KARACHI METROPOLITAN CORPORATION

ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012 ROAD WORKS

1 of 161

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS UNIT R-1 Clearing and grubbing the site by cutting, uprooting and removing all rubbish and shrubs including disposal to (outside Sq.m. Municipal limits) designated places. R-2 Removal of trees 150mm to 300mm girth including disposal to No. (outside Municipal limits) designated places. R-3 Removal of trees 301mm to 600mm girth including disposal to No. (outside Municipal limits) designated places. R-4 Removal of trees 601mm or over girth including disposal to No. (outside Municipal limits) designated places. R-5 Dismantling of existing plain cement concrete including disposal Cu.m. of dismantled materials to designated places. R-6 Dismantling of existing reinforced cement concrete including separation of steel reinforcement, cleaning, straightening of steel and disposal of dismantled materials to designated places. Dismantling of existing asphalt concrete road including base, subbase and disposal of dismantled materials to designated places. R-8 Scarifying the existing road surface. R-9 Making diagonal grooves on existing asphalt surfaces as per Vol-II & III of special specification. R-10 Excavation in for road works in hard rock upto required depth and gradient including disposal of surplus / rejected excavated to designated places (outside Municipal limits). R-11 Excavation for road work in medium rock upto required depth and gradient including disposal of surplus / rejected excavated to designated places. (Outside Municipal limits) R-12 Excavation for road work in soft rock upto required depth and gradient including disposal of surplus / rejected excavated to designated places (outside Municipal limits). R-7 Cu.m. 1,682.45 RATE(Rs)

10.81 231.88 602.50 2,501.25 413.63

Cu.m. Sq.m. Sq.m.

236.93 12.03 30.08

Cu.m.

646.30

Cu.m.

453.80

Cu.m.

357.55

R-13 Excavation for road work in normal soil upto required depth and gradient including disposal of surplus / rejected excavated to Cu.m. designated places. (Outside Municipal limits) R-14 Excavation for road work in wet or silty soil required depth and gradient including disposal of surplus / rejected excavated to Cu.m. designated places. (Outside Municipal limits)

247.29

289.68

Approved.......................... 2 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS UNIT RATE(Rs) R-15 Preparation of sub-grade including cutting or filling to an average depth of 9", dressing to camber and consolidation with power roller for compaction 95% modified AASHTO density and achieving Sq.m. the design level. R-16 Dressing and levelling of roadway excavated material to designated section including compaction by sheep foot roller and power roller with optimum moisture content to 90% modified Sq.m. AASHTO density in layers not more than 6 inches (150mm). R-17 Providing, laying and compacting 300mm thick Granular Fill with Cu.m. material having CBR value > 15% at 95% modified AASHTO density. R-18 Providing and laying Granular Sub-Base course as per (AASHTO) standard specification including compacting to the required density by approved mechanical means (vibratory roller road packer and smooth wheel roller etc) i/c watering with all lead and Cu.m. lift etc complete paid as per VOL-II & III of specification. R-19 Providing and laying Aggregate base course CBR 80% as per (AASHTO) standard specification including compacting to the required density by approved mechanical means (vibratory roller road packer and smooth wheel roller etc) i/c watering with all lead and lift etc complete paid as per VOL-II & III of specifications. Cu.m. R-20 Providing & laying 4" thick compacted stone metal using 1-1/2" to 3/4" broken stone ballast approved grade and quality including Cu.m. watering, leveling and compacting to required density etc. R-21 Providing & laying stone soling 9" thick. including watering, leveling Cu.m. and compacting to required density etc. R-22 Providing & laying stone soling 12" thick. including watering, Cu.m. leveling and compacting to required density etc. R-23 Providing and spraying prime coat MC-70 cold applied BitushieldM as per VOL-II & III of special specification paid according to drums @ site or Bill of Lading Sprayed with Distributor Truck. 50% Rate will be reduce if Sprayed with Hand Operated Boiler Sq.m. 146.10 337.10 421.75 450.31 1,637.63 1,108.86 156.69

52.37

675.57

Approved.......................... 3 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS UNIT RATE(Rs) R-24 Providing and spraying tack coat MC-70 cold applied Bitushield-R as per VOL-II & III of special specification paid according to drums @ site or Bill of Lading. 20% Rate will be reduce if Sprayed with Sq.m. Hand Operated Boiler R-25 Providing and laying asphalt concrete binder course compacted

39.75

thickness 5 Cms (50mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be spread using paver machine. paid as per VOL-II & III pf specifications.
R-26 Providing and laying asphalt concrete binder course compacted Sq.m. 617.05

thickness 6 Cms (60mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be spread using paver machine. paid as per VOL-II & III of special specification.
R-27 Providing and laying asphalt concrete binder course compacted Sq.m. 715.23

thickness 7.5 Cms (75mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be spread using paver machine. paid as per VOL-II & III of special specification.
Sq.m. 862.51

Approved.......................... 4 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS UNIT RATE(Rs) R-28 Providing and laying asphalt concrete binder course compacted

thickness 10 Cms (100mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be spread using paver machine. paid as per VOL-II & III of special specification.
R-29 Providing and laying asphalt concrete wearing course compacted Sq.m. 1,143.53

thickness 5 Cms (50mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be spread using paver machine. paid as per VOL-II & III pf specifications.
R-30 Providing and laying asphalt concrete wearing course compacted Sq.m. 559.41

thickness 4 Cms (40mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be spread using paver machine. paid as per VOL-II & III pf specifications.
R-31 Providing and laying lean concrete having 1450 PSI cylindrical Sq.m. 472.75

strength (ready mixed concrete) including placing compacting, finishing, curing complete , screening and washing of crushed stone aggregate excluding the cost of shuttering.
Cu.m. 6,926.03

