Professional Documents
Culture Documents
CONSTRUCTION
1. SCOPE...................................................................................................4
3. SITE CONDITIONS................................................................................9
4. SAFETY .................................................................................................9
8. FIRE PROTECTION.............................................................................10
9. SCAFFOLDING ...................................................................................10
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
This specification shall be read in conjunction with all other specifications and documents
included in the Agreement between ADWEA/ENGINEER and the CONTRACTOR.
The CONTRACTOR shall be responsible for the Construction of the work taking due care to
comply with all laws, bylaws, regulations etc. issued by the Authorities.
The CONTRACTOR shall be responsible for the security of the site including his own and
Sub-Contractors work, plant, materials etc. and the safety of adjoining property, and shall be
liable for any loss or damage suffered.
The CONTRACTOR shall have deemed to have inspected and examined the work areas and
its surroundings and to have satisfied himself as to form and nature thereof including
subsurface conditions, hydrological and climatic conditions, the extent and nature of work,
and the means of access to the work areas.
No claims by way of cost or time, shall be admissible on account of non familiarity with site
conditions.
BS 6399, Part 1: Code of Practice for Dead and Imposed Loads, Part 2: Code of Practice for
Wind Loads.
BS 812 Methods for Sampling and Testing of Mineral Aggregates, Sands and
Fillers.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
BS 4482 Hard Drawn Mild Steel Wire for the Reinforcement of Concrete.
BS 709 Methods of Destructive Testing Fusion Welded Joints and Weld Metal
in Steel.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
BS 2853 Specification for the Design and Testing of Steel Overhead Runaway
Beams.
BS 4018 Specification for Pulley Blocks for Use With Wire Roper for Maximum
Lift of 25 ton in Combination.
BS 4190 Specification for ISO Metric Black Hexagon Bolts, Screws and Nuts.
BS 4429 Specification for Rigging Screws and Turn Buckles for General
Engineering Lifting Purposes and Pipe Hanger Applications.
BS 4465 Specification for Design and Construction of Electric Hoists for both
Passengers and Materials.
BS 4536 Specification for Heavy Duty Pulley Blocks for use with Wire Rope.
BS 4604 Specification for the Use of High Strength Friction Grip Bolts in
Structural Steelwork.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
BS 6210 Code of practice for Safe Use of Wire Rope Slings for General Lifting
Purposes.
BS 6323 Specification for Stainless and Welded Steel Tubes for Automobile,
Mechanical and General Engineering.
BS 6521 Guide for Proper Use and Maintenance of Calibrated Round Steel Link
Lifting Chains.
BS EN 10029 Specification for Tolerances on Dimensions, Shape and Mass for Hot
Rolled Steel Plates.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
BS EN 10210 Hot Finished Structural Hollow Sections of Non-alloy and Fine Grain
Structural Steels.
BS EN ISO 12944 Code of Practice for Protective Coating of Iron and Steel Structures
Against Corrosion.
BS EN ISO 1461 Specification for Hot-Dip Galvanized Coatings on Iron and Steel
Articles.
2.5 Painting
BS 6949 Specification for Bitumen Based Coating for Cold Application Excluding
Use in Contact with Potable Water.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
2.6 Pavements
3. SITE CONDITIONS
4. SAFETY
All CONTRACTOR's works shall be performed in accordance with best safe practices for
activities to be undertaken during construction.
Detailed method statements for each activity to be undertaken shall be prepared by the
CONTRACTOR inclusive of all proposed safety measures for submission to gain approval by
ADWEA/ENGINEER which must be obtained prior to the start of the activity concerned.
All CONTRACTOR's personnel shall be suitably trained to perform activities and in the safe
use of all equipment to be operated.
5. SETTING OUT
The CONTRACTOR shall employ experienced Land Surveyors to carry out all surveying and
setting out work. The CONTRACTOR will establish the lines and levels of the works prior to
commencement of works.
In order to establish the existing ground levels over the areas of the works, the
CONTRACTOR shall establish a grid over the site and agree the levels, grading etc. and final
levels required with ADWEA/ENGINEER.
The CONTRACTOR shall also check the accuracy of the Survey drawings etc. given to him
and notify ADWEA/ENGINEER of any Discrepancy whatsoever.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
The CONTRACTOR shall also carry out all dimensional and setting out checks on the
construction items as may be required by the technical sections of interdisciplinary
specifications of the contract.
Any and all discrepancies found during these checks shall be noted and brought to the
attention of ADWEA/ENGINEER with their significance to the works clearly highlighted.
The necessity for, provision of, details of and maintenance of Temporary road diversions and
existing road closures shall be subject to the approval of ADWEA/ENGINEER and the
Federal Traffic Police. No Public or Private facility shall be stopped or interrupted without the
written permission of ADWEA/ENGINEER. Such permission will not be given until suitable
permanent or temporary alternatives approved by ADWEA/ENGINEER have been provided
by the CONTRACTOR.
Before commencing construction work the CONTRACTOR shall locate the routes and identify
all services in the Area.
The CONTRACTOR shall take any and all measures reasonably required by any Public or
any Statutory Authority for the support and full protection of all mains, pipes, cables and other
apparatus during the progress of the works, and shall construct and provide to the satisfaction
of ADWEA/ENGINEER, all works necessary for the prevention of damage or interruption of
services.
8. FIRE PROTECTION
Adequate precautions shall be taken against fire through all CONTRACTORS and Sub-
Contractors operations.
Construction Practices, including cutting and welding, and protection of adjacent materials
during construction shall be in accordance with good standard practices for such work.
9. SCAFFOLDING
The CONTRACTOR shall provide, erect, maintain, dismantle and clear away at completion
proper and adequate scaffolding including that required for Sub-Contractors and Specialists.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
The CONTRACTOR shall properly uphold the sides of excavations and shall provide all
necessary timber planks and struts and/or temporary sheet piles. Stability calculations for
same shall be submitted to ADWEA/ENGINEER for approval.
The CONTRACTOR shall provide all necessary temporary supports to pipes, cables and the
like throughout his works. Stability calculations for such shall be submitted to
ADWEA/ENGINEER for approval.
The CONTRACTOR shall furnish ADWEA/ENGINEER with shop drawings which he shall
require -detailing materials, layouts, sizes, dimensions, etc. clearly. No such work shall be put
in hand until ADWEA/ENGINEER's approval of shop drawings has been obtained in writing.
The CONTRACTOR shall execute the work in accordance with the intent and meaning of
specifications and drawings and shall supply all accessories and other items essential for the
proper execution of the work and shall execute all work which may be reasonably inferred
whether or not specifically shown or described.
The whole of the workmanship, goods and materials incorporated in the works shall be new
and of the best quality available and shall be to the approval of ADWEA/ENGINEER.
Should ADWEA/ENGINEER discover on the works any materials other than those approved,
they may order their removal from site. Removal of these unapproved materials from site is to
be done at the expense of CONTRACTOR.
Prior to ordering or delivering any materials or manufactured item to site, the name and
address of the Supplier and, where required by ADWEA/ENGINEER, adequate samples,
sample schedules and Manufacturer's certificates for all the materials and goods to be used
in the works shall be submitted to ADWEA/ENGINEER for approval.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
The CONTRACTOR shall provide water and electricity for the works including that required by
the sub-contractors and provide all necessary temporary work.
Importing water by tanker and storing on site shall be allowed for by the CONTRACTOR.
Temporary electricity generating equipment, should this prove necessary, shall be allowed for
by the CONTRACTOR.
17. EARTHWORKS
17.1 General
The CONTRACTOR shall, before commencing any excavation, grading or fill, survey and
take levels on the original ground surface and correlate same with all drawings made
available to him. He shall then prepare plans and sections accordingly which should be
mutually agreed and signed by ADWEA/ENGINEER and CONTRACTOR as truly
representing the configuration of the areas in question at the commencement of work.
17.2.1 General
This work shall consist of clearing and grubbing the area of the work within the limits of the
Site and as ordered by ADWEA/ENGINEER of all debris, refuse, vegetation, demolition debris
and other deleterious material.
The CONTRACTOR shall perform the work of clearing and grubbing so as to remove the
material herein specified and if he wastes material suitable for incorporation into or for use on
the work, the amount of suitable material shall be replaced by the CONTRACTOR at his
expense. All material removed by the clearing and grubbing operation shall be transported
from the site or otherwise disposed of as specified or directed by ADWEA/ENGINEER.
With the exception of areas to be excavated, all depressions made below the ground surface
by the removal of rubbish or existing works shall be refilled with suitable material and
compacted to the satisfaction of ADWEA/ENGINEER.
Grading or excavation operations shall not be started in any areas until clearing and grubbing
within the area affected have been completed.
Fences, upon or within the limits of the works and not necessary for the construction shall be
removed carefully by the CONTRACTOR wholly or in part as specified or directed. The
materials so removed shall be piled neatly and in an acceptable manner or otherwise
disposed of as specified or directed by ADWEA/ENGINEER.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
Unless otherwise specified, all and any kind of works materials services, safety measures,
etc., as well as, and if so requested by ADWEA/ENGINEER all tests and samples required for
the completion of the work shall be included in the offer.
17.3.1 General
Survey points, bench marks, boundary stones and the like shall not be removed without
ADWEA/ENGINEER's written consent.
Extra bench marks to be provided by the CONTRACTOR shall be furnished with a plate,
approximately 25 x 25 cm in size, with the bench mark inscription painted in black letters on a
light background with clearly legible weatherproof oil paint.
For all fill and cut over 1.00 m in height, sturdy stakes shall be placed at any change of
direction of the ground but in all cases at intervals no greater than 30 m as directed by
ADWEA/ENGINEER.
Excavations in sand shall be to a slope of 1:3, one vertical to three horizontal. If any
permanent slope is to be kept in the sand it shall be stabilized by one of the following means,
- Cement/sand mixture
- Bituminous/cement mixture
The quantity, type and capacity of the equipment provided, the work method envisaged,
transportation and distribution of the excavated materials, location of stock-piles, main
storage areas as well as the approximate number of labourers, etc. and the working schedule
and any amendment to it during the construction period shall require ADWEA/ENGINEER's
prior approval.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
The CONTRACTOR shall be responsible for all necessary safety measures. From the
commencement of the work until acceptance, the CONTRACTOR shall strictly follow the
safety regulations in order to prevent accidents.
Proper strutting, sheeting and bracing, including re-arrangement of the installations when
necessary, protection of slopes, methods of excavation to reduce risk of slides, etc., shall be
for the responsibility of the CONTRACTOR. In the event of soil slides occurring during earth
and rock work, all damage shall be made good by the CONTRACTOR.
Where the nature of the soil gives reason to fear any drifting, initial excavation operations
shall be carried out with special care.
Excavation shall not be carried out below existing building foundations, if any, until shoring to
be performed by the CONTRACTOR has been completed. All existing structures,
foundations, pipes and cables, if any, which are to be incorporated into the final work shall be
adequately protected or replaced by the CONTRACTOR.
17.3.3 Over-excavation
If somewhere, and for any reason, excavations are executed beyond the established lines
and without ADWEA/ENGINEER's previous approval, the CONTRACTOR shall backfill with
lean concrete or other approved material, the volume corresponding to the over excavation at
his own expense.
Excavation material from the works selected by ADWEA/ENGINEER for use shall be placed
in its final position, if possible, or otherwise may be stockpiled or deposited on site as directed
by ADWEA/ENGINEER.
Only the stockpiling of rock, gravel and other non-cohesive materials to be used for
permanent work will be permitted. In no case shall the stockpiling of silt or disintegrated rock
to be used in structural fills be permitted.
Spoil unfit for re-use shall be removed by the CONTRACTOR to sites approved by
ADWEA/ENGINEER and shall not be permanently deposited other than on such sites. The
CONTRACTOR shall trim and form the edges of soil to profiles and levels as directed by
ADWEA/ENGINEER. He shall also maintain without interruption the flow of water courses
affected by the disposal of spoil materials and he shall observe any agreement concerning
the site existing between the employer and other personnel or authorities concerned.
The placing of materials within the waste areas shall be made in layers not exceeding 0.50 m
in thickness in order to obtain an appreciable degree of compaction by means of the
transportation equipment. All traffic towards or from the waste areas shall be continuously
directed and changed for the total covering of the surface of such areas in order to take
advantage of the weight of vehicles for compaction.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
The CONTRACTOR shall transport materials from the excavations to their final destination
whether in the work or in the waste areas, including any necessary temporary stockpiling and
the additional loading and transporting operations.
