Professional Documents
Culture Documents
Activity Description
Early Start
Early Finish
DEC 12 19 26 2
GRSR
Sheet 1 of 9
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved
Activity ID
Activity Description
Early Start
Early Finish
DEC 12 19 26 2
GRSR
Sheet 2 of 9
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved
Activity ID
Activity Description
Early Start
Early Finish
DEC 12 19 26 2
GRSR
Sheet 3 of 9
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved
Activity ID
Activity Description
Early Start
Early Finish
DEC 12 19 26 2
GRSR
Sheet 4 of 9
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved
Activity ID
Activity Description
Early Start
Early Finish
DEC 12 19 26 2
RT for EP RT for EP to IBPP Intermediate top Polar petal Erection & Fit up Bottom Polar Petal Welding RT for BPP BP-IBPP welding RT for BPP-IBPP Intermediate Top polar Welding Intermediate Top Polar-Equitorial Petal Welding RT for ITPP & EP to ITPP Top Polar Petal Erection & Fitup Top Polar Petal Welding Top Polar-Intermediate Top Polar Welding RT for TP & TP to ITPP Fitup & Welding of Pad Plates Erection of Top Crown with Nozzles Temp-insulation for PWHT PWHT Erection & Welding of Stairway structures Welding of Internal pipinng FWS erection & Welding Erection of sway Rods Grouting Erection of Internal Scaffolding UT,Hardness & MPT after PWHT Removal of Internal Saffolding Erection, Fitup & Welding of Bottom Crown Local PWHT for Bottom Crown Petals Water Filling Of Hydrotest Dewatering UT after Hydrotest Painting of sphere Mechanical Completion Nitrogen Purging Commisioning
01OCT09 11MAR10 24NOV09 29NOV09 13:29
3 3 12 12 3 12 3 16 16 3 10 15 16 3 25 5 8 1 5 3 8 2 4 5 5 5 5 3 6 4 5 12 1 4 1
0 3 0 8 3 12 3 8 7 3 10 15 16 3 25 5 8 1 5 3 8 2 4 5 5 5 5 3 6 4 5 12 1 0 0
100 19NOV09A 0 24NOV09 100 02NOV09A 60 20NOV09A 0 04DEC09 0 24NOV09 0 08DEC09 70 16NOV09A 85 23NOV09A 0 03DEC09 0 25NOV09 0 05DEC09 0 08DEC09 0 26DEC09 0 02DEC09 0 24DEC09 0 29DEC09 0 06JAN10 0 07JAN10 0 07JAN10 0 07JAN10 0 12JAN10 0 07JAN10 0 07JAN10 0 12JAN10 0 17JAN10 0 22JAN10 0 26JAN10 0 29JAN10 0 04FEB10 0 08FEB10 0 13FEB10 0 25FEB10 100 100
GRSR
22NOV09A 26NOV09 11NOV09A 01DEC09 06DEC09 05DEC09 10DEC09 01DEC09 30NOV09 05DEC09 04DEC09 19DEC09 23DEC09 28DEC09 26DEC09 28DEC09 05JAN10 06JAN10 11JAN10 09JAN10 14JAN10 13JAN10 10JAN10 11JAN10 16JAN10 21JAN10 26JAN10 28JAN10 03FEB10 07FEB10 12FEB10 24FEB10 25FEB10
11NOV09A 14NOV09 01NOV09 13NOV09 27NOV09 16NOV09 30NOV09 13NOV09 16NOV09 06DEC09 03DEC09 13DEC09 16DEC09 03JAN10 10DEC09 01JAN10 06JAN10 14JAN10 15JAN10 15JAN10 15JAN10 20JAN10 15JAN10 15JAN10 20JAN10 25JAN10 30JAN10 03FEB10 06FEB10 12FEB10 16FEB10 21FEB10 05MAR10
13NOV09 16NOV09 12NOV09 24NOV09 29NOV09 27NOV09 02DEC09 28NOV09 01DEC09 08DEC09 12DEC09 27DEC09 31DEC09 05JAN10 03JAN10 05JAN10 13JAN10 14JAN10 19JAN10 17JAN10 22JAN10 21JAN10 18JAN10 19JAN10 24JAN10 29JAN10 03FEB10 05FEB10 11FEB10 15FEB10 20FEB10 04MAR10 05MAR10
RT for EP RT for EP to IBPP Intermediate top Polar petal Erection & Fit up Bottom Polar Petal Welding RT for BPP BP-IBPP welding RT for BPP-IBPP Intermediate Top polar Welding Intermediate Top Polar-Equitorial Petal Welding RT for ITPP & EP to ITPP Top Polar Petal Erection & Fitup Top Polar Petal Welding Top Polar-Intermediate Top Polar Welding RT for TP & TP to ITPP Fitup & Welding of Pad Plates Erection of Top Crown with Nozzles Temp-insulation for PWHT PWHT Erection & Welding of Stairway structures Welding of Internal pipinng FWS erection & Welding Erection of sway Rods Grouting Erection of Internal Scaffolding UT,Hardness & MPT after PWHT Removal of Internal Saffolding Erection, Fitup & Welding of Bottom Crown Local PWHT for Bottom Crown Petals Water Filling Of Hydrotest Dewatering UT after Hydrotest Painting of sphere Mechanical Completion Nitrogen Purging Commisioning
Sheet 5 of 9
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved
Activity ID
Activity Description
Early Start
Early Finish
DEC 12 19 26 2