Approved.......................... 5 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS reinforced cement concrete 2250 PSI UNIT RATE(Rs) R-32 Providing and laying

cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, curing, compacting and finishing complete in all respect as shown on the drawings and as directed by the Engineer. (excluding the cost of steel reinforcement).
R-33 Providing and laying reinforced cement concrete having 2450 PSI Cu.m. 10,262.46

cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost of Cu.m. steel reinforcement). R-34 Providing and laying reinforced cement concrete having 3000 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost of Cu.m. steel reinforcement). R-35 Providing and laying reinforced cement concrete having 4000 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost of Cu.m. steel reinforcement). R-36 Providing and laying plain cement concrete 2250 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, curing, compacting and finishing complete in all respect as shown on the drawings and as directed by the Engineer.
R-37 Providing and laying plain cement concrete having 2450 PSI Cu.m.

10,461.20

10,925.16

11,587.66

10,191.82

cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer.
Cu.m. 10,390.56

Approved.......................... 6 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS UNIT RATE(Rs) R-38 Providing and laying plain cement concrete having 3000 PSI

cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer.
R-39 Providing and laying plain cement concrete having 4000 PSI Cu.m. 10,854.52

cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer.
R-40 Providing, cutting, bending and binding high tensile deformed billet Cu.m. 11,517.02

steel round bars (60,000 psi) conforming to ASTM 615 including the cost of binding wire, wastages, chairs, spacers block, hoisting and placing in position and such over laps as are not shown over the drawing, etc; at any level and any height complete in all respect as per drawings and instructions/ approval of the tonne Engineer. R-41 Providing, cutting, bending and binding high tensile tor steel bars (60,000 psi) conforming to ASTM 615 including the cost of binding wire, wastages, chairs, spacers block, hoisting and placing in position and such over laps as are not shown over the drawing, etc; at any level and any height complete in all respect as per drawings and instructions/ approval of the Engineer.As per general specification Vol-II and special specification Vol-III.
R-42 Providing and laying fairfaced reinforced cement concrete new jersey barrier having 3000 PSI compressive cylindrical strength Concrete (Ready mixed concrete) (area 3.50 Sft) as per drawing including the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength etc. complete in all respect. (Excluding the cost steel reinforcement) R.M. tonne

107,640.63

92,546.88

4,628.00

Approved.......................... 7 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS jersey barrier having 3000 PSI compressive cylindrical strength Concrete (Ready mixed concrete) (area 2.0 Sft) as per drawing including the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength etc. complete in all respect. (Excluding the cost steel reinforcement) R-44 Providing and laying fairfaced reinforced cement concrete new jersey barrier having 3000 PSI compressive cylindrical strength Concrete (Ready mixed concrete) (area 1.50 Sft) as per drawing including the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength etc. complete in all respect. R.M. (Excluding the cost steel reinforcement) R-45 Providing & fixing Precast Kerb Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x 18 inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean concrete, 2250 PSI concrete for haunching, 1:4 cement sand Sq.m. mortar etc Complete in all respect. R-46 Providing & fixing Precast Kerb Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x 18 inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean concrete, 2250 PSI concrete 6"x18" fill between two kerbs, laid in 1:4 cement sand mortar etc Complete in all respect. R-47 Providing & fixing Precast Edge Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x 12 inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean concrete, 2250 PSI concrete for haunching, 1:4 cement sand mortar etc Complete in all respect. R-48 Providing and fixing Reflectorized pavement studs (raised profile type single) aluminium. R-49 Providing & Fixing traffic sign boards (regulatory sign 3 feet dia.) R.M. 1,450.48 1,983.43 R.M. 2,644.57 UNIT RATE(Rs) R-43 Providing and laying fairfaced reinforced cement concrete new

1,253.75

R.M. No.

1,231.81 573.70

comprising 3" dia. G.I. pipe post, m.s. base plate, stiffeners, nuts, bolts, 16 gauge G.I. sheet, lean concrete, 3000 PSI concrete in foundations, excavation, enamel paint, retroreflective sheet diamond grade, lettering & signs complete in all respect as shown on the drawings and as directed by the Engineer.
No. 17,668.67

Approved.......................... 8 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS UNIT RATE(Rs) R-50 Providing & Fixing traffic sign boards (warning sign 3'x3'x3' triangle)

comprising 3" dia. G.I. pipe post, m.s.. base plate, stiffeners, nuts, bolts, 16 gauge G.I. sheet, lean concrete, 3000 PSI concrete in foundations, excavation, enamel paint, retroreflective sheet diamond grade, lettering & signs complete in all respect as shown on the drawings and as directed by the Engineer.
R-51 Providing and Fixing cement paving blocks flooring having size of 197x97 60(mm) of city / Quadra / cobble shape with pigmented having strength between 5000 psi to 8500 psi i/c filling the joints with hill sand and laying in specified manner / patter and design Sq.m. including 50mm thick sand bedding complete in all respect. R-52 Providing and Laying 2" Thick 3000 PSI (Ready Mixed) Cylindrical Strength cement concrete floor smooth finished including glass Sq.m. dividing strips laid in panels etc; complete in all respect. R-53 Providing and Laying 3" Thick 3000 PSI (Ready Mixed) Cylindrical Strength cement concrete floor smooth finished including glass Sq.m. dividing strips laid in panels etc; complete in all respect. R-54 Providing and Fixing Fair Face steel form work the formwork shall be made with 10 gauge steel plate and fixed at site with the help of steel and clamps on such a way that form will hold and resist the vibrating and pouring force and when form is open the concrete. The concrete surfaces shall be smooth and free from honey combing that no plaster and repair is required and Sq.m. compacted the job as per instruction. R-55 Bailing/ Dewatering and pumping out water Dewatering from Hour excavation. R-56 Providing and applying thermoplastic traffic marking paint (1.50mm thick) 422.92 454.30 951.50 738.61 1,145.16 No. 12,255.23

with drop of glass bead, cleaning of dust & dirt by mechanical means and all necessary arrangement for diversion of traffic complete in all respect as directed by the Engineer.
Sq.m. 1,023.25