17.3.5 Backfilling
Foundations and structures shall be backfilled with approved material compacted in layers by
suitable equipment until maximum density has been obtained to the satisfaction of
ADWEA/ENGINEER. Compacting shall be carried out with special care by means of
pneumatic or mechanical tampers of a type previously approved by ADWEA/ENGINEER to
avoid damage to structures.
Unless otherwise specified, backfilling density shall not be less than 95% of the maximum
density obtained by the Modified Proctor test (ASTM D 1557).
The thickness of loose fill layers shall not exceed 300 mm unless the CONTRACTOR proves
to the satisfaction by test beds that the equipment and method of compaction exceeds the
required density.
Surfaces receiving fill layers shall, if smooth, be previously scarified to obtain a good key
between the new fill layer and the subgrade.
Fill shall not be deposited under water without ADWEA/ENGINEER's permission. This
permission will not normally be granted for cohesive soil or for fill of any kind where the
standing water, in the opinion of ADWEA/ENGINEER, can be pumped out or diverted.
Permission may be granted to place rock fill by random dumping in areas where the depth of
water is greater than 30 cm but the methods and quality of the fill material shall be subject to
approval and when the fill level is 50 cm above the water surface it shall be compacted until
there is no discernible movement under the equipment used for placing or compacting fill.
Thereafter, normal backfilling and compaction shall be resumed.
Where swamps, bogs or other similar wet areas have to be traversed by the works, they shall
be drained as directed by ADWEA/ENGINEER according to the materials and conditions
encountered. Prior to the formation of embankments, fills, etc., any unsuitable materials
occurring on the site shall be removed to such depths and widths as may be directed by
ADWEA/ENGINEER and approved excavations shall be properly backfilled with suitable and
approved excavated materials and shall be deposited and compacted to the satisfaction of
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
The control of working and tests operations will be carried out by ADWEA/ENGINEER with
the full assistance of the CONTRACTOR.
The CONTRACTOR will prepare sheets for statistical analysis of the field and laboratory tests
as required in accordance with the respective ASTM or BS requirements.
Field density tests in accordance with BS 1377 will be required to be carried out by the
CONTRACTOR at each successive layer of fill at a sampling rate determined by
ADWEA/ENGINEER.
The auxiliary works comprise, but are not necessarily limited to the following :
- removing and storing of boundary stones, bench marks, etc., protection of surveying
points - designations by means of boards -survey and protection of all secondary survey
points, profiles, etc.
- keeping off or diversion of water, including any pumping required, difficult work caused
by water, etc.
- removal of any groynes, buried pipes, fascines and the like that might interfere with
excavation profiles, irrespective of whether or not such structures are specified.
- overcome difficulties resulting from the Specifications relating to filling, compaction tests,
eliminating unsuitable material from filling, and if necessary, mixing of different soil
materials.
- sorting of excavated materials which, if necessary, are to be used for special purposes.
- providing, maintaining and later removing access ways - maintaining existing ways and
roads - providing, placing, maintaining and later removing, conveying and dumping
materials and/or equipment that might be required.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
The tolerance limits for the permanent finished earthworks will be as follows:
Horizontal dimensions will be within +75 mm and -75 mm of the true dimensions shown on
the approved drawings.
For slopes to embankments or cuttings the horizontal deviation between the top and bottom
of the slope will be within +5% and -5% of the true horizontal component of the slope shown
or calculated from the approved drawings.
Formation levels shall be within 0 mm and -25mm of the true levels shown on drawings.
Other earthworks levels shall be within +05 mm and -50 mm of the true levels shown on the
approved drawings.
The CONTRACTOR shall provide and erect adequate number of sign posts at locations
directed by the concerned Department of ADWEA/ENGINEER. The size of the display
boards shall be 2000 deep x 1200 wide or as directed by the concerned Department of
ADWEA/ENGINEER. Minimum size of board shall be 500 deep x 800 wide.
The signboards shall carry the names of the project CONTRACTOR, the ADWEA and the
ENGINEER with logos including the particulars of the local site.
A single post of 76.2 mm dia. MS pipe shall be used for sign boards of 500 x 800 size. For
larger boards two posts of 76.2 mm dia MS pipe shall be used.
The supports shall be epoxy coated with a top coat of polyurethane in grey colour.
Appropriate signs and notices etc. shall be written, by a skilled sign writer, in English and
Arabic, to the approval of ADWEA/ENGINEER.
