You are on page 1of 4

SUG 250

UNIVERSITI TEKNOLOGI MARA (PERLIS)


INTRODUCTION TO HYDROGRAPHIC (SUG 250) Tutorial 4: 8 Hours

a) Figure 1 shows the information about chart datum as obtained during the survey. Table 1 shows the tide reading whereas Table 2 shows measured depth respectively. The Reduced Level at the top of tide pole is 3.742 m and chart datum is 0.441 m below MSL. Distinguish charted depth for each fix.

4m Sea water surface MS L CD


Figure 1

No

Time (HM) 11 55 12 00 12 05 12 10 12 15 12 20

1 2 3 4 5 6

Tide Reading (meters) Refer to Zero of Gauge 0.65 0.81 0.95 1.11 1.25 1.33

Fix 1 2 3 4 5 6 7 8 9 10

Table 1

Time Measured Depth (HMS) (meters) 12 00 00 9.9 12 02 10 8.3 12 03 40 8.05 12 05 00 8 12 07 20 7.35 12 08 50 7.3 12 10 10 7.2 12 12 10 5.6 12 14 20 4.3 12 15 00 3.5 Table 2

SUG 250 NOV 2011 MAC 2012, UiTM (Perlis)

SUG 250

UNIVERSITI TEKNOLOGI MARA (PERLIS)


INTRODUCTION TO HYDROGRAPHIC (SUG 250) Tutorial 4: 8 Hours

b) A hydrographic survey project for the purpose of producing bathymetric plan has been successfully carried out on 22 September 2009 at Penang Port. Information on the Chart Datum (CD) is shown in Figure 2. The Reduced Level at the top of staff is 3.125m and the chart datum is 0.905 meters below Mean Sea Level (MSL). Appendix 1 shows part of the depth information obtained. The survey time recorded for fix 1 is 0900 hours and for fix 10 is 0915 hours. Tides data are shown in Table 3. Referring to measured depth in Table 4, estimate all the measured depth to produce charted depth.

Staff mark 4m

Water surface MSL CD


Figure 2: Chart Datum Information

No 1 2 3 4 5 6

Time 0855 0900 0905 0910 0915 0920

Staff Reading (meters) 1.20 1.12 0.98 0.82 0.68 0.52 Table 3

Fix 1 2 3 4 5 6 7 8 9 10

Time 09 00 00 09 01 40 09 03 20 09 05 00 09 06 40 09 08 20 09 10 00 09 11 40 09 13 20 09 15 00
Table 4

Measured Depth 3.75 16.50 13.50 12.75 14.50 7.50 4.50 18.75 16.75 6.25

SUG 250 NOV 2011 MAC 2012, UiTM (Perlis)

SUG 250

UNIVERSITI TEKNOLOGI MARA (PERLIS)


INTRODUCTION TO HYDROGRAPHIC (SUG 250) Tutorial 4: 8 Hours

c) Figure 3 shows the information of a chart datum as obtained during the survey. Table 5 shows the tide reading whereas Table 6 shows measured depth respectively. The Reduced Level at the top of the tide pole is 3.945 m and chart datum is 0.504 m below Land Survey Datum (LSD). Distinguish charted depth for each fix
Table 5

No

Time (HM) 7 55 8 00 8 05 8 10 8 15

4m Sea water surface LSD CD


Figure 3 Table 6

1 2 3 4 5

Tide Reading (meters) Refer to Zero of Gauge 0.55 0.69 0.99 1.11 1.23

Fix 1 2 3 4 5 6 7

Time (HM) 8 00 00 8 01 00 8 03 20 8 05 00 8 06 50 8 10 00 8 11 30

Measured Depth (meters) 3.5 2.5 4.5 5.1 3.2 6.5 12.5

SUG 250 NOV 2011 MAC 2012, UiTM (Perlis)

SUG 250

UNIVERSITI TEKNOLOGI MARA (PERLIS)


INTRODUCTION TO HYDROGRAPHIC (SUG 250) Tutorial 4: 8 Hours

d) Estimate reduced depth for all fix based on measured depth in Table 1. Tidal observation method using tape and plumbob are shown in Figure 3 and tide data is in Table 2. (10 marks)
JETTY TBM 1.877m

WATER SURFACE

LSD

SEABED

Figure 3 Measured Depth Time Measured Fix Hour Minute Second Depth 3.41 1 8 0 0 6.44 2 8 6 10 2.44 3 8 13 50 2.66 4 8 20 30 1.4 5 8 30 0 Table 1 Tides Data Time No Hour Minute Tape Reading 1.31 1 7 55 1.41 2 8 0 1.51 3 8 10 1.69 4 8 20 1.8 5 8 30 Table 2

SUG 250 NOV 2011 MAC 2012, UiTM (Perlis)