Approved.......................... 9 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS UNIT RATE(Rs) R-57 Providing and applying chlorinated rubber traffic marking paint (DFT

100microns) including cleaning of dust & dirt by mechanical means and all necessary arrangement for diversion of traffic complete in all respect as directed by the Engineer.
R-58 Fixing Precast Kerb Block already stock at site including the cost of excavation, form Work for haunching, 450 PSI lean concrete, 2250 PSI concrete for haunching, 1:4 cement sand mortar etc Complete in all respect. R-59 Fixing paving blocks already stock at site including filling the joints with Sq.m. 446.25

R.M.

436.10

approved sand and laid in approved pattern and design including 50mm thick sand cushion/ bedding complete in all respect.
R-60 Removing of existing Precast Kerb Block any pattern, any thickness including stacking at suitable places all leads and lifts Complete in all respect as directed by the Engineer. R-61 Removing paving blocks including stacking at suitable place all lead and lifts Sq.m. 189.18

R.M. Sq.m.

39.99 215.20

complete in all respect as directed by the Engineer..


R-62 Providing & laying random rubble stone masonry dry, roughly hammer dressed stone, well bonded, faced with hammer dressed selected stone, Complete in all respect. R-63 Providing & laying random rubble stone masonry dry, roughly hammer dressed stone, well bonded, faced with hammer dressed selected stone, laid and jointed in 1:4 cement sand mortar Complete in all respect. R-64 Providing & laying stone masonry squared rubble, dressed, uncoursed dry, well bonded, faced with hammer dressed selected stone, Complete in all respect. R-65 Providing & laying stone masonry squared rubble, dressed, uncoursed, well bonded, faced with hammer dressed selected stone, laid and joint in 1:4 cement sand mortar Complete in all respect. R-66 Providing & laying roll pointing. Complete in all respect. R-67 Providing & laying stone masonry squared rubble, dressed, coursed, well bonded, faced with hammer dressed selected stone, laid and joint in 1:4 cement sand mortar Complete in all respect. R-68 Providing & laying Rip Rap Class "A" Comprising natural stone weighing 15 Kg. to 25Kg. complete in all respect.

Sq.m.

2,100.72

Cu.m.

3,205.77

Cu.m.

3,907.39

Cu.m. Sq.m.

4,521.48 267.04

Cu.m. Cu.m.

4,786.38 1,571.78

Approved.......................... 10 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

KARACHI METROPOLITAN CORPORATION


ENGINEERING DEPARTMENT

SCHEDULE OF RATES -2012

ROAD WORKS
S/NO. DESCRIPTION OF WORKS UNIT RATE(Rs) 1,909.54 2,163.41 R-69 Providing & laying Rip Rap Class "B" Comprising natural stone Cu.m. weighing 30 Kg. to 70Kg. complete in all respect. R-70 Providing & laying Rip Rap Class "C" Comprising natural stone Cu.m. weighing 60 Kg. to 100Kg. complete in all respect.

Approved.......................... 11 of 161
DIRECTOR GENERAL TECHNICAL SERVICES

RATE ANALYSES FOR ROAD WORKS


STATION:DATED:NAME OF WORK :Karachi 09-01-2012 Karachi Metropolitan Corporation Schedule of Rates -2012

" BASIC MATERIALS PRICES "


S.N 1 2 3 4 5 6 7 8 9

DESCRIPTION
CEMENT (O P) including Cartage CEMENT (S.R.) including Cartage MORUM SAND (Coarse) SAND (Fine) CRUSH ( Hub) STONE METAL STONE METAL more than 6" STONE DUST

UNIT
BAG BAG CFT CFT CFT CFT CFT CFT CFT CFT CFT CFT CFT CFT CFT GALLONS TONNE TONNE

RATE
395.00 407.00 10.00 22.00 20.99 27.97 20.00 18.00 20.00 20.00 60.00 22.00 25.00 30.00 16.00 0.50 73,500.00 62,000.00

10 RANDOM STONE 11 DRESSED STONE 12 STONE FOR RIP RAP CLASS "A" (15KG~25kG) 13 STONE FOR RIP RAP CLASS "B" (30KG~70kG) 14 STONE FOR RIP RAP CLASS "C" (60KG~100kG) 15 SUBBASE MATERIAL 16 WATER 17 DEFORMED STEEL GRADE- 60(Above 3/8"dia) 18 TOR STEEL GRADE- 60(Above 3/8"dia)

Approved.......................... Page 12 of 161


DIRECTOR GENERAL TECHNICAL SERVICES

RATE ANALYSES FOR ROAD WORKS


STATION:DATED:NAME OF WORK :Karachi 09-01-2012 Karachi Metropolitan Corporation Schedule of Rates -2012

19 BINDING WIRE

" BASIC MATERIALS PRICES "

KG TONNE CFT KG KG KG SFT. CFT. CFT. CFT. CFT. CFT. No. No. RFT. RFT. NO. SFT. SFT. KG. KG.

115.00 92,000.00 15.00 85.65 88.92 70.00 490.00 135.90 150.05 154.30 164.21 178.37 175.00 170.00 167.23 271.06 350.00 56.69 62.73 100.00 95.00

20 STRUCTURAL STEEL 21 GRANULAR FILL MATERIAL 22 BITUMEN MC-70 ( FOR PRIME COAT ) 23 BITUMEN RS-1 ( FOR TACK COAT ) 24 BITUMEN 60/70 GRADE 25 RETROREFLECTING SHEET DIAMOND GRADE 26 READY MIXED CONCRETE 1450 PSI CYLINDRICAL STRENGTH 27 READY MIXED CONCRETE 2250 PSI CYLINDRICAL STRENGTH 28 READY MIXED CONCRETE 2450 PSI CYLINDRICAL STRENGTH 29 READY MIXED CONCRETE 3000 PSI CYLINDRICAL STRENGTH 30 READY MIXED CONCRETE 4000 PSI CYLINDRICAL STRENGTH 31 KERBSTONE 6"X12"18" (Envicrete) 32 EDGESTONE 6"X12"12" (Envicrete) 33 G.I. PIPE 2" DIAMETER (medium) 34 G.I. PIPE 3" DIAMETER (medium) 35 BOLTS 12MM DIA. 300MM LONG 36 PAVING STONE 60MM COLOURED 37 PAVING STONE 80MM GREY 38 M.S. SHEET 16SWG 39 M.S. SHEET 10SWG

Approved.......................... Page 13 of 161


DIRECTOR GENERAL TECHNICAL SERVICES

RATE ANALYSES FOR ROAD WORKS


STATION:DATED:NAME OF WORK :Karachi 09-01-2012 Karachi Metropolitan Corporation Schedule of Rates -2012

40 THERMOPLASTIC PAINT (POWDER) 25 KG.BAG " BASIC MATERIALS 41 GLASS BEADS 25 KG.BAG 42 CHLORINATED RUBBER PAINT 20 LITRES PACK 43 THINNER

PRICES "

KG KG LITRES LITRES

165.00 86.50 425.00 215.00

Approved.......................... Page 14 of 161


DIRECTOR GENERAL TECHNICAL SERVICES

RATE ANALYSES FOR ROAD WORKS


STATION:DATED:NAME OF WORK :Karachi 09-01-2012 Karachi Metropolitan Corporation Schedule of Rates -2012

" BASIC MATERIALS PRICES " "LABOUR RATES"


DESCRIPTION UNIT RATE

S.N

1
2

SKILLED WORKER UNSKILLED WORKER

Hours Hours

93.75 56.25

Approved.......................... Page 15 of 161


DIRECTOR GENERAL TECHNICAL SERVICES

RATE ANALYSES FOR ROAD WORKS


STATION:DATED:NAME OF WORK :Karachi 09-01-2012 Karachi Metropolitan Corporation Schedule of Rates -2012

"HIRE CHARGES RATES OF EQUIPMENT / MACHINERY"


S.N
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

" BASIC MATERIALS PRICES "


DESCRIPTION

UNIT
Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Sft. Sft. Hours Hours

RATE
530.00 2,000.00 1,500.00 434.00 2,000.00 1,313.00 1,600.00 2,500.00 1,500.00 650.00 625.00 3,850.00 325.00 625.00 45.00 400.00 160.00 39.31 20.00 212.00 600.00

Tractor (50HP Capacity) including fuel & Driver Motorgrader (140 HP) including fuel & Driver Steel Wheel Roller (Combination roller 10-12 ton) including fuel & Driver Water Bouzer (Truck mounted Capacity 10,000 litres) including fuel & Driver Front Loader (1.50 Cu.m.) including fuel & Driver Dumper ( 10 ton capacity) including fuel & Driver Batching plant 80 tons/hr capacity Paver finisheer including fuel & operatior Pneumatic tyred roller (PTR) (18 ton) including fuel & operator Asphalt Spraying truck (500 litres) including fuel & operator Compressor (300 CFM) including operator Bulldozer (CAT D-7) including fuel & operator Rock Driller inlcuding operator Power Broom (2.1 M wide) including operator Paint Spray Machine including operatior Mixer Machine 0.25 M3 including fuel & operator Vibrator including fuel & operator Steel formwork Wooden formwork Plate compactor including fuel & operator Road Marking machine including operator

Approved.......................... Page 16 of 161


DIRECTOR GENERAL TECHNICAL SERVICES

RATE ANALYSES FOR ROAD WORKS


STATION:DATED:NAME OF WORK :Karachi 09-01-2012 Karachi Metropolitan Corporation Schedule of Rates -2012 Hours Hours Hours

22 23 24

Jack Hammer HP-100 (Tyre type) including operator Tire Excavator Mobile Crane 10 Ton including operator

" BASIC MATERIALS PRICES "

2,100.00 1,800.00 1,491.54

Approved.......................... Page 17 of 161


DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 18

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-1 UNIT: Sq.m. DESCRIPTION:Clearing and grubbing the site by cutting, uprooting and removing all rubbish and shrubs including disposal to (outside Muncipal limits) designated places.

Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Tractor including fuel & driver Loader including fuel & driver Dumper including driver & fuel Total of "B" 2250 Sq.m. or 24210 Sft.

Unit

No.

Quantity

Rate

Hours Hours

1 8

8.00 8.00

93.75 56.25

Hours Hours Hours

2 1 1

8.00 2.00 2.00

530.0 2000.0 1313.0

Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m. 25 % 24210 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 19

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-2 UNIT: No. DESCRIPTION:Removal trees 150mm to 300mm girth including disposal to (outside Muncipal limits) designated places.

Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Tractor including fuel & driver Misc. rope, wire etc. Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Number 10 Nos.

Unit

No.

Quantity

Rate

Hours Hours

1 4

4.00 4.00

93.75 56.25

Hours LS

1.00

530.0

25 % 10 Nos.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 20

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-3 UNIT: No. DESCRIPTION:Removal trees 301mm to 600mm girth including disposal to (outside Muncipal limits) designated places.

Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Tractor including fuel & driver Misc. rope, wire etc. Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Number 10 Nos.

Unit

No.

Quantity

Rate

Hours Hours

1 4

8.00 8.00

93.75 56.25

Hours LS

4.00

530.0

25 % 10 Nos.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 21

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-4 UNIT: No. DESCRIPTION:Removal trees 601mm or over girth including disposal to (outside Muncipal limits) designated places.

Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Tractor including fuel & driver Misc. rope, wire etc. Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Number 10 Nos.

Unit

No.

Quantity

Rate

Hours Hours

1 4

8.00 8.00

93.75 56.25

Hours LS

16.00

530.0

25 % 10 Nos.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 22

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-5 UNIT: Cu.m. DESCRIPTION:Dismantling of existing plain cement concrete including disposal of dismantled materials to designated places. Detail Detail for 100 Cu.m. Unit No. Quantity Rate

A. LABOUR Un-skilled Workers Skilled Workers Total of "B" Hours Hours 4 4 8.0 8.0 93.75 56.25

B. TOOLS & PLANTS Tractor including fuel & operator Loader 2.5 m3 including fuel & operator Dumper including fuel & operator Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.m. 25 % 100 Cu.m. Hours Hours Hours 1 2 2 3.37 4.00 4.00 530.0 2000.0 1313.0

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 23

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-6 UNIT: Cu.m. DESCRIPTION:Dismantling of existing reinforced cement concrete including separation of steel reinforcement, cleaning, straightening of steel and disposal of dismantled materials to designated places. Detail Detail for 100 Cu.m. Unit No. Quantity Rate

A. LABOUR Un-skilled Workers Skilled Workers Total of "B" Hours Hours 8 8 8.0 8.0 93.75 56.25

B. TOOLS & PLANTS Bulldozer including fuel & operator Rock Driller including operator Jack Hammer including operator Loader 2.5 m3 including fuel & operator Dumper including fuel & operator Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.m. 25 % 100 Cu.m. Hours Hours Hours Hours Hours 2 2 2 2 2 8.00 5.07 8.00 4.00 4.00 3850.00 325.00 2100.00 2000.00 1313.00

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 24

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-7 UNIT: Cu.m. DESCRIPTION:Dismantling of existing asphalt concrete road including base, subbase and disposal of dismantled materials to designated places. Detail Detail for 100 Cu.m. or 3532.1 Cft. Unit No. Quantity Rate

A. LABOUR Un-skilled Workers Skilled Workers Total of "B" Hours Hours 1 1 8.0 8.0 56.25 93.75

B. TOOLS & PLANTS Shovel Loader 2.5 m3 including fuel & operator Dumper including fuel & operator Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m. 25 % 3532.1 Cft. Hours Hours 1 2 4.00 4.00 2000.00 1313.00

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 25

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-8 UNIT: Sq.m. DESCRIPTION:Scarifying/Tucking the existing asphalt concrete surface by pick axe with 10 tucks per square meter of not more than 20mm depth including removing the debris, cleaning and disposal of materials to designated places as directed by the Engineer. Detail Detail for 100 Sq.m. or 1076 Sft. Unit No. Quantity Rate

A. LABOUR Un-skilled Workers Total of "A" Hours 2 8.0 56.25

B. TOOLS & PLANTS Power broom including fuel & operator Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m. 25 % 1076 Sft. Hours 1 0.10 625.00

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 26

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-9 UNIT: Sq.m. DESCRIPTION:Making diagonal grooves on existing asphalt surfaces as per Vol-II & III of special specification. Detail Detail for 100 Sq.m. or 1076 Sft. Unit No. Quantity Rate

A. LABOUR Un-skilled Workers Total of "A" Hours 2 4.0 56.25

B. TOOLS & PLANTS Excavator including fuel & operator Power broom including fuel & operator Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m. 25 % 1076 Sft. Hours Hours 1 1 1.00 0.25 1800.00 625.00

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 27

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-10 UNIT: Cu.m. Excavation in for road works in hard rock upto required depth and gradient including disposal of surplus / rejected excavated to designated places (outside Municipal limits). Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Bulldozer including fuel & driver Loader including fuel & driver Dumper including driver & fuel Total of "B" Hours Hours Hours 1 1 2 8.00 4.00 4.00 3850.0 2000.0 1313.0 Hours Hours 2 2 8.00 8.00 93.75 56.25 100 Cu.m. or 3532 Cft. Unit No. Quantity Rate DESCRIPTION:-

Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m. 25 % 3532.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 28

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-11 UNIT: Cu.m. Excavation for road work in medium rock upto required depth and gradient including disposal of surplus / rejected excavated to designated places. (Outside Municipal limits) Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Bulldozer including fuel & driver Loader including fuel & driver Dumper including driver & fuel Total of "B" Hours Hours Hours 1 1 2 4.00 4.00 4.00 3850.0 2000.0 1313.0 Hours Hours 2 2 8.00 8.00 93.75 56.25 100 Cu.m. or 3532 Cft. Unit No. Quantity Rate DESCRIPTION:-

Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m. 25 % 3532.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 29

