Professional Documents
Culture Documents
Contract No : H9301
Project Title : South Steel Project
Location : Jizan
Client : SSC
(QA) App’d
Table of Contents
1. Scope
2. References
3. Excavation
5. Backfill
7. Attachment
SSC-stx co. ltd Doc.No.:
South Steel-Project U/G Piping Installation Procedure Rev. : A
of In Saudi Arabia Page : 3 of 11
1.0 Scope
This procedure describes the general requirements of underground piping
work which include the performance of all activities such as excavation work,
backfilling, protective coating and wrapping of carbon steel pipe.
2.0 References
2.1 The related procedures which supplement this procedure are as follows :
- STX STD. Specification
Doc. Underground Piping installation and Testing
- General Welding Procedure.
- Piping Fabrication and Installation Procedure.
2.2 The codes and standards applicable to this procedure are as described in
Piping Fabrication and Installation Procedure.
3.0 Excavation
3.3 Type of pipe bed for the pipe shall be granular soil bed.
3.4 Under roads and in trucking areas all underground pipe work shall be
protected from damage by superimposed loads by the provision of sleeves
surrounded by reinforced concrete encasement.
4.1 Materials
4.1.1 Prime
The primer shall compatible with and from the same source as the tape
wrapping.
4.1.3 Coating for Valves, Flanges, and Patchwork Irregular shaped components
shall be coated with Polyken #938 or Tape coat TC mastic and wrapped with
tape.
4.2.3 Risers
Risers, from underground pipe, shall be wrapped with tape to a minimum of
75mm above finished grade (top of paving) and neatly terminated with two full
laps of tape.
5.0 Backfill
5.1 When the work of backfill pipe are carried out protective measure shall be
taken in consideration to prevent accident such as side wall collages, flooding
of water etc. which can cause damage to pipe and injuries to personnel.
5.2 Care shall be taken to prevent soil and sand from following into pipes, and to
prevent pipes from re-flatting due to underground water or rainwater.
5.3 For bedding and underground pipe, the trench shall be excavated 100 to
150mm below the pipe and filled with granular soil material to a height of at
SSC-stx co. ltd Doc.No.:
South Steel-Project U/G Piping Installation Procedure Rev. : A
of In Saudi Arabia Page : 6 of 11
least the middle of the pipe. Backfill material paced in an excavated trench
shall be compacted with equipment which will produce the degree of
compaction specified.
5.4 In case additional soil and sand for backfilling contain gravel, crushed stone
etc. this shall be used only for upper portion of underground pipes to prevent
damage to pipe coatings.
5.5 Back-filling shall be done with appropriate tamping and 50-100mm overlapping
shall be maintained. Tamping may be done by any one of the following :
- Water binding method
- Rammer method
- Vibrator method
- Compact roller method
- Combination of above methods
The amount of water used in compaction shall be limited to that indicated by
Modified Proctor Test; through soaking or flooding shall not be allowed.
5.6 Back-filling shall be done in layers of uniform thickness is dependant upon the
compaction equipment.
5.8 Back-filling shall only be done after coating and wrapping of welding portions is
completed.
5.9 Pipe supports such as wooden sleeper, sand bag may be installed for aligning
as well as preventing subsidence or movement of pipes, if necessary. After
alignment, wooden sleepers shall be removed and sand bags shall be splited.
6.0 Inspection and Examination (the different requirements can be applied to:)
The surface to be coated and wrapped shall be dry and clean of rust, oil or
other foreign materials.
6.3 Appearance
Finished conditions of coated and wrapped parts shall be inspected visually to
confirm that these materials are fully clinging to the surface of pipe.
7.0 Attachment
VISUAL INSPECTION
RECORD
SSC-stx co. ltd Doc.No.:
South Steel-Project U/G Piping Installation Procedure Rev. : A
of In Saudi Arabia Page : 8 of 11
Form No. :
Page 1 of 2
SSC-stx co. ltd Doc.No.:
South Steel-Project U/G Piping Installation Procedure Rev. : A
of In Saudi Arabia Page : 11 of 11
Page 2 of 2