Professional Documents
Culture Documents
CSC.01
he primary focus of this paper is to present a methodol- application of risk analysis to help project managers control cost
cally responsible for cost control. Most complex projects share the
common theme that they are fraught with risks and uncertainty Risk Defined
that can cause cost escalations. For example, Laufer and Howell The literature abounds with definitions of risk. Risk can be a
found that about 80 percent of all projects begin the construction somewhat ambiguous term unless its definition and convention
process with a high level of uncertainty [8]. Construction project are clearly stated. The concept of risk is used to assess and evalu-
managers and cost engineers have a challenging task to build a ate uncertainties associated with an event. Risk can be measured
complex project that is on budget. as a pair of the probability of occurrence (likelihood) of an event
Construction and cost engineering professionals have long and the consequences (outcomes) associated with the event’s
recognized the need for improvements in the area of cost control occurrence. This pairing is not a mathematical operation, a scalar
[6]. Managing costs includes estimating, scheduling, accumulat- or vector quantity, but a matching of an event’s likelihood of
ing and analyzing cost data, and finally implementing measures occurrence with the expected outcome. The generally accepted
to correct a cost problem. There are several cost control tech- expression for risk is shown in equation 1 [7].
niques that are used by the construction industry to varying
degrees. These are exception reporting, trend analysis, earned
value, range estimating, and forecast unit cost. Except for perhaps
Risk º [(P1 , C1 )(
, P2 , C 2 ),..., (Px , C x )]
earned value, these cost control techniques tend to focus on vari- (equation 1)
ances in line items once the cost overrun has been discovered.
What is needed is a cost control methodology that proactively In this equation, Px is the occurrence probability of event x,
seeks out potential cost issues and provides project managers with and Cx is the occurrence consequences or outcomes of event x.
as much warning as possible before their occurrence. The consequences of a risk event in the project management field
will most likely be in terms of dollars. Risk is sometimes thought
as the potential for harm. In a project management context and as
RISK ANALYSIS defined in this paper, risk is thought of as being concerned with
opportunities or potential gain as well as negative consequences.
Risk analysis is identified as a major subset to project man- This broader risk definition is known as risk engineering [15].
agement [14]. However, its application appears limited within the There is a consensus within the technical community that a
field of construction project management. It is limited in its wide- comprehensive risk analysis consists of risk assessment, risk man-
spread use [2], and sometimes it is only applied to developing agement, and risk communication [12]. Risk assessment is the
schedules [11] or cost estimates [5]. The reasons for this limited process of identifying and evaluating areas of risk. Risk manage-
use are difficult to identify and quantify. McKim proposed that ment is the act or practice of dealing with or controlling this risk.
risk analysis is viewed by construction cost engineers as an intim- Risks can be managed based on the information provided from
idating subject [10]. Blair states that the data required to apply risk the risk assessment to determine risk acceptability and using deci-
analysis is often expressed in linguistic terms and is difficult to sion analysis to make risk informed decisions for control and mit-
apply in a classic quantitative risk analysis [4]. An application of igation purposes. Risk communication is the process of docu-
fuzzy logic and set theory can be used as a solution to the later rea- menting and exchanging information about the results of risk
son [4, 13]. Al-Bahar and Crandall also point out that construction studies to various interested parties.
professionals tend to use rules-of-thumb, and rely on intuition or
experience when dealing with risk [2]. What is needed is an
CSC.01.1
2001 AACE International Transactions
Risk Assessment
Risk assessment is a technical and scientific process by which
the risk of given situations for a system are modeled and quanti-
fied. Risk assessment provides qualitative and quantitative data to Lines of
decision-makers for later use in risk management. Risk assessment Constant Risk
for construction projects can be performed by comparing the
resource requirements needed to build the projects to the existing
industrial capacity and by performing simulations of the construc-
Increasing Risk
tion processes. These techniques highlight the critical cost areas
and opportunities for savings. When data does not exist or is
Likelihood
unavailable, a construction risk assessment can be made in quali-
tative terms. Where data exists or can be obtained, the risk assess- Curved Line of
ment is quantitative. The risk assessment then considers devia- Constant Risk
tions from these construction scenarios that can lead to undesir-
able or positive consequences. The consequences can be
described in terms of adverse or positive effects on a project’s cost,
schedule, safety, or technical performance.
