri 19/04/19 Thu 02/05/1927FS-5 days
29 Concrete Work 5 days Fri 03/05/19 Thu 09/05/1928
30 Pavement (Hardstanding and 30 days Mon Fri 10/05/19
Floor Slab) 01/04/19
31 Excavation and Earthwork 5 days Mon 01/04/19Fri 05/04/19 21
32 Disposal of excavated material 2 days Mon 08/04/19Tue 09/04/1931
33 Filling to make up level 5 days Tue 09/04/19Mon 15/04/1932
34 Surface Treatment 2 days Tue 16/04/19Wed 17/04/1933
35 DPM 5 days Thu 18/04/19Wed 24/04/1934
36 Reinforcement 5 days Thu 25/04/19Wed 01/05/1935
37 FormWork 5 days Thu 02/05/19Wed 08/05/1936
38 Concrete Work 2 days Thu 09/05/19Fri 10/05/19 37
39 Commissioning and Handover 12 days Mon 13/05/19
Tue 28/05/19
40 Pre Commissioning 1 day Mon 13/05/19Mon 13/05/1929
41 Correction of Defects 10 days Tue 14/05/19Mon 27/05/1940
42 Commissioning and Handover 1 day Tue 28/05/19Tue 28/05/1940,41

Task Project Summary Manual Task Start-only Deadline


Project: JEDIAH POW2 Split Inactive Task Duration-only Finish-only Progress
Date: Wed 31/10/18
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone