0 SCHEDULE OF PRICES APPENDIX B


5.1 PRELIMINARIES AND GENERAL MATTERS PART II

ITEM DESCRIPTION UNIT AMOUNT


QR.

PRELIMINARIES

The following costs are for those preliminaries required


for the complete execution of the whole of the
CONTRACT SERVICES.

CONTRACT Particulars

For convenience, only those provisions considered to


have an obvious financial effect are set out below and
against each provision, the price is inserted for
compliance:

A Article 11.7 : Performance Bond Item

B Article 19 : Insurance Specific to the Contract Item

CONTRACTOR is deemed to have allowed for


compliance with the remainder of the provisions of the
General Conditions of Contract (which have a
preliminary financial impact). CONTRACTOR has
inserted below any other Article which, in his opinion,
attach a financial consideration, listing the Article
number, heading and the price of complying therewith
in the amount column.

C Article No. ……….......... Item

D Article No. ………………. Item

APPENDIX B.PART II/hs B/2/1 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.1 PRELIMINARIES AND GENERAL MATTERS PART II

To collection Page B/2/3 QR.

ITEM DESCRIPTION UNIT AMOUNT


QR.

GENERAL MATTERS

Mobilisation and Demobilisation

A Allow for mobilisation of all manpower and other


resources necessary for the proper execution of
SERVICES. Item

B Allow for maintenance of all manpower and other


resources necessary for the proper execution of
SERVICES Item

C Allow for de-mobilisation of all manpower and other


resources necessary for the proper execution of
SERVICES. Item

Generally

D Allow for progress meetings with QP during the course


of the CONTRACT. Item

E Allow for QA/QC Activities, Liaison with various parties


from QP, Government Authorities and OEM suppliers, Item
etc.

G Allow for compliance with CONTRACT terms and


conditions regarding obtaining entry permits, ID cards,
Safetywear, etc. Item

H Allow for compliance with the remainder of the


provisions under CONTRACT Terms and Conditions
and specifications. Item

Other costs deem required under this Section as listed


below

J ……………………………….. Item

APPENDIX B.PART II/hs B/2/2 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.1 PRELIMINARIES AND GENERAL MATTERS PART II

K ……………………………….. Item

To collection Page B/2/3 QR.

ITEM DESCRIPTION AMOUNT QR.

Collection

Total from Page B/2/1

Total from Page B/2/2

APPENDIX B.PART II/hs B/2/3 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.1 PRELIMINARIES AND GENERAL MATTERS PART II

Amount of Schedule 5.1 carried to Main Summary 5.3

APPENDIX B.PART II/hs B/2/4 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.2 SCOPE OF SERVICES PART II

ITEM DESCRIPTION UNIT AMOUNT Q.R

REPLACEMENT OF HOT OIL/CRUDE OIL HEAT


EXCHANGERS AT DUKHAN FIELD

A Retrieve, collate and verify all relevant documents Item


and existing information and data from QP and/or
other authorites.

B Carry out all necessary surveys, site investigation of item


existing facilities associated with the SERVICES
including preparing and submitting relevant Survey
Reports as required.

C Conduct Topographic Survey, Geographical Item


Investigation and Survey of Existing Facilities

D Prepare, submit and present commented/ approved Item


Design Base Memorandum

E Conduct HAZOP Study and submit HAZOP Study, Item


HAZOP Action, and HAZOP Close-Out Reports

F Provide Detailed Engineering Work Package Item


including Piping Isometrics and Material Take-Off for
piping tie-in works

G Conduct all required Design and Engineering Item


Services and produce all required Deliverables

H Prepare and submit Project Dossiers Item

J Prepare and submit EPIC Tender Package Item

K Prepare and submit EPIC Project Cost Estimate Item

L Prepare and submit EPIC Project Schedule Item

APPENDIX B.PART II/hs B/2/4 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.2 SCOPE OF SERVICES PART II

To collection Page B/2/6

ITEM DESCRIPTION UNIT AMOUNT Q.R

M Prepare and submit FEED Project Close-Out Report Item

N Comply with Quality Assurance/ Quality Control Item


Requirements and conduct Project Quality Audits as
per QC Plan

Other costs deem required as below (CONTRACTOR


to list): -

O …………………………………………….. Item

P …………………………………………….. Item

Q …………………………………………….. Item

APPENDIX B.PART II/hs B/2/5 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.2 SCOPE OF SERVICES PART II

To collection Page B/2/6

ITEM DESCRIPTION AMOUNT QR.

Collection

Total from Page B/2/4

Total from Page B/2/5

APPENDIX B.PART II/hs B/2/6 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.2 SCOPE OF SERVICES PART II

Amount of Schedule 5.2 carried to Main Summary 5.3

APPENDIX B.PART II/hs B/2/7 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.3 MAIN SUMMARY PART II

ITEM DESCRIPTION AMOUNT Q.R

A Sch. 5.1 Preliminaries and General Matters

B Sch. 5.2 Scope of SERVICES


Replacement of Hot Oil/Crude Oil Heat Exchangers at
Dukhan Field

TOTAL PRICE

Total PRICE in words, (Qatar Riyals ____________________________________

________________________________________________________________)

APPENDIX B.PART II/hs B/2/7 LTC 07/102


5.0 SCHEDULE OF PRICES APPENDIX B
5.3 MAIN SUMMARY PART II

carried to Form of Tender