You are on page 1of 9

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27

40-TK-602 LIQUID FUEL TANK


CONSTRUCTION & PROCUREMENT
40TK602.01 40TK602.02 40TK602.03 40TK602.04 40TK602.05 40TK602.06 40TK602.07 40TK602.08 40TK602.09 40TK602.10 40TK602.11 40TK602.12 40TK602.13 40TK602.14 40TK602.15 40TK602.16 40TK602.17 40TK602.18 Water Filling for Hydrotest Dewatering & Cleaning Bottom Plate Vacuum Box & DP Test External Scaffolding for Painting External Blasting & Primer Intermediate Coating Final Coating Internal Scaffolding for Painting Internal blasting & 1st coat for shell & Roof 2nd coat for shell & Roof Internal scaffholding Dismantling Internal Blasting & 1st coat for Bottom plate 2nd coat for Bottom plate internal Floating Roof Primary seal Jet mixer, Emergency Valve & Dip Hatch Pre-commisioning Handing Over 10 4 4 6 4 2 2 5 4 2 3 1 1 6 3 2 3 1 0 0 0 0 0 0 2 0 0 2 3 1 1 6 3 2 3 1 100 24OCT09A 100 06NOV09A 100 12NOV09A 100 22OCT09A 100 08NOV09A 100 13NOV09A 25 17NOV09A 100 14NOV09A 100 23NOV09A 0 24NOV09 0 26NOV09 0 29NOV09 0 30NOV09 0 01DEC09 0 07DEC09 0 10DEC09 0 12DEC09 0 15DEC09 05NOV09A 12NOV09A 13NOV09A 27OCT09A 11NOV09A 18NOV09A 25NOV09 19NOV09A 26NOV09A 25NOV09 28NOV09 29NOV09 30NOV09 06DEC09 09DEC09 11DEC09 14DEC09 15DEC09 24OCT09 04NOV09 08NOV09 24OCT09 10NOV09 14NOV09 16NOV09 10NOV09 16NOV09 20NOV09 22NOV09 25NOV09 26NOV09 27NOV09 03DEC09 06DEC09 08DEC09 11DEC09 03NOV09 07NOV09 11NOV09 27OCT09 13NOV09 15NOV09 15NOV09 14NOV09 20NOV09 21NOV09 24NOV09 25NOV09 26NOV09 02DEC09 05DEC09 07DEC09 10DEC09 11DEC09 Water Filling for Hydrotest Dewatering & Cleaning Bottom Plate Vacuum Box & DP Test External Scaffolding for Painting External Blasting & Primer Intermediate Coating Final Coating Internal Scaffolding for Painting Internal blasting & 1st coat for shell & Roof 2nd coat for shell & Roof Internal scaffholding Dismantling Internal Blasting & 1st coat for Bottom plate 2nd coat for Bottom plate internal Floating Roof Primary seal Jet mixer, Emergency Valve & Dip Hatch Pre-commisioning Handing Over

Start Date Finish Date Data Date Run Date

01OCT09 11MAR10 24NOV09 29NOV09 13:29

Early Bar Target Bar Progress Bar Critical Activity

GRSR

Sheet 1 of 9

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27

40-TK-603AOCU GASOLENE TANK


CONSTRUCTION & PROCUREMENT
40T603A.01 40T603A.02 40T603A.03 40T603A.04 40T603A.05 40T603A.06 40T603A.07 40T603A.08 40T603A.09 40T603A.10 40T603A.11 40T603A.12 40T603A.13 40T603A.14 40T603A.15 40T603A.16 40T603A.17 40T603A.18 Shell Course-S3 Shell Course-S2 Shell Course-S1 Shell to Bottom Fit up & Welding Shell Nozzle Anchor Chair Stairway Grouting by TR Water Filling for Hydrotest Dewatering & Cleaning Bottom plate Vaccuum & DP test External Scaffolding for Painting External Blasting & Primer Coat Intermediate Coating Final Coating Emergency Valve & Dip hatch Pre-Commisioning Handing Over 8 8 8 4 6 6 6 4 5 4 1 4 5 2 2 1 2 1 0 0 6 4 6 6 6 4 5 4 1 4 5 2 2 1 2 1 100 05NOV09A 100 08NOV09A 50 22NOV09A 0 30NOV09 0 04DEC09 0 04DEC09 0 04DEC09 0 10DEC09 0 14DEC09 0 19DEC09 0 23DEC09 0 14DEC09 0 18DEC09 0 23DEC09 0 25DEC09 0 27DEC09 0 28DEC09 0 30DEC09 18NOV09A 21NOV09A 29NOV09 03DEC09 09DEC09 09DEC09 09DEC09 13DEC09 18DEC09 22DEC09 23DEC09 17DEC09 22DEC09 24DEC09 26DEC09 27DEC09 29DEC09 30DEC09 05NOV09A 08NOV09 13NOV09 21NOV09 24NOV09 24NOV09 24NOV09 02DEC09 06DEC09 11DEC09 15DEC09 06DEC09 11DEC09 16DEC09 18DEC09 20DEC09 21DEC09 23DEC09 10NOV09 15NOV09 20NOV09 23NOV09 29NOV09 29NOV09 01DEC09 05DEC09 10DEC09 14DEC09 15DEC09 10DEC09 15DEC09 17DEC09 19DEC09 20DEC09 22DEC09 23DEC09 Shell Course-S3 Shell Course-S2 Shell Course-S1 Shell to Bottom Fit up & Welding Shell Nozzle Anchor Chair Stairway Grouting by TR Water Filling for Hydrotest Dewatering & Cleaning Bottom plate Vaccuum & DP test External Scaffolding for Painting External Blasting & Primer Coat Intermediate Coating Final Coating Emergency Valve & Dip hatch Pre-Commisioning Handing Over

Start Date Finish Date Data Date Run Date

01OCT09 11MAR10 24NOV09 29NOV09 13:29

Early Bar Target Bar Progress Bar Critical Activity

GRSR

Sheet 2 of 9

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27

40-TK-603B OCU GASOLENE TANK


CONSTRUCTION & PROCUREMENT
40T603B.01 40T603B.02 40T603B.03 40T603B.04 40T603B.05 40T603B.06 40T603B.07 40T603B.08 40T603B.09 40T603B.10 40T603B.11 40T603B.12 40T603B.13 40T603B.14 40T603B.15 40T603B.16 40T603B.17 40T603B.18 40T603B.19 40T603B.20 40T603B.21 Doom Roof Petals Erection, Fit up & Welding Roof Nozzle Roof Hand Rail Platform Shell Course-S3 Shell Course-S2 Shell Course-S1 Shell to Bottom Fit up & Welding Shell Nozzle Anchor Chair Stairway Grouting by TR Water Filling for Hydrotest Dewatering & Cleaning Bottom plate Vaccuum & DP test External Scaffolding for Painting External Blasting & Primer Coat Intermediate Coating Final Coating Emergency Valve & Dip hatch Pre-Commisioning Handing Over 10 8 6 4 4 4 5 6 6 6 4 5 3 1 5 5 2 2 1 1 1 0 0 0 4 4 4 5 6 6 6 4 5 3 1 5 5 2 2 1 1 1 100 29OCT09A 100 24NOV09A 100 13NOV09A 0 29NOV09A 0 30NOV09 0 03DEC09 0 07DEC09 0 12DEC09 0 12DEC09 0 10DEC09 0 16DEC09 0 20DEC09 0 25DEC09 0 28DEC09 0 19DEC09 0 24DEC09 0 29DEC09 0 31DEC09 0 02JAN10 0 03JAN10 0 04JAN10 20NOV09A 27NOV09A 25NOV09A 30NOV09 03DEC09 06DEC09 11DEC09 17DEC09 17DEC09 15DEC09 19DEC09 24DEC09 27DEC09 28DEC09 23DEC09 28DEC09 30DEC09 01JAN10 02JAN10 03JAN10 04JAN10 01NOV09A 11NOV09 13NOV09 15NOV09 19NOV09 23NOV09 01DEC09 04DEC09 04DEC09 02DEC09 10DEC09 14DEC09 19DEC09 23DEC09 14DEC09 19DEC09 24DEC09 26DEC09 28DEC09 29DEC09 31DEC09 10NOV09 18NOV09 18NOV09 22NOV09 26NOV09 30NOV09 03DEC09 09DEC09 09DEC09 09DEC09 13DEC09 18DEC09 22DEC09 23DEC09 18DEC09 23DEC09 25DEC09 27DEC09 28DEC09 30DEC09 31DEC09 Doom Roof Petals Erection, Fit up & Welding Roof Nozzle Roof Hand Rail Platform Shell Course-S3 Shell Course-S2 Shell Course-S1 Shell to Bottom Fit up & Welding Shell Nozzle Anchor Chair Stairway Grouting by TR Water Filling for Hydrotest Dewatering & Cleaning Bottom plate Vaccuum & DP test External Scaffolding for Painting External Blasting & Primer Coat Intermediate Coating Final Coating Emergency Valve & Dip hatch Pre-Commisioning Handing Over