The CONTRACTOR in carrying out excavation for trenches shall, where required, erect and
maintain an approved type of temporary fencing around any work and shall provide fenced
access ways across the trenches.
The CONTRACTOR shall ensure that all excavation and timbering is carried out in a careful
manner, that it is rendered secure and safe, and that all measures necessary are taken to
prevent the removal or falling in of material beyond the trench dimensions detailed. The
CONTRACTOR shall maintain all timbering until the completion of the work to the satisfaction
of ADWEA/ENGINEER and shall promptly remove any material which has caved into the
excavation.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
A clear space shall be left between the edge of the excavation and the inner toes of the spoil
banks, to the approval of ADWEA/ENGINEER.
No back-throwing whatever shall be allowed and all materials shall be brought to the surface
and formed in heaps clear of the excavation.
The material excavated in trenches shall, if unsuitable, be removed from site and shall be
replaced with suitable material.
All surplus and unsuitable excavated material shall be carted to the approved tip.
The bottom of the trench shall be accurately graded. Care shall be taken not to excavate
below the depths indicated. Where rock is encountered, the rock shall be excavated to the
required depth. Uneven surfaces of the bottom of trench shall be excavated 150mm deeper.
Such depth in rock shall be backfilled with approved fill material and compacted as specified
and/or as directed by ADWEA/ENGINEER.
The width and depth of the trenches for electrical and telephone cables/ducts shall be as
specified in the relative drawings or as ordered by ADWEA/ENGINEER. Banks may be
sloped or widened to facilitate placement of cables, but not to an extent that will cause
interference with other utilities and structures. No battering of trenches shall be allowed under
existing carriageways, unless otherwise agreed by ADWEA/ENGINEER.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
Where new cable ducts are to be laid alongside, over or under the existing, the
CONTRACTOR shall take care to interfere as little as possible with the existing services and
connections thereto and any damage shall be repaired by the CONTRACTOR to the approval
of the appropriate Authority or by the appropriate Authority at the cost of the CONTRACTOR.
The CONTRACTOR shall make all arrangements for protecting existing services and for
temporarily diverting them to maintain the services without interruption.
Existing services, pipes, mains, ducts, etc., exposed in trenches for new work shall be
protected in accordance with the requirements of the relevant Authority before trenches are
refilled.
The CONTRACTOR shall lay cables, fittings, specials, etc., under hedges, fences, walls, etc.,
as necessary.
Where hedges are damaged or destroyed the whole shall be restored and reinstated with
shrubs of the same kind as the hedge, planted in due season in an approved manner and
fenced or otherwise protected as required by ADWEA or occupiers and the ENGINEER.
Where fences or walls are damaged or destroyed the whole shall be restored and reinstated
with like materials to the satisfaction of ADWEA or occupiers and the ENGINEER.
The CONTRACTOR shall ensure that no trees are damaged or permanently removed in
carrying out the Contract except where directed due to the presence of permanent works and
approval is given by the relevant Authority.
Trench refilling shall commence with approved fill in compacted layers not exceeding 200 mm
thick, each layer being well compacted by hand with iron rammers weighing not less than 5
kg, until the trench has been filled to a height of 300 mm above the top of the materials e.g.
cables/ducts etc.
The remainder of the trench shall then be refilled in compacted layers not exceeding 200 mm
in thickness, each layer being well compacted with power rammers, vibrating plate
compactors or other mechanical means of a type to be approved until the ground is
thoroughly consolidated up to the required level for surface reinstatement. Each layer shall be
compacted to 95% of its maximum dry density, should the quantity of the excavated materials
be not sufficient, due to unsuitability or otherwise, for the process of backfill and fill, the
CONTRACTOR shall obtain the quantity required of such backfilled and fill from approved
borrow pits and transport same to the site of work at his own expense.
Trenches shall not be backfilled until all required tests are performed and until
ADWEA/ENGINEER has verified that the materials e.g. cables/ducts etc. have been installed
in accordance with the specifications and drawings.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION
Where cover to materials e.g. cables/ducts is less than 400 mm, or where ordered by
ADWEA/ENGINEER, protection in the form of concrete encasing shall be provided according
to an approved drawing or as ordered by ADWEA/ENGINEER.
Client ADWEA
Project: STANDARD SPECIFICATIONS FOR WATER WORKS
Title: SPECIFICATION FOR GENERAL CIVIL CONSTRUCTION