REMODELACION Y AMPLIACION DE SS.

HH

MATERIALES
DESCRIPCION CANTIDAD UNIDAD P.U

1- CEMENTO 170.00 Bolsas x 23.00 =


2- ARENA GRUESA 9.00 m3 x 30.00 =
3- ARENA FINA 15.00 m3 x 30.00 =
4- PIEDRA DE 1/2" 7.00 m3 x 45.00 =
5- PIEDRA BASE 6.00 m3 x 80.00 =
LADRILLO SOLIDO
6- 1.20 Millares x 400.00 =
ARTESANAL 9X13X24 cm
7- CERAMICA 18.00 m2 x 18.00 =
8- ALAMBRE DE AMARRE N°8 20.00 Kg x 4.00 =
9- CLAVOS DE 2" 10.00 Kg x 4.00 =

MANO DE OBRA
DESCRIPCION CANTIDAD UNIDAD P.U

PRECIO A TODO COSTO DE


1- 1.00 GLB x 3010.20 =
MANO DE OBRA

Tiempo de Ejecución: 45 Días Calendario


ION DE SS.HH

PARCIAL

S/ 3,910.00
S/ 270.00
S/ 450.00
S/ 315.00
S/ 480.00

S/ 480.00

S/ 324.00
S/ 80.00
S/ 40.00

S/ 6,349.00

A
PARCIAL

S/ 3,010.20

S/ 3,010.20
MEJORAMIENTO DE MERCADO EL PROGRESO - SECTOR FRATERNIDAD II

MANO DE OBRA
DESCRIPCION CANT. UND. P.U PARCIAL

INSTALACION DE SISTEMA DE DESAGUA Y AGUA

REPLANTEO DE RED DE DESAGUE DE TUBERIA DE 4" E INSTALACION DE RED DE 6" ……………………… 143.00 ml x 20.00 = S/ 2,860.00
COLOCACION DE CAJAS DE DESAGUE CON TAPA REGISTRO DE 60X35 CM…………………………………… 10.00 Und. x 50.00 = S/ 500.00
INSTALACION DE TUBERIA DE AGUA Y PRUEBA DE AGUA …………………………………………………………. 95.00 ml x 10.00 = S/ 950.00
RECTIFICACIONES DE TUBERIA DE AGUA ……………………………………………………………………………… 5.00 Pto. x 10.00 = S/ 50.00

INSTALACION DE SISTEMA ELECTRICO DE TODOS LOS PUESTOS DEL MERCADO( INDEPENDIENTES)

RECORRIDO DE TUBERIA DE 2" ………………………………………………………………………………………… 145.00 ml x 7.00 = S/ 1,015.00


RECORRIDO DE TUBERIA DE 3/4" ………………………………………………………………………………………. 541.00 ml x 1.30 = S/ 703.30

VEREDA DE CONCRETO

VACEADO DE VEREDA F´C= 175 KG/CM2 , E = 10 CM …………………………...…………………………………… 600.00 m2 x 10.00 = S/ 6,000.00

TOTAL EN MANO DE OBRA ……………………………………………………………...……………………………………………………………………………… S/ 12,078.30


MATERIALES
DESCRIPCION CANT. UND. P.U PARCIAL

INSTALACION DE SISTEMA DE DESAGUA Y AGUA

TUBOS PARA DESAGUE UF DE 6" ANARANJADO ………………………………………………………………… 8.00 Und. x 90.00 = S/ 720.00
TUBOS PARA AGUA DE 1/2" …………………………………………………………………………………...………… 10.00 Und. x 6.20 = S/ 62.00
TUBOS PARA AGUA DE 1" …………………………………………………………………………………………………... 16.00 Und. x 17.90 = S/ 286.40
UNIONES PARA AGUA DE 1/2" ……………………………………………………………………………………………... 30.00 Und. x 0.50 = S/ 15.00
PEGAMENTO PARA TUBERIA OATEY ( 250 ml) ……………………………………………………………………..… 1.00 Und. x 22.00 = S/ 22.00

INSTALACION DE SISTEMA ELECTRICO DE TODOS LOS PUESTOS DEL MERCADO( INDEPENDIENTES)

TUBO DE LUZ DE 2" …………………………………………………………………………………………………..…… 40.00 Und. x 11.00 = S/ 440.00


TUBO DE LUZ DE 3/4" …………………………………………………………………………………………………..…… 180.00 Und. x 2.50 = S/ 450.00
CURVAS DE LUZ DE 3/4" ………………………………………………………………………………………………….. 200.00 Und. x 0.40 = S/ 80.00
CURVAS DE LUZ DE 2" …………………………………………………………………………………………………..… 20.00 Und. x 5.00 = S/ 100.00
CAJA DE PASO DE 30X20 CM ……………………………………………………………………………………………… 5.00 Und. x 30.00 = S/ 150.00
CAJA DE PASO DE 20X20 CM ……………………………………………………………………………………………… 18.00 Und. x 20.00 = S/ 360.00

VEREDA DE CONCRETO

ARENA GRUESA ………………………………………………………………………………………………………….….. 30.00 m3 x 20.00 = S/ 600.00


PIEDRA DE 1/2" ……………………………………………………………………………………………………………..... 48.00 m3 x 30.00 = S/ 1,440.00
CEMENTO TIPO PORTLAND ( 42,5 KG ) ………………………………………………………………..………………… 480.00 Bolsas x 22.00 = S/ 10,560.00

TOTAL EN MATERIALES ……………………………………………………………...……………………………………………………………………………… S/ 15,285.40


TIEMPO DE EJECUCION : 30 DIAS CALENDARIO