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-12 UNIT: Cu.m. Excavation for road work in soft rock upto required depth and gradient including disposal of surplus / rejected excavated to designated places (outside Municipal limits). Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Bulldozer including fuel & driver Loader including fuel & driver Dumper including driver & fuel Total of "B" Hours Hours Hours 1 1 2 2.00 4.00 4.00 3850.0 2000.0 1313.0 Hours Hours 2 2 8.00 8.00 93.75 56.25 100 Cu.m. or 3532 Cft. Unit No. Quantity Rate DESCRIPTION:-

Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m. 25 % 3532.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 30

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-13 UNIT: Cu.m. Excavation for road work in normal soil upto required depth and gradient including disposal of surplus / rejected excavated to designated places. (Outside Municipal limits) Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Tractor including fuel & driver Loader including fuel & driver Dumper including driver & fuel Total of "B" Hours Hours Hours 1 1 2 0.15 4.00 4.00 530.0 2000.0 1313.0 Hours Hours 1 1 8.00 8.00 93.75 56.25 100 Cu.m. or 3532 Cft. Unit No. Quantity Rate DESCRIPTION:-

Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m. 25 % 3532.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 31

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-14 UNIT: Cu.m. Excavation for road work in wet or silty soil required depth and gradient including disposal of surplus / rejected excavated to designated places. (Outside Municipal limits) Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Tractor including fuel & driver Loader including fuel & driver Dumper including driver & fuel Total of "B" Hours Hours Hours 1 1 2 4.00 4.00 4.00 530.0 2000.0 1313.0 Hours Hours 1 4 8.00 8.00 93.75 56.25 100 Cu.m. or 3532 Cft. Unit No. Quantity Rate DESCRIPTION:-

Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m. 25 % 3532.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 32

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-15 UNIT: Sq.m. DESCRIPTION:Preparation of sub-grade including cutting or filling to an average depth of 9", dressing to camber and consolidation with power roller for compaction 95% modified AASHTO density and achieving the design level. Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Motorgrader (140 HP) including fuel & Driver Steel Wheel Roller (10-12 ton) including fuel & Driver Water Bouzer (Truck mounted Capacity 10,000 litres) including fuel & Driver Total of "B" Hours Hours Hours 1 2 2 8.00 8.00 4.00 2000.0 1500.0 434.0 Hours Hours 1 1 8.00 8.00 93.75 56.25 3500 Sq.m. or 37660 Sft. Unit No. Quantity Rate

Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m. 25 % 37660 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 33

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-16 UNIT: Cu.m. DESCRIPTION:Dressing and levelling of roadway excavated material to designated section including compaction by sheep foot roller and power roller with optimum moisture content or 90% modified AASHTO density in layers not more than 6 inches (150mm). Detail Detail for A. LABOUR Skilled worker unskilled worker Total of "A" B. TOOLS AND PLANTS Motorgrader (140 HP) including fuel & Driver Bulldozer including fuel & driver Steel Wheel Roller (10-12 ton) including fuel & Driver Sheep footl Roller including fuel & Driver Water Bouzer (Truck mounted Capacity 10,000 litres) including fuel & Driver Total of "B" Hours Hours Hours Hours Hours 1 2 2 2 2 8.00 8.00 8.00 8.00 4.00 2000.0 3850.0 1500.0 1500.0 434.0 Hours Hours 1 4 8.00 8.00 93.75 56.25 1050 Cu.m. or 37087.05 Cft. Unit No. Quantity Rate

Basic Cost "A+B" Add Contractor's overhead & Profit Rate for one Cu.ft. Rate for one Cu.m. 25 % Total Cost for 37087.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 34

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-17 UNIT: Cu.m. DESCRIPTION:-

Providing, laying and compacting 300mm thick improved sub-grade fill with material having CBR value > 15% at 95% modified AASHTO density. Detail Unit 3532 Cft. No. Quantity Rate

Detail for A. MATERIAL Morum Add for compaction

100 Cu.m. or

Cft. 25 % Total of "A"

3532.10

10.00

B. LABOUR Skilled worker unskilled worker Total of "B" C. TOOLS AND PLANTS Tractor including fuel & driver Roller including fuel & driver Water bouzer including fuel & driver Total of "C"

Hours Hours

2 2

8.00 8.00

93.75 56.25

Hours Hours Hours

1 1 1

2.00 4.00 1.00

530.0 1500.0 434.0

Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m.

25 % 3532.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 35

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-18 UNIT: Cu.m. DESCRIPTION:-

Providing and laying Granular Sub-Base course as per (AASHTO) standard specification including compacting to the required density by approved mechanical means (vibratory roller road packer and smooth wheel roller etc) i/c watering with all lead and lift etc complete paid as per VOL-II & III of specification. Detail Unit 3532 Cft. No. Quantity Rate

Detail for

100 Cu.m. or

A. MATERIAL Subbase material Extra for compaction 25 % Water optimum moisture content 8% Total of "A" B. LABOUR Skilled worker unskilled worker Total of "B" C. TOOLS AND PLANTS Tractor including fuel & driver Motor grader including fuel & driver Roller including fuel & driver Water bouzer including fuel & driver Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m.