Start Date Finish Date Data Date Run Date

01OCT09 11MAR10 24NOV09 29NOV09 13:29

Early Bar Target Bar Progress Bar Critical Activity

GRSR

Sheet 3 of 9

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27

40-TP-402 BUTANE SPHERE


CONSTRUCTION & PROCUREMENT
40T402.01 40T402.02 40T402.07 40T402.08 40T402.11 40T402.12 40T402.13 40T402.14 40T402.16 40T402.17 40T402.18 40T402.19 40T402.20 40T402.21 40T402.22 40T402.23 Fit up & Welding of Pads RT Clearance by third party Grouting Erection & Welding of Stairway structures Welding of Internal Piping Removal of Internal Scaffholding Erection of Sway Rods Erection & Welding of Bottom Crown with nozzles Water Filling for Hydrotest Dewatering Fire Water System Erection & Welding UT after Hydrotest Painting of Sphere Mechanical Completion Nitrogen Purging Commisioning 1 3 4 5 5 5 2 6 6 4 8 5 12 2 4 1 0 3 4 5 5 5 2 6 6 4 8 5 12 2 0 0 100 16OCT09A 0 24NOV09 0 27NOV09 0 29NOV09 0 04DEC09 0 09DEC09 0 04DEC09 0 14DEC09 0 20DEC09 0 26DEC09 0 22DEC09 0 30DEC09 0 04JAN10 0 16JAN10 100 100 07NOV09A 26NOV09 30NOV09 03DEC09 08DEC09 13DEC09 05DEC09 19DEC09 25DEC09 29DEC09 29DEC09 03JAN10 15JAN10 17JAN10 08NOV09A 10NOV09 22NOV09 24NOV09 15DEC09 20DEC09 20DEC09 25DEC09 03JAN10 09JAN10 05JAN10 13JAN10 18JAN10 30JAN10 08NOV09 11NOV09 25NOV09 28NOV09 19DEC09 24DEC09 21DEC09 30DEC09 08JAN10 12JAN10 12JAN10 17JAN10 29JAN10 31JAN10 Fit up & Welding of Pads RT Clearance by third party Grouting Erection & Welding of Stairway structures Welding of Internal Piping Removal of Internal Scaffholding Erection of Sway Rods Erection & Welding of Bottom Crown with nozzles Water Filling for Hydrotest Dewatering Fire Water System Erection & Welding UT after Hydrotest Painting of Sphere Mechanical Completion Nitrogen Purging Commisioning