RT for EP Intermediate Bottom polar Petal welding Intermediate Bottom Polar-EP Welding RT for Equitorial & Intermediate Bottom Polar Bottom polar petal Erection & Fitup. Derrick assembly Erection Intermediate Top Polar petal Erection & Fitup Bottom Polar Petal Welding RT for BPP BP-IBP welding RT for BPP & IBPP Intermediate Top polar Welding Intermediate Top Polar-Equitorial Petal Welding RT for ITPP & EP to ITPP Top Polar Petal Erection & Fitup Top Polar Petal Welding Top Polar-Intermediate Top Polar Welding RT for TP & TP to ITPP Fitup & Welding of Pad Plates Erection of Top Crown with Nozzles Temp-Insulation for PWHT PWHT Erection & Welding of Stairway structures Erection of sway Rods Welding of Internal pipinng FWS erection & Welding Internal Scaffolding UT,Hardness & MPT after PWHT Removal of Internal Scaffolding Erection, Fitup & Welding of Bottom Crown Local PWHT for Bottom Crown Petals Grouting Water Filling Of Hydrotest Dewatering UT after Hydrotest
01OCT09 11MAR10 24NOV09 29NOV09 13:29
3 24 16 3 10 4 12 11 3 14 3 23 15 3 6 9 11 3 25 5 8 1 5 2 3 8 5 5 5 5 3 4 6 4 5
3 0 13 3 0 0 0 11 3 14 3 23 15 3 6 9 11 3 25 5 8 1 5 2 3 8 5 5 5 5 3 4 6 4 5
100 24NOV09 100 28OCT09A 50 24NOV09A 0 27NOV09 100 07NOV09A 100 12NOV09A 100 15NOV09A 0 26NOV09A 0 13DEC09 0 13DEC09 0 29DEC09 20 26NOV09A 0 04DEC09 0 21DEC09 0 15DEC09 0 20DEC09 0 28DEC09 0 10JAN10 0 15DEC09 0 08JAN10 0 13JAN10 0 21JAN10 0 22JAN10 0 27JAN10 0 22JAN10 0 22JAN10 0 22JAN10 0 27JAN10 0 01FEB10 0 05FEB10 0 09FEB10 0 22JAN10 0 12FEB10 0 18FEB10 0 22FEB10
GRSR
26NOV09 26NOV09A 09DEC09 29NOV09 15NOV09A 13NOV09A 22NOV09A 10DEC09 15DEC09 26DEC09 31DEC09 18DEC09 18DEC09 23DEC09 20DEC09 28DEC09 07JAN10 12JAN10 08JAN10 12JAN10 20JAN10 21JAN10 26JAN10 28JAN10 24JAN10 29JAN10 26JAN10 31JAN10 05FEB10 09FEB10 11FEB10 25JAN10 17FEB10 21FEB10 26FEB10
17NOV09A 28OCT09A 06NOV09 09NOV09 12NOV09 17NOV09 21NOV09 03DEC09 17DEC09 06DEC09 20DEC09 20DEC09 23DEC09 10JAN10 13DEC09 23DEC09 26DEC09 13JAN10 18DEC09 11JAN10 16JAN10 24JAN10 25JAN10 30JAN10 25JAN10 25JAN10 25JAN10 30JAN10 04FEB10 08FEB10 12FEB10 25JAN10 15FEB10 21FEB10 25FEB10
19NOV09 20NOV09 21NOV09 11NOV09 21NOV09 20NOV09 02DEC09 14DEC09 19DEC09 17DEC09 22DEC09 04JAN10 07JAN10 12JAN10 22DEC09 06JAN10 10JAN10 15JAN10 11JAN10 15JAN10 23JAN10 24JAN10 29JAN10 31JAN10 27JAN10 01FEB10 29JAN10 03FEB10 08FEB10 12FEB10 14FEB10 28JAN10 20FEB10 24FEB10 01MAR10
Sheet 6 of 9
RT for EP Intermediate Bottom polar Petal welding Intermediate Bottom Polar-EP Welding RT for Equitorial & Intermediate Bottom Polar Bottom polar petal Erection & Fitup. Derrick assembly Erection Intermediate Top Polar petal Erection & Fitup Bottom Polar Petal Welding RT for BPP BP-IBP welding RT for BPP & IBPP Intermediate Top polar Welding Intermediate Top Polar-Equitorial Petal Welding RT for ITPP & EP to ITPP Top Polar Petal Erection & Fitup Top Polar Petal Welding Top Polar-Intermediate Top Polar Welding RT for TP & TP to ITPP Fitup & Welding of Pad Plates Erection of Top Crown with Nozzles Temp-Insulation for PWHT PWHT Erection & Welding of Stairway structures Erection of sway Rods Welding of Internal pipinng FWS erection & Welding Internal Scaffolding UT,Hardness & MPT after PWHT Removal of Internal Scaffolding Erection, Fitup & Welding of Bottom Crown Local PWHT for Bottom Crown Petals Grouting Water Filling Of Hydrotest Dewatering UT after Hydrotest
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved
Activity ID
Activity Description
Early Start
Early Finish
Target 1 Target 1 Early Start Early Finish 3 02MAR10 14MAR10 13MAR10 14MAR10
DEC 12 19 26 2
2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27 Painting of sphere Mechanical Completion Nitrogen Purging Commisioning
GRSR
Sheet 7 of 9
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved
Activity ID
Activity Description
Early Start
Early Finish
DEC 12 19 26 2
GRSR
Sheet 8 of 9
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved
Activity ID
Activity Description
Early Start
Early Finish
DEC 12 19 26 2
GRSR
Sheet 9 of 9
Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout
Date
Revision
Checked
Approved