Cft. Gallon

3532 3387

16.00 0.50

Hours Hours

2 2

8.00 8.00

93.75 56.25

Hours Hours Hours Hours

1 1 1 1

4.00 1.00 6.00 2.00

530.0 2000.0 1500.0 434.0

25 % 3532.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 36

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-19 UNIT: Cu.m. DESCRIPTION:-

Providing and laying Aggregate base course CBR 80% as per (AASHTO) standard specification including compacting to the required density by approved mechanical means (vibratory roller road packer and smooth wheel roller etc) i/c watering with all lead and lift etc complete paid as per VOL-II & III of specifications. Detail 100 Cu.m. or Unit 3532 Cft. No. Quantity Rate

Detail for

A. MATERIAL Crushed stone 60 % Stone dust 40 % Extra for compaction 25 % Water optimum moisture content 8% Total of "A" B. LABOUR Skilled worker unskilled worker Total of "B" C. TOOLS AND PLANTS Loader including fuel & driver Dumper including driver & fuel Motor grader including fuel & driver Roller including fuel & driver Water bouzer including fuel & driver Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m.

Cft. Cft. Gallon

2119 1413 3387

27.97 20.00 0.50

Hours Hours

2 2

8.00 8.00

93.75 56.25

Hours Hours Hours Hours Hours

1 1 1 1 1

2.00 2.00 2.00 4.00 2.00

2000.0 1313.0 2000.0 1500.0 434.0

25 % 3532.1 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 37

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-20 UNIT: Sq.m. DESCRIPTION:-

Providing & laying 4" thick compacted stone metal using 1-1/2" to 3/4" broken stone ballast approved grade and quality including watering, leveling and compacting to required density etc.

Detail for A. MATERIAL Stone metal Stone dust Water

Detail 100 Sq.m. or

Unit 1076 Sft.

No.

Quantity

Rate

16.6 % Sft.

Cft. Cft. Gallons Total of "A"

355.08 178.62 500.00

20.00 20.00 0.50

B. LABOUR Skilled worker unskilled worker Total of "B" C. TOOLS AND PLANTS Tractor including fuel & operator Roller including fuel & driver Water bouzer including fuel & driver Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours

1 4

8.00 8.00

93.75 56.25

Hours Hours Hours

1 1 1

2.00 8.00 1.00

530.0 1500.0 434.0

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 38

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-21 UNIT: Cu.m. DESCRIPTION:-

Providing & laying stone soling 9" thick. including watering, leveling and compacting to required density etc. Detail 10 Cu.m. or Unit 353 Cft. No. Quantity Rate

Detail for A. MATERIAL Stone Wastage Water

Cft. 10 % Gallons Total of "A"

353.21 500.00

18.00 0.50

B. LABOUR Skilled worker unskilled worker Total of "B" C. TOOLS AND PLANTS Compactor including fuel & operator Water bouzer including fuel & driver Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m.

Hours Hours

1 4

8.00 8.00

93.75 56.25

Hours Hours

1 1

4.00 1.00

212.0 434.00

25 % 353.21 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 39

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-22 UNIT: Cu.m. DESCRIPTION:-

Providing & laying stone soling 12" thick. including watering, leveling and compacting to required density etc. Detail 10 Cu.m. or Unit 353 Cft. No. Quantity Rate

Detail for A. MATERIAL Stone wastage Water

Cft. 10 % Sft. Gallons Total of "A"

353.21 500.00

18.00 0.50

B. LABOUR Skilled worker unskilled worker Total of "B" C. TOOLS AND PLANTS Compactor including fuel & operator Water bouzer including fuel & driver Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Cu.ft. Rate for one Cu.m.

Hours Hours

2 4

8.00 8.00

93.75 56.25

Hours Hours

1 1

4.00 1.00

212.0 434.00

25 % 353.21 Cft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 40

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-23 UNIT: Sq.m. DESCRIPTION:-

Providing and spraying prime coat MC-70 cold applied Bitushield-M as per VOL-II & III of special specification paid according to drums @ site or Bill of Lading Sprayed with Distributor Truck. 30% Rate will be reduce if Sprayed with Hand Operated Boiler Detail 100 Sq.m. or 1076 Sft. 11 litres / 100 sft. Unit No. Quantity Rate

Detail for Spreading ratio A. MATERIAL


Prime coat @ of 1076
Sft.

11 litres / 100 sft.


x
11

118.36

Medium curing cut back for prime coat (MC-70)

Litres Wastage B. LABOUR Skilled Workers Un-skilled Workers Total of "B" C. TOOLS & PLANTS
Asphalt spraying truck (500 litres capacity)

118.36

85.65

5% Total of "A" Hours Hours 1 2 1.0 1.0 93.75 56.25

Compressor including operator Power broom including fuel & operator Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours Hours

1.00 1.00 1.00

1.00 0.15 0.15

650.00 625.00 625.00

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 41

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-24 UNIT: Sq.m. DESCRIPTION:-

Providing and spraying tack coat MC-70 cold applied Bitushield-R as per VOL-II & III of special specification paid according to drums @ site or Bill of Lading. 30% Rate will be reduce if Sprayed with Hand Operated Boiler Detail 100 Sq.m. or 1076 Sft. 1.4 litres / 100 sft. Unit No. Quantity Rate

Detail for Spreading ratio A. MATERIAL


Tack coat @ of 1076
Sft.

1.40 litres/ 100 Sft. x


1

15.064

Medium curing cut back for tack coat (RS-1)

Litres Wastage B. LABOUR Skilled Workers Un-skilled Workers Total of "B" C. TOOLS & PLANTS
Asphalt spraying truck (500 litres capacity)

15.06

88.92

10.0 % Total of "A" Hours Hours 1 3 1.0 2.0 93.75 56.25

Compressor including operator Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours

1 1

1.00 1.00

650.00 625.00

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 42

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-25 UNIT: Sq.m. DESCRIPTION:-

Providing and laying asphalt concrete binder course compacted thickness 5 Cms (50mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be spread using paver machine. paid as per VOL-II & III pf specifications.