Start Date Finish Date Data Date Run Date

01OCT09 11MAR10 24NOV09 29NOV09 13:29

Early Bar Target Bar Progress Bar Critical Activity

GRSR

Sheet 4 of 9

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27

40-TP-403A MIXED BUTANE SPHERE


CONSTRUCTION & PROCUREMENT
40T403A.01 40T403A.02 40T403A.03 40T403A.04 40T403A.05 40T403A.06 40T403A.07 40T403A.08 40T403A.09 40T403A.10 40T403A.11 40T403A.12 40T403A.13 40T403A.14 40T403A.15 40T403A.16 40T403A.17 40T403A.18 40T403A.19 40T403A.20 40T403A.21 40T403A.22 40T403A.23 40T403A.24 40T403A.25 40T403A.26 40T403A.27 40T403A.28 40T403A.29 40T403A.30 40T403A.31 40T403A.32 40T403A.33 40T403A.34 40T403A.35
Start Date Finish Date Data Date Run Date

RT for EP RT for EP to IBPP Intermediate top Polar petal Erection & Fit up Bottom Polar Petal Welding RT for BPP BP-IBPP welding RT for BPP-IBPP Intermediate Top polar Welding Intermediate Top Polar-Equitorial Petal Welding RT for ITPP & EP to ITPP Top Polar Petal Erection & Fitup Top Polar Petal Welding Top Polar-Intermediate Top Polar Welding RT for TP & TP to ITPP Fitup & Welding of Pad Plates Erection of Top Crown with Nozzles Temp-insulation for PWHT PWHT Erection & Welding of Stairway structures Welding of Internal pipinng FWS erection & Welding Erection of sway Rods Grouting Erection of Internal Scaffolding UT,Hardness & MPT after PWHT Removal of Internal Saffolding Erection, Fitup & Welding of Bottom Crown Local PWHT for Bottom Crown Petals Water Filling Of Hydrotest Dewatering UT after Hydrotest Painting of sphere Mechanical Completion Nitrogen Purging Commisioning
01OCT09 11MAR10 24NOV09 29NOV09 13:29

3 3 12 12 3 12 3 16 16 3 10 15 16 3 25 5 8 1 5 3 8 2 4 5 5 5 5 3 6 4 5 12 1 4 1

0 3 0 8 3 12 3 8 7 3 10 15 16 3 25 5 8 1 5 3 8 2 4 5 5 5 5 3 6 4 5 12 1 0 0

100 19NOV09A 0 24NOV09 100 02NOV09A 60 20NOV09A 0 04DEC09 0 24NOV09 0 08DEC09 70 16NOV09A 85 23NOV09A 0 03DEC09 0 25NOV09 0 05DEC09 0 08DEC09 0 26DEC09 0 02DEC09 0 24DEC09 0 29DEC09 0 06JAN10 0 07JAN10 0 07JAN10 0 07JAN10 0 12JAN10 0 07JAN10 0 07JAN10 0 12JAN10 0 17JAN10 0 22JAN10 0 26JAN10 0 29JAN10 0 04FEB10 0 08FEB10 0 13FEB10 0 25FEB10 100 100
GRSR

22NOV09A 26NOV09 11NOV09A 01DEC09 06DEC09 05DEC09 10DEC09 01DEC09 30NOV09 05DEC09 04DEC09 19DEC09 23DEC09 28DEC09 26DEC09 28DEC09 05JAN10 06JAN10 11JAN10 09JAN10 14JAN10 13JAN10 10JAN10 11JAN10 16JAN10 21JAN10 26JAN10 28JAN10 03FEB10 07FEB10 12FEB10 24FEB10 25FEB10

11NOV09A 14NOV09 01NOV09 13NOV09 27NOV09 16NOV09 30NOV09 13NOV09 16NOV09 06DEC09 03DEC09 13DEC09 16DEC09 03JAN10 10DEC09 01JAN10 06JAN10 14JAN10 15JAN10 15JAN10 15JAN10 20JAN10 15JAN10 15JAN10 20JAN10 25JAN10 30JAN10 03FEB10 06FEB10 12FEB10 16FEB10 21FEB10 05MAR10

13NOV09 16NOV09 12NOV09 24NOV09 29NOV09 27NOV09 02DEC09 28NOV09 01DEC09 08DEC09 12DEC09 27DEC09 31DEC09 05JAN10 03JAN10 05JAN10 13JAN10 14JAN10 19JAN10 17JAN10 22JAN10 21JAN10 18JAN10 19JAN10 24JAN10 29JAN10 03FEB10 05FEB10 11FEB10 15FEB10 20FEB10 04MAR10 05MAR10

RT for EP RT for EP to IBPP Intermediate top Polar petal Erection & Fit up Bottom Polar Petal Welding RT for BPP BP-IBPP welding RT for BPP-IBPP Intermediate Top polar Welding Intermediate Top Polar-Equitorial Petal Welding RT for ITPP & EP to ITPP Top Polar Petal Erection & Fitup Top Polar Petal Welding Top Polar-Intermediate Top Polar Welding RT for TP & TP to ITPP Fitup & Welding of Pad Plates Erection of Top Crown with Nozzles Temp-insulation for PWHT PWHT Erection & Welding of Stairway structures Welding of Internal pipinng FWS erection & Welding Erection of sway Rods Grouting Erection of Internal Scaffolding UT,Hardness & MPT after PWHT Removal of Internal Saffolding Erection, Fitup & Welding of Bottom Crown Local PWHT for Bottom Crown Petals Water Filling Of Hydrotest Dewatering UT after Hydrotest Painting of sphere Mechanical Completion Nitrogen Purging Commisioning
Sheet 5 of 9

Early Bar Target Bar Progress Bar Critical Activity

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27

40-TP-403B MIXED BUTAN SPHERE


CONSTRUCTION & PROCUREMENT
40T403B.01 40T403B.02 40T403B.03 40T403B.04 40T403B.05 40T403B.06 40T403B.07 40T403B.08 40T403B.09 40T403B.10 40T403B.11 40T403B.12 40T403B.13 40T403B.14 40T403B.15 40T403B.16 40T403B.17 40T403B.18 40T403B.19 40T403B.20 40T403B.21 40T403B.22 40T403B.23 40T403B.24 40T403B.25 40T403B.26 40T403B.27 40T403B.28 40T403B.29 40T403B.30 40T403B.31 40T403B.32 40T403B.33 40T403B.34 40T403B.35
Start Date Finish Date Data Date Run Date

RT for EP Intermediate Bottom polar Petal welding Intermediate Bottom Polar-EP Welding RT for Equitorial & Intermediate Bottom Polar Bottom polar petal Erection & Fitup. Derrick assembly Erection Intermediate Top Polar petal Erection & Fitup Bottom Polar Petal Welding RT for BPP BP-IBP welding RT for BPP & IBPP Intermediate Top polar Welding Intermediate Top Polar-Equitorial Petal Welding RT for ITPP & EP to ITPP Top Polar Petal Erection & Fitup Top Polar Petal Welding Top Polar-Intermediate Top Polar Welding RT for TP & TP to ITPP Fitup & Welding of Pad Plates Erection of Top Crown with Nozzles Temp-Insulation for PWHT PWHT Erection & Welding of Stairway structures Erection of sway Rods Welding of Internal pipinng FWS erection & Welding Internal Scaffolding UT,Hardness & MPT after PWHT Removal of Internal Scaffolding Erection, Fitup & Welding of Bottom Crown Local PWHT for Bottom Crown Petals Grouting Water Filling Of Hydrotest Dewatering UT after Hydrotest
01OCT09 11MAR10 24NOV09 29NOV09 13:29

3 24 16 3 10 4 12 11 3 14 3 23 15 3 6 9 11 3 25 5 8 1 5 2 3 8 5 5 5 5 3 4 6 4 5

3 0 13 3 0 0 0 11 3 14 3 23 15 3 6 9 11 3 25 5 8 1 5 2 3 8 5 5 5 5 3 4 6 4 5

100 24NOV09 100 28OCT09A 50 24NOV09A 0 27NOV09 100 07NOV09A 100 12NOV09A 100 15NOV09A 0 26NOV09A 0 13DEC09 0 13DEC09 0 29DEC09 20 26NOV09A 0 04DEC09 0 21DEC09 0 15DEC09 0 20DEC09 0 28DEC09 0 10JAN10 0 15DEC09 0 08JAN10 0 13JAN10 0 21JAN10 0 22JAN10 0 27JAN10 0 22JAN10 0 22JAN10 0 22JAN10 0 27JAN10 0 01FEB10 0 05FEB10 0 09FEB10 0 22JAN10 0 12FEB10 0 18FEB10 0 22FEB10
GRSR

26NOV09 26NOV09A 09DEC09 29NOV09 15NOV09A 13NOV09A 22NOV09A 10DEC09 15DEC09 26DEC09 31DEC09 18DEC09 18DEC09 23DEC09 20DEC09 28DEC09 07JAN10 12JAN10 08JAN10 12JAN10 20JAN10 21JAN10 26JAN10 28JAN10 24JAN10 29JAN10 26JAN10 31JAN10 05FEB10 09FEB10 11FEB10 25JAN10 17FEB10 21FEB10 26FEB10

17NOV09A 28OCT09A 06NOV09 09NOV09 12NOV09 17NOV09 21NOV09 03DEC09 17DEC09 06DEC09 20DEC09 20DEC09 23DEC09 10JAN10 13DEC09 23DEC09 26DEC09 13JAN10 18DEC09 11JAN10 16JAN10 24JAN10 25JAN10 30JAN10 25JAN10 25JAN10 25JAN10 30JAN10 04FEB10 08FEB10 12FEB10 25JAN10 15FEB10 21FEB10 25FEB10

19NOV09 20NOV09 21NOV09 11NOV09 21NOV09 20NOV09 02DEC09 14DEC09 19DEC09 17DEC09 22DEC09 04JAN10 07JAN10 12JAN10 22DEC09 06JAN10 10JAN10 15JAN10 11JAN10 15JAN10 23JAN10 24JAN10 29JAN10 31JAN10 27JAN10 01FEB10 29JAN10 03FEB10 08FEB10 12FEB10 14FEB10 28JAN10 20FEB10 24FEB10 01MAR10
Sheet 6 of 9

RT for EP Intermediate Bottom polar Petal welding Intermediate Bottom Polar-EP Welding RT for Equitorial & Intermediate Bottom Polar Bottom polar petal Erection & Fitup. Derrick assembly Erection Intermediate Top Polar petal Erection & Fitup Bottom Polar Petal Welding RT for BPP BP-IBP welding RT for BPP & IBPP Intermediate Top polar Welding Intermediate Top Polar-Equitorial Petal Welding RT for ITPP & EP to ITPP Top Polar Petal Erection & Fitup Top Polar Petal Welding Top Polar-Intermediate Top Polar Welding RT for TP & TP to ITPP Fitup & Welding of Pad Plates Erection of Top Crown with Nozzles Temp-Insulation for PWHT PWHT Erection & Welding of Stairway structures Erection of sway Rods Welding of Internal pipinng FWS erection & Welding Internal Scaffolding UT,Hardness & MPT after PWHT Removal of Internal Scaffolding Erection, Fitup & Welding of Bottom Crown Local PWHT for Bottom Crown Petals Grouting Water Filling Of Hydrotest Dewatering UT after Hydrotest

Early Bar Target Bar Progress Bar Critical Activity

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3 02MAR10 14MAR10 13MAR10 14MAR10

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27 Painting of sphere Mechanical Completion Nitrogen Purging Commisioning

CONSTRUCTION & PROCUREMENT


40T403B.36 40T403B.37 40T403B.38 40T403B.39 Painting of sphere Mechanical Completion Nitrogen Purging Commisioning 12 1 4 1 12 1 0 0 0 27FEB10 0 11MAR10 100 100 10MAR10 11MAR10

