T & D CIRCLE, JABALPUR

TEST SCHEDULE
Welcome Message Server (NORTEL)

Document No TD/NTII/GSM/ Nortel/WMS/ 233


No of Pages. 3
Issue No. I
Issued By: T&D Circle, Jabalpur
Approved By: CGM T&D Circle
Date of Issue: 15.07.06
Amendment No (If Any) 1
No of Pages:
Issued by:
Date of Issue:

RESTRICTED USE BY BSNL


EMPLOYEES ONLY

“ FIX IT RIGHT AT THE FIRST INSTANCE”


TECHNICAL AND DEVELOPMENT CIRCLE WMS TEST SCHEDULE
JABALPUR

TEST SCHEDULE FOR WMS

PART A. INFRASTRUCTURE TEST

TEST PROCEDURE /
Sl. TEST DESCRIPTION REFERENCE REMARKS
No
1 Raised floor and False ceiling or EI- AT-7010
Antistatic flooring (as provided) (Digital E 10B)
2 Network connectivity/ Trunking As per approved layout plan
diagram/ Point code / GT details
3 Lighting and Power outlets

4 Check of earthing systems and its Earth resistance value should


distribution to equipment be < 0.5 ohm
5 Check of Fire Detection System EI Protection - Fire
AT - 7000
6 A.C. Plant (as applicable) EI Building ACT 002, T0003
7 Engine Alternator As per EA test schedule
8 Power Plant & Batteries & Inverter/UPS As per T & D test schedule
(If provided) & its distribution
9 Location, Alignment & Rigidity (LAR) As per Approved plan
10 Cable laying & Terminations & marking Visual check as per cable
on cables diagram
11 Voltage drop test Voltage drop < 1V from
Battery point to equpt. input
12 DDF: LAR , cable laying and check of As per DDF lay out diagram
protective devices, earthing &
termination
13 QA certificate of all equipment For imported items factory
test report is to be
submitted
14 General Check points Visual check, sign writing etc.

15 Media A/T of each type As per A/T schedule A/T certificate


required if existing

No. TD/NTII/GSM/Nortel/ WMS/ 233 Page 2 of 3 Issue –I


Dated 15.07.06
TECHNICAL AND DEVELOPMENT CIRCLE WMS TEST SCHEDULE
JABALPUR

PART B SYSTEM TEST

SL. TEST ITEM REFERENCE/ REMARK


No. PROCEDURE

1 Hardware conformity for all equipments As per P.O. & B.O.M.


including tools, Spares, . testers and valid
licensed software for operating systems
2 Software conformity check As per system
Software release is to be verified with the document
referred document
3 System Shutdown and Power ON test As per system
document
4 Continuity & redundancy check on PCM Continuity test may be Obtain a certificate
cable/link (Test E1s as per certificate) done using test kit. from nodal circle
about no. of links
(E1) sufficient for
WMS
5 Check of Documentation, Hard / soft copy. As per P.O.
6 Check of approved connectivity diagram
7 Check of spare cards
8 Check for Alarms
9 Diagnostic check
10 Service Provisioning and Administration
test
• Operator provisioning
• Message templates
• Filter provisioning
11 Check for IN Roamers statistics VLR
wise & operator wise
12 FUNCTIONAL CHECK

12.1 National In-roamer welcome


12.2 Subsequent visit ant re-welcome
avoidance timer check
12.3 No message sent during black out period
12.4 White listing and black listing capability

No. TD/NTII/GSM/Nortel/ WMS/ 233 Page 3 of 3 Issue –I


Dated 15.07.06
TECHNICAL AND DEVELOPMENT CIRCLE WMS TEST SCHEDULE
JABALPUR

12.5 Promotional messages


12.6 Verification of holding period for
promotional time messages
12.7 Verification of time delay between the
messages
12.8 Verify max. Messages per day
12.9 Verify personalized messages for roamers
12.10 Welcome message to new home
subscribers

No. TD/NTII/GSM/Nortel/ WMS/ 233 Page 4 of 3 Issue –I


Dated 15.07.06