Qualitative risk analysis uses expert opinion to evaluate the
probability and consequence of an event’s occurrence. Safety
review/audit, checklist, what-if, hazard and operability study Consequence
(HAZOP), preliminary hazard analysis, risk assessment matrix
Figure 1—Risk Profile and Levels of Risk
tables, analytical hierarchy process, consequence assessment and
cause consequence diagrams, expected monetary value using the where DCost is the monetary amount required to reduce risk and
Delphi technique, and influence diagrams are normally consid- DRisk is the level of risk reduction.
ered qualitative techniques. Quantitative analysis relies on statisti- An integral part of risk management is the use of decision
cal methods and databases that determine the probability and analysis. Project management and engineering are professions
consequence of an event. Simulation, failure modes and effects that require decisions to be made for the management of cost,
analysis, fault tree analysis, event tree analysis, success tree, acci- schedule technical, and safety risks. Most decision analysis tech-
dent progression and frequency analysis, common cause scenar- niques have the following steps or phases: identify the problem
ios, sensitivity factors, fuzzy stochastic applications, risk premium, and objectives, develop alternatives, evaluate the alternatives, and
expected monetary value and expected net present value, risk implement the best alternative [3]. In a risk-based decision analy-
adjusted rate of return, and stochastic dominance are generally sis, these steps should include the uncertainties associated with
considered quantitative risk assessment techniques. the data or alternatives. Four possible decision analysis methods
that can be used in a risk-based decision analysis methodology are
decision trees, goal trees, the analytic hierarchy process, and risk-
Risk Management based net present value.
Risk management is the process by which system operators,
project managers, and owners make decisions, changes, and
choose different system configurations based on the data generat- RISK-BASED COST CONTROL
ed in the risk assessment. Risk management is also dynamic as
new information about risk events becomes available managers A cost control technique that anticipates potential cost issues
should adjust accordingly. by using risk analysis and simulation techniques to highlight
In order to make decisions based on risk, a level of acceptable
potential areas prone to cost escalation is presented. This risk
risk must be determined. A risk profile diagram is shown in figure
analysis is also used to highlight areas where cost savings or a com-
1, lines of constant risk show that risk increases as the likelihood
petitive advantage may be gained. The risk analysis techniques
and/or consequence of a risk event increases. Figure 1 also shows
employed are a dynamic process, constantly updated, as new
that when considering risk acceptance, curves that show a high information becomes available. Risk analysis information, along
consequence with an extremely low likelihood, and vice versa, with cost forecasting tools, is combined to anticipate a project’s
may be used to show acceptable risk. Management should deter- cost problems and completion costs.
mine risk acceptance through a systematic process that may be The presented methodology is applied in the planning and
project specific, based on general corporate or government guide-
execution phase of a project as illustrated in figure 2. Risk meth-
lines. Risk acceptance can also be determined by the cost effec-ods are used to help establish cost and schedule targets in the
tiveness of risk reduction or opportunity gained. This cost effec-
planning phase. A project’s costs are a function of schedule, and
tiveness is calculated as the integration of cost and schedule is an important part of the
methodology. In the execution phase, risk methods are applied to
DRisk help managers control projects with the goal of delivering them
Cost Effectiveness =
DCost on budget and schedule.
The presented risk analysis is a combination of both qualita-
(equation 2) tive and quantitative risk methods. The generic structure of this
CSC.01.2
2001 AACE International Transactions
risk analysis for cost control is shown in figure 3. In the risk assess-
ment phase the probabilities and consequences of risks or oppor-
Risk Methods tunities are quantified and using a risk assessment matrix table a
Cost/ Schedule determination of risk is made. Table 1 is an example of a risk
Targets assessment matrix table. Once an expression for the likelihood
Planning and consequence of an event is developed, a risk rating can be
determined. For example, if the likelihood of a labor strike is like-
ly and the consequence of this event is critical, the risk rating from
Risk Methods
table 1 for a labor strike is “high.” Risk ratings are then compared
to risk acceptance levels. and a decision analysis process is used to
Project Control Execution assist management. The activities in the boxes represent risk
assessments. and the activities in the arrow represent a shift to risk
management functions. The basic structure shown in figure 3 is
applied in both the planning and execution phases of a project
except in the execution phase earned value techniques and con-
tinuous monitoring are performed.
Project Delivered on Budget
& on Time
PLANNING PHASE
System Definition
Risk Identification
Define Events
Assessment of Assessment of
Probabilities Consequences
Risk Assessment
Risk
Acceptability
Decision
Analysis
Project
WBS
Work Package
Point Estimates
Risk or Opportunity
Identified via Risk Check List
Qualitatively Described via
Risk Matrix Work Package
Quantitatively Applied to Estimates with
Cost Estimate via Simulation Uncertainty
Estimated Cost of
Risk Mitigation
Project with
or
Highlighted Risks or
Opportunities
Opportunities
Risk Events
Defined
Assess Risk
Probability
Consequences
Risk
Acceptable?
Establish
Risk Assessment
No
Earned Value
Decision
Analysis
Establish Earned Value
Yes
Update
Monitor
Risk Assessment Data
Earned Value Data
Monthly
Update
Project Information
Risk Assessment
Risk Assessment Data
Earned Value
Earned Value Data
Why?
Risk
Review
Yes Cost
Risk Assessment
Variance?
