33 kv transmission...

Classic Schedule Layout 13-May-19 15:20


Activity ID Activity Name Original Duration Start Finish Total Float Qtr 1, 2019 Qtr 2, 2019
Dec Jan Feb Mar Apr
NEWPROJ-7 33 kv transmission 314 08-May-19 20-Jul-20 0
A
A1150 project start 0 08-May-19 A
NEWPROJ-7.1 basic requirements 100 08-May-19 A 24-Sep-19 0
A1000 conductors 100 08-May-19 A 24-Sep-19 0
A1010 support poles 10 05-Jun-19 18-Jun-19 0
A1020 nuts and bolts 5 19-Jun-19 25-Jun-19 0
A1040 jumpers 8 26-Jun-19 05-Jul-19 0
A1140 lightning arrestors 40 08-Jul-19 30-Aug-19 0
NEWPROJ-7.2 cross arms 65 02-Sep-19 29-Nov-19 0
A1030 v shape cross arms 45 02-Sep-19 01-Nov-19 0
A1050 ground cross arms 20 04-Nov-19 29-Nov-19 0
NEWPROJ-7.3 battery 31 02-Dec-19 13-Jan-20 0
A1060 battery set 12 02-Dec-19 17-Dec-19 0
A1070 station battery charger 19 18-Dec-19 13-Jan-20 0
NEWPROJ-7.4 insulators 76 14-Jan-20 28-Apr-20 0
A1080 disk insulators 20 14-Jan-20 10-Feb-20 0
A1090 suspension insulators 56 11-Feb-20 28-Apr-20 0
A1100 strain insulators 18 17-Mar-20 09-Apr-20 0
NEWPROJ-7.5 other requirements 72 10-Apr-20 20-Jul-20 0
A1110 circuit breakers 28 10-Apr-20 19-May-20 0
A1120 control panels 14 20-May-20 08-Jun-20 0
A1130 fuse & switches 30 09-Jun-20 20-Jul-20 0
A1160 project end 0 20-Jul-20 0

Actual Level of Effort Remaining Work Page 1 of 4 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
33 kv transmission... Classic Schedule Layout 13-May-19 15:20
Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

project start, 08-May-19 A


24-Sep-19, NEWPROJ-7.1 basic requirements
conductors
support poles
nuts and bolts
jumpers
lightning arrestors
29-Nov-19, NEWPROJ-7.2 cross arms
v shape cross arms
ground cross arms
13-Jan-20, NEWPROJ-7.3 battery
battery set
station battery charger

disk insulators

Actual Level of Effort Remaining Work Page 2 of 4 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
33 kv transmission... Classic Schedule Layout 13-May-19 15:20
Activity ID Activity Name Original Duration Start Finish Total Float Qtr 1, 2019 Qtr 2, 2019
Dec Jan Feb Mar Apr
NEWPROJ-8 construction 0 0

NEWPROJ-9 solar project 5 13-May-19 17-May-19 0

NEWPROJ-9.1 engineering 5 13-May-19 17-May-19 0


A1000 electrical 5 13-May-19 17-May-19
A1010 mechanical 5 13-May-19 17-May-19
A1020 civil 5 13-May-19 17-May-19
A1030 design 5 13-May-19 17-May-19
A1040 it/computer 5 13-May-19 17-May-19
A1050 project management 5 13-May-19 17-May-19

NEWPROJ-9.2 procurement 5 13-May-19 17-May-19 0


A1060 pv modules 5 13-May-19 17-May-19
A1070 cables 5 13-May-19 17-May-19
A1080 inverters 5 13-May-19 17-May-19
A1090 electrical equipments 5 13-May-19 17-May-19
A1100 material required to build MMS 5 13-May-19 17-May-19

NEWPROJ-9.3 construction 5 13-May-19 17-May-19 0


A1110 construction for x'mer 5 13-May-19 17-May-19
A1120 land grading and leveling work 5 13-May-19 17-May-19
A1130 foundation for inverters 5 13-May-19 17-May-19
A1140 pile boring and concreting 5 13-May-19 17-May-19

Actual Level of Effort Remaining Work Page 3 of 4 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
33 kv transmission... Classic Schedule Layout 13-May-19 15:20
Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

17-May-19, NEWPROJ-9 solar project

17-May-19, NEWPROJ-9.1 engineering


electrical
mechanical
civil
design
it/computer
project management
17-May-19, NEWPROJ-9.2 procurement
pv modules
cables
inverters
electrical equipments
material required to build MMS
17-May-19, NEWPROJ-9.3 construction
construction for x'mer
land grading and leveling work
foundation for inverters
pile boring and concreting

Actual Level of Effort Remaining Work Page 4 of 4 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation