Professional Documents
Culture Documents
•
SLNo.
Other Method Statement
Document No. Rev Date Description Category
Method Statement of
33P1-WBJV-BFCC/PCC- Secant piling, Excavation
1 01 26.06.2016 FOR APPROVAL
MS-001 and Dewatering upto
-17.00MSL
~~ 11', \\.
~WABAG • \'1\ \ --7 "
,.,!-,~I
L. . , j
8ElHASA PROJECTS llC
lLi\~ Z6jUNZ016
C'~ -, ,. )-tJ' ,;. ~ "i'g.~: . #':'~.w ~i ~i!
For MIs WABAG-BELHASA JV WLL
\
! ' ;'';J~~ __' e''1'1.-'~
'~:,\J t: ~
j
l~n~s~tive
4. (
\t...--.._ - ?
./ -
I
Reference : 33PI-WBJV-BFCC-MS-004
Method Statement of Secant piling - Annexure A
Date:23.06.2016 I 33P1-WBJV-BFCC-M5-004
I Rev. 0
LIST OF CONTENTS
1.0 INTRODUCTiON
3.0 MATERIALS
3.1 Concrete
3.2 Steel
4.0 RESOURCES
,\ ,,
SC-tDF
(fJDbr'!,',?q../Oy) o
. r"
, , •. /
-. -{
~
\,-~) r 1t...(,.J/~:
~- jt r::; F~· t· oJ
Rev. 0 33P1-WBJV-BFCC-MS-004
Method Statement of Secant piling - Annexure A
Date:23.06.2016 I 33P1-WBJV-BFCC-MS-004
1 Rev. 0
Standards I Documents
3.0 MATERIALS
3.1 Secant Pile
Reinforcement of grade Fe500 NI mm2
Spacer Material: HOPE Spacer
Binding wire: GI18 SWG
Primary plies (Soft Plies)
Concrete of grade C 20 with SRC and Water Proofing Admixture added to Concrete for
Piles penetrating into Aquifer
Secondary plies (Hard Pile)
Concrete of grade C 45 with SRC and Water Proofing Admixture added to Concrete for
Piles penetrating into the Aquifer
Guide Wall
Blinding Concrete of grade C 20 with SRC &RCC part of Guide Beam with Concrete of Grade
C 20 with SRC
4. Resources
Drilling rig }
With accessories = 1 Nos. for the drilling of secant pile wall.
Rev. 0 33P1 -WBJV-BFCC-MS-004
. "'.,_ •C ... ...... . .: ,- . ~ ;
~>.:. '
, ,
2. :/ 1 • . _· d. r ..,:.:~
-tl .:.,
- I ./~:; , I (".~
Date:23.06.2016 I 33P1-WBJV-BFCC-MS-004
I Rev. 0
wall within the tolerable limits. Guide wall will be cast in 4 quadrants and on completion
and curing period of 7 days of 1st quadrant, Secant Pile driving will be set out and
started by driving in a sequence. Parallely casting for next quadrant will 00 taken up and
driving of secant pile will continue after allowing for minimum curing time of 7 days.
Trench excavation for bottom width of 1900 mm shall be carried out along the secant
/ pile wail centre line for a depth 90 cm from working platform level. The polystyrene
board matching the profile I pattem of hard and soft pile as manufactured is proposed to
be installed by steel pins driven on blinding concrete and tied in the top with binding
, .
" ","
.. ... wire as shown in the sketch below.
, : r
, J. ~_ (<:
,:
7 { ::.
The guide wall concreting shall be carried out after placing the nominal reinforcement
'7
as shown in approved drawing. •
..... -
5.3 Survey works
A qualified Surveyor will be deployed for setting out surveying works. The Surveyor will
Rev. 0 33P1-WBJV-BFCC-MS-004
,"" .' ,;> \ . ] :-- 1-:; 1
- '/
Date:23.06.2016 I 33P1-WBJV-BFCC-MS-004
I Rev. 0
Any noticeable variation shall be brought to the attention of the Engineer. The depth of
borehole shall be measured using an end weighted measuring tape and to be recorded in the
/"
Pile record sheet. .I/
Rev. 0 33P1-WBJV-BFCC-MS-004
Method Statement of Secant piling - Annexure A
Enclosure
1) Drawings
2) Traffic Management Plan including position of machinery at Site
3) Casting Sequence for 4 quadrants of Guide Beam
4) Risk Assessment
5) Site drainage Arrangement & Temporary Stock Pile of muck
Rev. 0 33P1-WBJV-BFCC-M5-004
..
r.r.~ ~L-....u\ ,,,~I ~\ ,~, ",'I ~.) '>! 11 L.S~
BAHRAIN FOUNDATION CONSTRUCTION COMPANY W.L.L.