Cost Data
Project
Completion
CSC.01.7
2001 AACE International Transactions
the essence, the availability of accurate data, and it is systematical solutions to potential cost issues. Risk profiles of risk events are dis-
and simple. played, and the cost effectiveness of risk reduction is used to assist
Time is of the essence during the execution phase because a in making risk acceptability decisions. The graphical expressions
decision must be made early enough to affect the project’s out- of risk also help to determine whether lowering a consequence or
come. This window of opportunity is greatest at the beginning of the likelihood of an event will have the greatest effect on lowering
a project and decreases proportionally with the time remaining on the risk.
a project. The typical complex construction project will be one of The primary objective of the methodology is to control costs
a kind or significantly different from past projects, therefore accu- when building complex structures. This is achieved through a
rate data on past projects may not be available to populate a simi- succession of steps culminating in a decision analysis process. The
lar decision analysis that requires probabilistic data. Goal trees are decisions made must be followed by actions designed to rectify a
a systematic process that exposes several options for management problem or take advantage of a situation. The results of these
to consider. To aid in rapid decision making they are swiftly and actions are also monitored to ensure that a correct alternative was
simply constructed. chosen. The cycle of reassessment, analyzing earned value data,
The advantage of goal trees is speed and simplicity. decision-making, and monitoring continues until a project is com-
Unfortunately goal trees do not provide an expected monetary pleted.
value or a probability of success. This may be acceptable due to
the short window of opportunity and the lack of accurate data in
the execution phase. Should time allow and accurate data is avail- REFERENCES
able, decision trees should be used to help decision-makers decide
between alternatives. 1. AbouRizk, S.M., and D. Halpin. Statistical Properties of
Construction Duration Data. Journal of Construction
Engineering and Management 118, number 3 (1992).
Execution Phase Cost Control 2. Al-Bahar, J.F., and K.C. Crandall. Systematic Risk
In this stage of a project’s life cycle, management takes action Management Approach for Construction Projects. Journal of
to correct an observed variance. Once a decision has been made Construction Engineering and Management 116, number
and action taken, the results must be monitored for their effec- 3 (1990).
tiveness. This process continues until a project is completed. 3. Ayyub, B.M., and R.H. McCuen. Probability, Statistics and
Reliability for Engineers. Boca Raton, FL: CRC Press, 1997.
4. Blair, A.N. Risk Analysis of Cost and Schedule of Complex
ost control is needed in the construction project man- Engineering Systems. Ph.D. thesis, University of Maryland,
6.
College Park, MD, 1999.
Hulett, D.T. Project Schedule Risk Assessment. Project
Management Journal (March 1995).
Humphreys, K.K. Jelen’s Cost and Optimization
Engineering. 3rd ed. New York: McGraw-Hill, 1991.
able results. To be the most effective over the life cycle of a proj- 7. Kumamoto, H., and E.J. Henley. Probabilistic Risk
ect, a cost control system must be applicable to both the planning Assessment and Management for Engineers and Scientists.
and execution phases. The system needs to be simple enough that 2nd ed. New York: IEEE Press, 1996.
it is applicable and generic enough to apply to a wide cross-sec- 8. Laufer, A., and G.A. Howell. Construction Planning: Revising
tion of projects. the Paradigm. Project Management Journal (June 1993).
A risk-based cost control methodology was presented that 9. Law, A., and W.D. Kelton. Simulation Modeling and
combines simulation, earned value, and risk analysis techniques Analysis. 2nd ed. New York: McGraw-Hill, 1991.
in a novel approach to cost control. This proposed methodology 10. McKim, R.A. Risk Management Back to Basics. Cost
provides construction project managers with a structured frame- Engineering 34, number 12 (1992).
work to make cost control decisions during the planning and exe- 11. Mullholland, B., and J. Christian. Risk Assessment in
cution phases of construction. During the planning phase, risks Construction Schedules. Journal of Construction
are identified, assessed, deemed acceptable or unacceptable, a Engineering and Management 125, number 1 (1999).
decision analysis is performed, and risk-based cost and schedule 12. National Research Council. Risk Assessment in the Federal
targets using a simulation technique are developed. During the Government: Managing the Process. Washington, DC:
execution phase, a similar process is followed, with the addition of National Academy Press, 1983.
the cost control technique of earned value that is intertwined with 13. Ock, J.H. Activity Duration Quantification Under
risk assessment updates and decision analysis to provide cost con- Uncertainty: Fuzzy Set Theory Application. Cost
trol. The presented methodology uses goal and decision trees, Engineering 38, number 1 (1996).
where appropriate, to develop the most cost-effective solution to 14. PMI Project Management Institute. A Guide to the Project
cost issues. Management Body of Knowledge. Upper Darby, PA: Project
A salient feature of the presented methodology is the struc- Management Institute, 1996.
tured format, graphical expression of risk, and proposed solutions 15. Wang, J.X., and M.L. Roush. What Every Engineer Should
to mitigate the risk. The structured format allows project team Know About Risk Engineering and Risk Management.
members to systematically identify, quantify, discuss, and pose New York: Marcel Dekker, 2000.
CSC.01.8
2001 AACE International Transactions
William J. Bender, PE
Assistant Professor, Construction Management
Central Washington University
Ellensburg, WA 98926
phone: 509-963-3543
e-mail: benderw@cwu.edu
Bilal M. Ayyub, PE
Professor, Department of Civil and Environmental Engineering
University of Maryland
College Park, MD 20742
CSC.01.9