Start Date Finish Date Data Date Run Date

01OCT09 11MAR10 24NOV09 29NOV09 13:29

Early Bar Target Bar Progress Bar Critical Activity

GRSR

Sheet 7 of 9

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27

40-TP-905A ETHANE SPHERE


CONSTRUCTION & PROCUREMENT
40T905A.01 40T905A.02 40T905A.03 40T905A.04 40T905A.05 40T905A.06 40T905A.07 40T905A.08 40T905A.09 40T905A.10 40T905A.11 40T905A.12 40T905A.13 40T905A.14 40T905A.15 40T905A.16 40T905A.17 40T905A.18 40T905A.19 40T905A.20 40T905A.21 40T905A.22 40T905A.23 RT For EP RT for Equitorail Petal & Bottom Polar Petal Top Polar Petal Welding RT for Top Polar Petal Top polar Petal-Equitorail Petal Welding RT for Equitorial-Top Polar Petal Erection & Welding of Top Crown With Nozzle Fitup & Welding of Internal Piping Fit up and Welding of Pads Erection & Welding of Bottom Crown Erection & Welding of Stairway structures Grouting Erection of Sway Rods FWS Erection & Welding Water Filling of Hydrotest Dewatering & Cleaning UT After Hydrotest Painting of sphere Cold Insulation Mechanical Completion Nitrogen Purging Cool Down operation Commisioning 3 3 17 3 9 3 4 2 15 4 8 4 5 7 6 5 5 8 20 1 3 2 1 0 0 0 3 0 3 4 2 15 4 8 4 5 7 6 5 5 8 20 1 0 0 0 100 02NOV09A 100 11NOV09A 100 11NOV09A 0 24NOV09 100 11NOV09A 0 27NOV09 0 30NOV09 0 04DEC09 0 04DEC09 0 19DEC09 0 23DEC09 0 31DEC09 0 25DEC09 0 25DEC09 0 01JAN10 0 07JAN10 0 12JAN10 0 17JAN10 0 25JAN10 0 14FEB10 100 100 100 04NOV09A 17NOV09A 23NOV09A 26NOV09 23NOV09A 29NOV09 03DEC09 05DEC09 18DEC09 22DEC09 30DEC09 03JAN10 29DEC09 31DEC09 06JAN10 11JAN10 16JAN10 24JAN10 13FEB10 14FEB10 02NOV09A 26OCT09A 24OCT09 15NOV09 11NOV09 23NOV09 26NOV09 30NOV09 24NOV09 02DEC09 19DEC09 27DEC09 25DEC09 25DEC09 01JAN10 07JAN10 12JAN10 17JAN10 25JAN10 14FEB10 04NOV09A 28OCT09 09NOV09 17NOV09 19NOV09 25NOV09 29NOV09 01DEC09 23DEC09 05DEC09 26DEC09 30DEC09 29DEC09 31DEC09 06JAN10 11JAN10 16JAN10 24JAN10 13FEB10 14FEB10 RT For EP RT for Equitorail Petal & Bottom Polar Petal Top Polar Petal Welding RT for Top Polar Petal Top polar Petal-Equitorail Petal Welding RT for Equitorial-Top Polar Petal Erection & Welding of Top Crown With Nozzle Fitup & Welding of Internal Piping Fit up and Welding of Pads Erection & Welding of Bottom Crown Erection & Welding of Stairway structures Grouting Erection of Sway Rods FWS Erection & Welding Water Filling of Hydrotest Dewatering & Cleaning UT After Hydrotest Painting of sphere Cold Insulation Mechanical Completion Nitrogen Purging Cool Down operation Commisioning