B FCC I
SAFEIYPLAN
BFCC's Aim: Working safely without harm or damage to employees and properties
4- MSDS (Materials Safety Data Sheet) has to be maintained for every required materials such
as:
• Diesel
• Oil
BFCC/Safety Plan/Page 1 of 9
.
r·r· j ~~\ ",':/1 ~\ ,=;, .,'1 ~.) ... ! 1\ LS~
BAHRAIN FOUNDATION CONSTRUCTION COMPANY W.L.L.
BFCC
BFCC/Safety Plan/Page 3 of 9
('.('. ~ ~L-.u\ ff,~1 ~ \ ,:;, "'i 0-:.) '>! 11 L.S~
Co
• Displacement panel.
while running. • Provide choke.
9. Placing & use of • Placing a machine • Check & place the welding machine at
welding Machine
in walkway or safe corner without creating any
emergency obstruction.
BFCC/Safety Plan/Page 5 of 9
.
r-r· j ,,,':J\ ~\ ,:;, .''i L>--:J
~L....,\ ... ! ,\ ~~
BAHRAIN FOUNDATION CONSTRUCTION COMPANY W.L.L.
BFCC
14. Working at Height • Improper access & • Proper secure ladder or built up ladder
egress to platform shall be used to access I egress platform
or machine or machine.
• Not wearing safety • The person shall be trained for working at
hamess or height and use of I checking Ihooking the
hooking at rigid
point of structure. safety harness.
BFCC/Safety Plan/Page 7 of 9
~
11- Close the work permit and make sure that there is no harm to employees or properties.
Responsibilities:
• The company has to provide all the safety tools and equipments needed.
The Engineer and the foreman are at most responsible about the entire health, safety and
environment precaution, before starting the work. The engineer should apply and activate the
safety procedure which is given by the safety team, all the safety instructions have to be
considered.
• If the labour ignores the instruction given by the safety supervisor, engineer or the
foreman, he will be held fully responsible about any harm could happen to employees or
the properties.
• The safety team has to induct, instruct and advice all the working team for any risk they
may into it, how to prevent and avoid the potential hazards at site is essential.
Training:
Training courses will enhance capabilities of employees to work in a safe environment.
• Type of training courses can be decided based on the requirement of the site.
Issued by
Safety team
BFCC/Safety Plan/Page 9 of 9
l..-tr<~"","_Nl.-1Jt~
rJJ
~: ..'r.-' ...! ,__ ~~
'---:::-;.-;;\ _
.
•Y~~
J: ~-II~~h~- i~
, 11""'"
~ 14 .-'"',"------'
* '"
. -~ .-
TYP. HARD PILE
R8NF'T PROAlE PilE oS I R8NF'T PROALE
~
.//
-+-FH ~L.' 1
I
- I 0
0 _ _-
/'
- "- _ •• _ -
I
CAPPING BEAM REINF'T DETAil :i
SOT (0
CRANE
rr~'~J};~
J_ -=Y¥#", . ~
I
I - 1 l81J./·--S~=
-"I ,..aIO.Mcu.ID~
I\,. - - _ .
1TT1l
J1lU IW1IWH FOUHOo\TJON
CONSTRUCTlOH CONI'AHr W.L.L
IIStl
" -. . COII;:Ia""":;
-5~===1O·
,- . . .-
N
--
.:w~1
.-.............
u\s"".'tI;~Jj,
KINGDOM OF BAHRAIN
-~--
MWHKHONJI
WABAG-BELHASA JV
~:.oa:..
E:447278.536
__________________-J/
Signature DATE
PCC
r. ~~ !2."Ibl l b
Received by : - Signature Date
ReciDient comments :
Note: Please acknowledge and return a copy of this form to issuing person.
Pale no 1
-r~ J')') ~~JUoJ IJ u4~ ~~ ts~
SANTY EXCAVATION' CONSTRUCTION COMPANY SPC
METHOD STATEMENT
Date: March 26, 2016
AL MADINA AL SHAMALLIYA
SEWAGE TREATMENT PLANT 40 MLD
Date:
2
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCE
4.0 RESOURCES
4.1 Materials
4.2 Equipment
4.3 Manpower
5.0 RESPONSIBILITIES
10.0 APPENDIX
-r~ ,.); u1JIJ4JIJ u4~ ~I.w a.s~
SANTY EXCAVATION &CONSTRUCTION COMPANY SPC
METHOD STATEMENT
Page no
Date:
3
This page is a record of all revisions of this document. All previous issues are hereby
superseded and are to be destroyed.
