ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

Task Name

Duration 135 days 8 days 1 day 3 days 3 days 4 days 42 days 1 day 14 days 3 days 8 days 14 days 14 days 14 days 7 days 7 days 7 days 70 days 45 days 9 days 21 days 36 days 23 days 2 days 6 days 36 days 5 days 6 days 14 days 7 days 2 days 8 days 37 days 6 days 18 days 11 days 12 days 2 days 3 days 25 days 3 days 4 days 8 days 8 days 11 days 2 days 9 days 39 days 6 days 14 days 13 days 11 days 2 days 9 days 27 days 6 days

Start Tue 18/10/11 Tue 18/10/11 Thu 20/10/11 Tue 18/10/11 Fri 21/10/11 Mon 24/10/11 Fri 21/10/11 Fri 21/10/11 Mon 24/10/11 Wed 02/11/11 Fri 21/10/11 Fri 21/10/11 Wed 09/11/11 Mon 28/11/11 Mon 31/10/11 Mon 31/10/11 Mon 31/10/11 Fri 04/11/11 Fri 04/11/11 Fri 04/11/11 Sun 06/11/11 Mon 07/11/11 Fri 04/11/11 Fri 23/12/11 Tue 27/12/11 Fri 04/11/11 Fri 04/11/11 Mon 07/11/11 Thu 10/11/11 Sun 06/11/11 Thu 08/12/11 Mon 12/12/11 Thu 17/11/11 Thu 17/11/11 Fri 18/11/11 Mon 12/12/11 Thu 17/11/11 Mon 02/01/12 Wed 04/01/12 Mon 19/12/11 Mon 19/12/11 Thu 22/12/11 Wed 28/12/11 Wed 28/12/11 Thu 22/12/11 Fri 06/01/12 Tue 10/01/12 Mon 21/11/11 Mon 21/11/11 Tue 22/11/11 Mon 12/12/11 Mon 21/11/11 Thu 29/12/11 Mon 02/01/12 Mon 26/12/11 Mon 26/12/11

ADANGA NORTH APLATFORM FABRICATION


MOBILIZATION Kick-off Meeting Pre-Mob Project Equipment Mobilization of test Crew (Hydrotest, NDT etc) Tests and Certification of Additional Welders

Prede Physical % Complete October B M Thu 19/04/12 0% Thu 27/10/11 Thu 20/10/11 Thu 20/10/11 Tue 25/10/11 3,4 Thu 27/10/11 3,5SS Thu 15/12/11 Fri 21/10/11 3 Wed 09/11/118 Fri 04/11/116 Tue 01/11/113 Tue 08/11/113 Fri 25/11/1112 Thu 15/12/11 13 Mon 07/11/11 Mon 07/11/114 Mon 07/11/1116SS Tue 07/02/12 Tue 03/01/12 Mon 14/11/1117SS Thu 01/12/11 20SS Fri 23/12/11 21SS Fri 02/12/11 20SS Mon 26/12/11 23 Tue 03/01/12 24 Wed 21/12/11 Wed 09/11/1110SS Sat 12/11/1127SS Mon 28/11/1128SS Sat 12/11/1127SS Fri 09/12/11 29,30 Wed 21/12/11 31 Fri 06/01/12 Thu 24/11/1110 Tue 13/12/11 34SS Mon 26/12/11 35SS Fri 02/12/11 34SS Tue 03/01/12 36 Fri 06/01/12 38 Fri 20/01/12 33SS Wed 21/12/11 10 Tue 27/12/11 41 Fri 06/01/12 42 Fri 06/01/12 43SS Thu 05/01/12 42SS Mon 09/01/12 45 Fri 20/01/12 46 Thu 12/01/12 Mon 28/11/1110 Fri 09/12/11 49SS Wed 28/12/11 50 Mon 05/12/11 49SS Fri 30/12/11 51 Thu 12/01/12 53,52 Tue 31/01/12 Mon 02/01/12 10 0% 100% 100% 100% 100% 0% 100% 50% 100% 90% 100% 37% 20% 0% 100% 100% 0% 0% 60% 60% 60% 60% 0% 0% 0% 100% 100% 100% 100% 100% 90% 0% 100% 100% 100% 100% 0% 0% 0% 30% 100% 0% 0% 25% 0% 0% 0% 100% 100% 0% 100% 0% 0% 0% 0%

Finish

November B M

December B M

January B M

February B M

March B

April B

M M E

Engineering & Project Documentation


Receive Client Drawing Prepare Shop drawings and prepare weld map Review Drawings for Constructibility Provide WPS /PQR and Qualify Welders Prepare & Issue Project Procedures and documentation to Addax Receive comments from Addax Finailse Project Procedures and documentation PROCUREMENT Procurement of additional Consumables Procurement of additional Safety equipment FABRICTION Hand Rails,Escape Ladder,Cages & walk way Cutting and edging Fit up and tack weld in position Weld in place Dimensional control Carry out NDT Blasting and Painting VALVE ACCESS PLATFORM Cutting and edging of main Beams/minor beams Fit ups and Tack-welding of main beams/Minor beams Welding of Main Beams/Minor beams Dimensional control of beams Carry out NDT Blasting and Painting of Structural frameworks LAUNCHER DECK Cutting and edging of main Beams/minor beams Fit ups and Tack-welding of main beams/Minor beams Welding of Main Beams/Minor beams Dimensional control of beams Carry out NDT on all welded structure Blasting and Painting of Structural frameworks DECK LEGS, DECK SUPPORTS AND BRACINGS Preparation of temporary construction aids Cutting and edging of deck legs Fit up and tack weld in position Weld in place Dimensional control Carry out NDT on all welded structure Blasting and Painting MAIN DECK Cutting and edging of main Beams/minor beams Fit ups and Tack-welding of main beams/minor beams Welding of Main Beams and Minor beams Dimensional control of beams Carry out NDT Blasting and Painting of Structural frameworks CAISSON INSTALLATION GUIDE FRAMES/stabbing guides/installatio Cutting and edging of Installation guide frame

12/01

Task Project: ADNA PROJECT EXECUTION Date: Thu 09/02/12 Split Milestone Summary

Project Summary External Tasks External Milestone Inactive Task

Inactive Milestone Inactive Summary Manual Task Duration-only Page 1

Manual Summary Rollup Manual Summary Start-only Finish-only

Progress Deadline

ID 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109

Task Name Fit ups and Tack-welding of Installation guide frame Welding of Installation guide frame Dimensional control of beams Carry out NDT Blasting and Painting of Installation guide frame BOAT LANDING LADDERS, ESCAPE LADDER Cutting and edging Fit up and tack weld in position Weld in in place Dimensional control of beams Carry out NDT Blasting and Painting of Installation guide frame BOAT LANDING Cutting and edging Fit up and tack weld in position Weld in in place Carry out NDT Install gratings Blasting & painting ANODE CLAMP Cutting and edging Rolling and machining of components (clamps, Hinge plates etc) Fitting & Tacking Assemble Clamps Install Padeye INTEGRATION OF DECK (ERECTION) Preparation of Deck integration Areas. Installation of deck grillages and deck temporary supports. Integration of Luncher deck on the legs Welding of Luncher deck on the legs Integration of main deck on the legs Welding of main deck on the legs Integration of the valve access platform on the legs Welding of the valve access platforms on the legs Installation of valve access supports and bracings NDE of all weldings INTEGRATION OF PIPES Installation of pipe Supports Installation of prefabricated piping spools Installation of equipments(Chemical Injection skid, test separators, instrume installation of Pig launcher and Pig receiver Installation of manifold Installation of instrumentatin lines Complete Painitng Touchups of the unit WEIGHING OF PLATFORM Touch up painting & clean up of fabrication area/Load Out Package loose fabricated items Prepare packing list/Load out Cleanup of Fabrication Area LOAD OUT Complete Preparation and company approval of load out design Final Loadout of Deck As build Documentation