Start Date Finish Date Data Date Run Date

01OCT09 11MAR10 24NOV09 29NOV09 13:29

Early Bar Target Bar Progress Bar Critical Activity

GRSR

Sheet 8 of 9

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Rem % Dur Dur Comp

Early Start

Early Finish

Target 1 Target 1 Early Start Early Finish 3

2009 OCT NOV 10 17 24 31 7 14 21 28 5

DEC 12 19 26 2

2010 JAN FEB MAR 9 16 23 30 6 13 20 27 6 13 20 27

40-TP-905B ETHANE SPHERE


CONSTRUCTION & PROCUREMENT
40T905B.01 40T905B.02 40T905B.03 40T905B.04 40T905B.05 40T905B.06 40T905B.07 40T905B.08 40T905B.09 40T905B.10 40T905B.11 40T905B.12 40T905B.13 40T905B.14 40T905B.15 40T905B.16 40T905B.17 40T905B.18 40T905B.19 40T905B.20 40T905B.21 40T905B.22 40T905B.23 40T905B.25 RT For EP Bottom Polar -Equitorial petal Welding RT for BPP & EP to BPP Top Polar Petal Welding RT for Top Polar Petal Top polar Petal-Equitorail Petal Welding RT for Equitorial-Top Polar Petal Erection & Welding of Top Crown With Nozzle Fit up and Welding of Pads Fitup & Welding of Internal Piping Erection & Welding of Bottom Crown Erection & Welding of Stairway structures Erection of Sway Rods FWS Erection & Welding Grouting Water Filling of Hydrotest Dewatering & Cleaning UT After Hydrotest Painting of sphere Cold Insulation Mechanical Completion Nitrogen Purging Cool Down operation Commisioning 3 11 3 13 3 8 3 4 10 2 4 8 2 7 4 7 6 5 8 15 1 3 2 1 0 0 3 13 3 8 3 4 10 2 4 8 2 7 4 7 6 5 8 15 1 0 0 0 100 08NOV09A 100 31OCT09A 100 16NOV09A 80 04NOV09A 0 13DEC09 0 09DEC09 0 20DEC09 0 17DEC09 0 19DEC09 0 21DEC09 0 23DEC09 0 30DEC09 0 30DEC09 0 31DEC09 0 28DEC09 0 07JAN10 0 14JAN10 0 20JAN10 0 25JAN10 0 02FEB10 0 17FEB10 100 100 100 11NOV09A 10NOV09A 26NOV09 09DEC09 15DEC09 16DEC09 22DEC09 20DEC09 28DEC09 22DEC09 26DEC09 06JAN10 31DEC09 06JAN10 31DEC09 13JAN10 19JAN10 24JAN10 01FEB10 16FEB10 17FEB10 08NOV09A 31OCT09A 14NOV09 11NOV09 05DEC09 01DEC09 13DEC09 04NOV09 01DEC09 05DEC09 07DEC09 17NOV09 25NOV09 28NOV09 25DEC09 04JAN10 11JAN10 17JAN10 22JAN10 30JAN10 19FEB10 10NOV09 10NOV09A 16NOV09 29NOV09 07DEC09 09DEC09 15DEC09 03DEC09 04DEC09 06DEC09 10DEC09 24NOV09 26NOV09 04DEC09 28DEC09 10JAN10 16JAN10 21JAN10 29JAN10 18FEB10 19FEB10 Mechanical Completion Nitrogen Purging Cool Down operation Commisioning RT For EP Bottom Polar -Equitorial petal Welding RT for BPP & EP to BPP Top Polar Petal Welding RT for Top Polar Petal Top polar Petal-Equitorail Petal Welding RT for Equitorial-Top Polar Petal Erection & Welding of Top Crown With Nozzle Fit up and Welding of Pads Fitup & Welding of Internal Piping Erection & Welding of Bottom Crown Erection & Welding of Stairway structures Erection of Sway Rods FWS Erection & Welding Grouting Water Filling of Hydrotest Dewatering & Cleaning UT After Hydrotest Painting of sphere Cold Insulation

Start Date Finish Date Data Date Run Date

01OCT09 11MAR10 24NOV09 29NOV09 13:29

Early Bar Target Bar Progress Bar Critical Activity

GRSR

Sheet 9 of 9

Vijay Tanks & Vessels Balance Tank & Sphere Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.