REVISION LOG
Note:
Revision after Rev.O shall be denoted by a triangle symbol, the revision number being
denoted within the symbol. Revision symbol is positioned adjacent to the paragraph being
revised.
II(» jJJ U~jLiJIJ u4~ ~l4u ~~
SANTY EXCAVATION &CONSTRUCTION COMPANY SPC METHOD STATEMENT
Page no 4
rt/,.~'#
1.0 PURPOSE / ~?«,oJ '
This method statement describes the methodology of earthworks for TLPS area
located in the project site of AI Madina Shamaliya Sewage treatment plant and long
sea outfall.
2.0 SCOPE
3.0 REFERENCE
4.0 RESOURCES
I. Materials , ..
a. Soft and Hard Safety barricade shall be done ,,/
b. Personal Protective Equipment (PPE: Basic PPE Like Hard Hat, Safety
Shoes, Goggles, Reflecting Waists Shall Be used at site)
c. Breathing apparatus, Access Ladders, Scaffoldings, Access Ramp,
Stretchers and Emergency ~ervices and other HSE r~~ated Provisions
shall be provided at site. H'?::. S C' l'> d,.ffC../r.,;-,
II.Equipments
e. 200 Ton Crane - 1 No for Removing the Excavator from final Depth of
Excavated shaft
f. Soil Grubber / Bucket for Hauling excavated material from excavated Pit
depth of 15.00 to 27.00 Mtr. below from Ground Level
g. Dump Trucks (Capacity 12 & 20 M3 )
h. Loader (Capacity 3.0 M3 )
i. Water Tank (Capacity 5000 Gallons and as necessary)
j. Roller Compactor (20 ton)
k. Necessary other equipment to complete scope
III.Manpower
The required manpower for the execution of foreseen works shall be as per approved
program and as follows;
Date:
7
F. During execution an area of Minimum 16.00 Mtr surrounding the shaft area shall
remain clear of any disruption and the area will be isolated by barriers provided at
site.
G. Excavator LC 220 with Bucket & Rock Breaker will continuously be present inside the
shaft until the final level of excavation is reached. Up to 15.00 Mtr of excavation
depth the excavated material will be removed from shaft by the long boom excavator
which is located top of the shaft. Below 15.00 Mtr depth the excavated material will
be removed by bucket and crane.
H. After reaching of 15.00 Mtr below ground level of excavation, the crane mountable
type Grubber or Sand Bucket to haul the excavated materials from shaft to ground
level and it shall be transported to client designated place:
I. Tower Crane Minimum lifting Capacity of 5 Tons including competent operator shall
be provided to lift the Grubb or bucket from the shaft. The crane movement shall
reach the whole excavation area and the sling Should reach the full depth of
excavation to remove the excavated soil.
K. After reaching, the final level of excavation and subject to the approval and
inspection of depth and shall be arrange 200-Ton capacity crane to remove the
excavator from the shaft.
All the works shall be complied with procedures described in the Approved Project
Quality Plan of PCC
Specific safety measures shall be implemented as per the Project Safety Plan.
V Page
....... -
--"'-
AL MADINA AL SHAMALLIYA
SEWAGE TREATMENT PLANT 40 MLD
AL MADINA AL SHAMALLIYA
SEWAGE TREATMENT PLANT 40 MLD
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCE
4.0 RESOURCES
4.1 MATERIALS
4. 2 MANPOWER
5.0 RESPONSIBILITIES
11.0 APPENDIX - I
a. DRAWINGS
D Ref: No: ~1lPS -16()
AL MADINA AL SHAMALLIYA
SEWAGE TREATMENT PLANT 40 MLD
REVISION LOG
Note:
Revision after Rev.O shall be denoted by a triangle symbol, the revision number being denoted
within the symbol. Revision symbol is positioned adjacent to the paragraph being revised.
~ Ref: No: ~1IPS-AeIO
AL MADINA AL SHAMALLIYA
SEWAGE TREATMENT PLANT 40 MLD
1.0 PURPOSE
This method statement describes the methodology to adopt dewatering system for TLPS
Structure located in AI Madina Shamaliya, Kingdom of Bahrain.
The purpose of the documentation emanating from this method statement is to ensure that
quality control objectives are maintained and accurate records are established for all related
activities.
2.0 SCOPE
This method statement covers the following procedures to be adapted for dewatering system
forTLPS.
3.0 REFERENCE
4.0 RESOURCES
4.1 Materials
• Safety barricade
• Personal Protective Equipment (PPE)
• Warning Tapes
• Steel rod ( for marking)
• 20 mm white aggregate
• 300 mm PVC slotted pipes
• Electrical accessories
• Discharge hose
• Sedimentation tank
D Ref: No: tlIwmt'g1lPS-Fe.O
a. JCB
b. Submersible pumps ( 24 M3 / Hour)
c. Crane - ( 25 ton)
d. Deep well drilling equipment
4.3 Manpower
4.3.1 . The required manpower for the execution of foreseen works shall be as per
approved program and as follows;
a. Construction Manager
b. Project Engineer
c. QA/QC Engineer
d. Safety Officer
e. Surveyor
f. Foreman
g. Operators
h. Skilled Worker
i. Labourers
j. Day and night supervisors from Sub contractor
5.0 RESPONSIBILITIES
• Work progress is carried out according to planned program and all the equipment
required to execute the works are available and are available at site in good condition
• CM will liaise with Client and Consultant at site for any critical activity.
• Specific attention is paid to all safety measures and quality control in coordination with
Safety Engineer and QC Engineer in line with HSE Plan and Quality Control Plan.
• CM will monitor and control the daily activities in coordination with Project Engineer,
Foreman and Safety officer.
• Coordination with Safety Engineer to ensure that the works are carried out in a safe
working atmosphere
• Work progress is monitored in accordance with the required program and report the
same to the Construction Manager
• Coordination with QC Engineer for any inspection and testing as required
6 Ref: No: IliwIEItsllP.S -FWl
<:;1tC> METHOD STATEMENT Date: 21.06.2016
• Coordination with surveyor and plan the survey works in advance as per the work
sequence
• Implementation of any request that might be raised by the Consultant
• The carrying out of the works are as per the related quality procedures
• Inspection for the related works and requesting for the Consultant's approval
• Maintenance of completed inspection records
• Will assists by QC inspector
• The implementation of all safety measures in accordance with the HSE plan of main
contractor and HSE plan of sub-contractor and that the whole work force is aware of its
proper implementation
• The implementation of safety measures is adequate to maintain a safe working
environment on the site
• Inspection of all the site activities and training personnel for accident prevention and its
proper reporting to the HSE Manager / HSE officer of main contractor WBJV
• Setting out of control points and setting out of building at all stages.
• Prepare and submit survey report for prior to inspection.
• The carrying out of the work and the proper distribution of all available resources in
coordination with the Project Engineer on a daily basis
• Daily reports of the work are kept and coordinated with the Site Engineer for future
planning
• Incorporate all QA and Safety requirements as requested by the concerned Engineer
Specific safety measures shall be implemented as per the Project Safety Plan.
a. The deep well area will be protected with hard barricade (Safety Cones, Hard
Barricades, warning tapes, safety sign boards, flickering lights, etc.) and fencing to
restrict unauthorized entry.
b. Prior to starting of dewatering at site, approval will be secured from Supreme Council of
Environment as per norms in practice
c. Hose leak will be controlled while doing de watering
d. Periodically the Sedimentation Tank will be cleaned to avoid sludge accumulation at
tank
e. The following safety precautions will be exercised;
• Ensure that all workers related to this work shall have attended Safety Induction
and shall be provided with proper PPE.
• Implement "Permit to Work" system. No work shall proceed unless inspected by
WBJV Safety Officer.
• Conduct Daily Tool Box Meeting for mutual understanding of workers and record
attendance of attendees.
• Safety warning tapes and warning sign shall be provided as a barrier of
equipment's entry.
• It shall be ensured that all equipment deployed at site will not pollute the environment
beyond the standard specified and all works shall be undertaken in accordance with the
approved Construction Environment Management Plan(CEMP}
9.0 Enclosure
6 Ref: No: ~1IPS.1W)
90° Elbow
,.J------~~'---- To The Disposal
Gravel pack
20mm
20.60m
600mm dia
borehole
Not to Scale
\.' Page
Sedimentation tank
/\ AL MADINA AL SHAMALLlYA SEWAGE TREATMENT PLANT 40 MLD PROJECT
~WABAG
'--'
<.4
J1tt"
/~ Hazard Identification, Risk Assessment & Risk Control Register
\l RISK ASSESSMENT OF EXCAVATION & DE-WATERING FOR TLPS
Sr. No
1.
~,
~.
Excavation.
.... ...".
Cave-in, collapse of
-~ ,3
3
INI1IAL
1f~ II!
3 9
Risk Control ........
RESUDIAL
INITIAL RESUDIAL
Procaee
Sr. No ~~ Risk Involved Risk Control Measure
~ f~ ,~ h
I':' f:t l:l ],
•
Injury, damage to 2 3 6 Excavations shall be barricaded with hard 1 3 3
Personnel or
equipment falling plant and barrier and warning signs. Where excavations
in to excavation. machinery. are located adjacent to pedestrian or vehicle
access ways, flickering lights must be
provided for dark hours' alert.
Ground condition shall be checked,
equipment and materials shall be placed
sufficiently away from the edge of the
excavation.
Encounter with Fatality/ III Health 3 4 12 Any excavation which has chances of wall 1 4 4
hazardous gas collapse, presence of dangerous gases shall be
(H2S). treated as confined space and confined space
permit shall be obtained prior to enter such
excavations
Gas testing shall be carried out prior to enter
the deep excavation and entry shall be
allowed if only all the dangerous gases in ,
INITIAL I RESUDIAl
P.Ioc ...
Sr.No I
AclvII;y I ~~.
I RIIk Involved
f~ ,~ 1:;
I"
Risk Control Meastn
IJ~IIlll!
ontinues gas monitoring shall be carried out
y using calibrated portable gas monitor.
All the workers should wear personal gas
monitor and carry escape mask while working
in H2S designated areas. Only workers who
attained H2S training are allowed to work in
H2S designated areas.
Trained confined space attender shall be
assigned to monitor the entry, exit and
working duration of each employee at the
entrance of excavation.
2. I De-watering Fall into water Injury/ Drowning Proper signage and barricading of the work I 1 I 4 I 4
flooded excavation. area shall be done.
Daily inspection shall be carried out to check
any sign of excavation wall collapse.
Workers should not be allowed to work in the
excavation without inspecting the excavation
by a HSE Officer.
Subsidence of
equipment
T
Injury, property
damage. 12 1
3 6
1
De-watering facilitr should be in ~lace.
I Adequate supervision shall be ensured.
Equipment shall be operated away from water
I I I3 I3
lagged area.
INITIAL I RESUOIAL
Proce8a
Sr.No I PotentIal ....... RIsk Involved Risk Control Measure
AcIIvttY f~ 1,
f~ !" J~ Ifl II~
Occupational Skin Rash 3 3 9 Activity shall be monitored by competent 1 I3 I3
disease. supervisor.
Use appropriate water resistance PPE (Gum
Boot, Rubber Hand Gloves, disposable
coveralls).
I
Flooding I Damage caused by 3 3 9 All water pipe lines must be properly jointed I 1 I3 I3
water soil erosion. and clearly marked.
There shall be constant monitoring of de-
watering pump and pipelines to rectify faults
as soon as possible.
Using of electrical Electric shock, fire, 3 3 9 All electrical cables and electrical power I 1 I 3 I 3
power. bums.
points shall be away from dewatering
facilities. Double insulated industrial cable
and industrial socket shall be used.
I I I I I
2 I General. I Usage of defective Injury. 2 2 4 Check all tools and don't use defective tools. I 1 I2 I2
and greasy tools. Keep the tools clean and free from any
lubricants like oil grease etc.
No improvised tools shall be used.
Employees shall ensure that tools are in good
condition and if a defect is observed then it
INITIAl. RESUDIAL
Pmos,.
Sr. No PotentIal HazeRte RIIk Involved Risk Control Measure
f' ,!!
! ..
AQM.y
fl f:t 12 I'
must be replaced.
<J1C [> Hazard Identification, Risk Assessment & Risk Control Register
\7
'v RISK ASSESSMENT OF EXCAVATION & DE-WATERING FOR TLPS
INITIAL RI!SUDIAL
Procaaa
Sr. No
AcUvIty
PolentIaI . . . . RIsk Involved
f! f:t h
!.\
Risk Control Measure
f:t f:t J::
I'"
Rest only at designated areas.
Always have patience while dealing with
other employees.
2 2 4 1 2 2
Slippery surface. Slip and fall. All slippery surfaces shall be cleaned
immediately using sand.
Over speeding of 4 2 8 1 2 2
Injury, damage to All vehicles and construction equipment
vehicles property. entering and exist the construction area shall
be driven as slow as possible, not exceeding
20kmph. Flagman shall be given necessary
signals to the vehicles and construction
equipment while entering and existing the
work area.
--- -
Prepared By: ~
Akhil Pushpangadan
Reviewed By:
J anarthanan
~
-
r Approved BY :
James Philip
HSE Officer Project Engineer HSEManager