Duration 9 days 11 days 10 days 2 days 7 days 30 days 2 days 4 days 5 days 6 days 1 day 4 days 32 days 4 days 7 days 9 days 1 day 2 days 4 days 14 days 3 days 4 days 3 days 4 days 2 days 38 days 2 days 3 days 4 days 6 days 5 days 6 days 2 days 5 days 6 days 3 days 39 days 9 days 18 days 12 days 3 days 2 days 9 days 9 days 4 days 24 days 8 days 7 days 4 days 25 days 8 days 4 days 10 days

Start Mon 26/12/11 Wed 04/01/12 Mon 26/12/11 Thu 19/01/12 Mon 23/01/12 Mon 26/12/11 Mon 26/12/11 Mon 26/12/11 Mon 23/01/12 Mon 26/12/11 Mon 30/01/12 Tue 31/01/12 Mon 26/12/11 Mon 26/12/11 Fri 30/12/11 Tue 10/01/12 Mon 23/01/12 Mon 06/02/12 Tue 24/01/12 Mon 26/12/11 Mon 26/12/11 Thu 29/12/11 Wed 04/01/12 Mon 09/01/12 Mon 09/01/12 Mon 09/01/12 Mon 23/01/12 Mon 23/01/12 Mon 09/01/12 Fri 13/01/12 Thu 26/01/12 Thu 02/02/12 Thu 02/02/12 Fri 10/02/12 Fri 17/02/12 Mon 27/02/12 Mon 27/02/12 Mon 27/02/12 Fri 09/03/12 Wed 04/04/12 Fri 09/03/12 Wed 04/04/12 Fri 09/03/12 Mon 26/03/12 Thu 22/03/12 Fri 09/03/12 Fri 09/03/12 Wed 21/03/12 Fri 06/04/12 Wed 14/03/12 Fri 30/03/12 Thu 12/04/12 Wed 14/03/12

Prede Physical % Complete October B M Thu 05/01/12 56SS 0% Wed 18/01/12 57SS 0% Fri 06/01/12 56SS 0% Fri 20/01/12 58 0% Tue 31/01/12 60 0% Fri 03/02/12 0% Tue 27/12/11 56SS 0% Thu 29/12/11 63SS 0% Fri 27/01/12 64,72 0% Mon 02/01/12 63SS 0% Mon 30/01/12 65 0% Fri 03/02/12 67 0% Tue 07/02/12 0% Thu 29/12/11 63SS 0% Mon 09/01/12 70 0% Fri 20/01/12 71 0% Mon 23/01/12 72 0% Tue 07/02/12 75,68 0% Fri 27/01/12 73 0% Thu 12/01/12 0% Wed 28/12/11 70SS 0% Tue 03/01/12 77 0% Fri 06/01/12 78 0% Thu 12/01/12 79 0% Tue 10/01/12 79 0% Wed 29/02/12 0% Tue 24/01/12 47 40% Wed 25/01/12 83SS 0% Thu 12/01/12 25,39 0% Fri 20/01/12 85 0% Wed 01/02/12 84,54 0% Thu 09/02/12 87 0% Fri 03/02/12 87 0% Thu 16/02/12 88,89 0% Fri 24/02/12 90 0% Wed 29/02/12 91,32 0% Thu 19/04/12 0% Thu 08/03/12 92SS 0% Tue 03/04/12 94 0% Thu 19/04/12 97,95 0% Tue 13/03/12 94SS 0% Thu 05/04/12 97,95 0% Wed 21/03/12 95SS 0% Thu 05/04/12 99,98 0% Tue 27/03/12 99 0% Wed 11/04/12 0% Tue 20/03/12 99SS 0% Thu 29/03/12 103 0% Wed 11/04/12 103,1 0% Tue 17/04/12 0% Tue 10/04/12 104 0% Tue 17/04/12 107,1 0% Tue 27/03/12 18SS 0%

Finish

November B M

December B M

January B M

February B M

March B

April B

M M E

Task Project: ADNA PROJECT EXECUTION Date: Thu 09/02/12 Split Milestone Summary

Project Summary External Tasks External Milestone Inactive Task

Inactive Milestone Inactive Summary Manual Task Duration-only Page 2

Manual Summary Rollup Manual Summary Start-only Finish-only

Progress Deadline