Detail Detail for 100 Sq.m. or 1076 Sft. Density of asphalt concrete considered Weight of asphalt concrete Qty. of asphalt concrete 5 Cu.m. or A. MATERIAL Asphalt concrete Asphalt 60/70 grade 3.5 % Fine aggregate 42 % M3 3 Coarse aggregate 49.5 % M3 4 Filler material 4.0 % M3 0.35 Wastage 5.0 % B. LABOUR Skilled Workers Un-skilled Workers

Unit

No.

Quantity 70.78

Rate

2500 Kg./Cu.m. or 12500 Kgs. 176.61 Cft.

12500.00 12500.00 12500.00 12500.00 Total of "A"

Kg. Cft. Cft. Cft.

438 119 140 12.25

70.00 22.00 27.97 20.00

Hours Hours Total of "B"

1 4

4.0 4.0

93.75 56.25

C. TOOLS & PLANTS Batching plant 1600tons/hr capacity with operator Dump Trucks 10tons capacity with driver & fuel Paver finisher with operator & fuel Steel Wheel roller with operator & fuel Pneumatic tyred roller with operator & fuel Water Bouzer with water, driver & fuel Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours Hours Hours Hours Hours

1 2 1 1 1 1

0.8 0.8 0.8 1.0 1.0 1.0

1600.0 1313.00 2500.0 1500.00 1500.00 434.00

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 43

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-26 UNIT: Sq.m. DESCRIPTION:-

Providing and laying asphalt concrete binder course compacted thickness 6 Cms (60mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be spread using paver machine. paid as per VOL-II & III of special specification.

Detail Detail for 100 Sq.m. or 1076 Sft. Density of asphalt concrete considered Weight of asphalt concrete Qty. of asphalt concrete 6 Cu.m. or A. MATERIAL Asphalt concrete Asphalt 60/70 grade 3.5 % Fine aggregate 42 % M3 4 Coarse aggregate 49.5 % M3 5 Filler material 4.0 % M3 0.42 Wastage 5.0 % B. LABOUR Skilled Workers Un-skilled Workers

Unit

No.

Quantity

Rate

2500 Kg./Cu.m. or 15000 Kgs. 211.93 Cft.

70.78 kg./Cft.

15000.00 15000.00 15000.00 15000.00 Total of "A"

Kg. Cft. Cft. Cft.

525 143 168 14.70

70.00 22.00 27.97 20.00

Hours Hours Total of "B"

1 4

4.0 4.0

93.75 56.25

C. TOOLS & PLANTS Batching plant 1600tons/hr capacity with operator Dump Trucks 10tons capacity with driver & fuel Paver finisher with operator & fuel Steel Wheel roller with operator & fuel Pneumatic tyre roller with operator & fuel Water Bouzer with water, driver & fuel Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours Hours Hours Hours Hours

1 2 1 1 1 1

0.8 0.8 0.8 1.0 1.0 1.0

1600.0 1313.00 2500.0 1500.00 1500.00 434.00

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 44

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-27 UNIT: Sq.m. DESCRIPTION:-

Providing and laying asphalt concrete binder course compacted thickness 7.5 Cms (75mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be spread using paver machine. paid as per VOL-II & III of special specification.

Detail Detail for 100 Sq.m. or 1076 Sft. Density of asphalt concrete considered Weight of asphalt concrete Qty. of asphalt concrete 7.5 Cu.m. or A. MATERIAL Asphalt concrete Asphalt 60/70 grade 3.5 % Fine aggregate 42 % M3 5 Coarse aggregate 49.5 % M3 6 Filler material 4.0 % M3 0.52 Wastage 5.0 % B. LABOUR Skilled Workers Un-skilled Workers

Unit

No.

Quantity

Rate

2500 Kg./Cu.m. or 18750 Kgs. 264.91 Cft.

70.78 kg./Cft.

18750.00 18750.00 18750.00 18750.00 Total of "A"

Kg. Cft. Cft. Cft.

656 178 210 18.37

70.00 22.00 27.97 20.00

Hours Hours Total of "B"

1 4

4.0 4.0

93.75 56.25

C. TOOLS & PLANTS Batching plant 1600tons/hr capacity with operator Dump Trucks 10tons capacity with driver & fuel Paver finisher with operator & fuel Steel Wheel roller with operator & fuel Pneumatic tyre roller with operator & fuel Water Bouzer with water, driver & fuel Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours Hours Hours Hours Hours

1 2 1 1 1 1

0.8 0.8 0.8 1.0 1.0 1.0

1600.0 1313.00 2500.0 1500.00 1500.00 434.00

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 45

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-28 UNIT: Sq.m. DESCRIPTION:-

Providing and laying asphalt concrete binder course compacted thickness 10 Cms (100mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be spread using paver machine. paid as per VOL-II & III of special specification.

Detail Detail for 100 Sq.m. or 1076 Sft. Density of asphalt concrete considered Weight of asphalt concrete Qty. of asphalt concrete 10 Cu.m. or A. MATERIAL Asphalt concrete Asphalt 60/70 grade 3.5 % Fine aggregate 42 % M3 7 Coarse aggregate 49.5 % M3 8 Filler material 4.0 % M3 0.69 Wastage 5.0 % B. LABOUR Skilled Workers Un-skilled Workers

Unit

No.

Quantity

Rate

2500 Kg./Cu.m. or 25000 Kgs. 353.21 Cft.

70.78 kg./Cft.

25000.00 25000.00 25000.00 25000.00 Total of "A"

Kg. Cft. Cft. Cft.

875 238 280 24.49

70.00 22.00 27.97 20.00

Hours Hours Total of "B"

1 4

4.0 4.0

93.75 56.25

C. TOOLS & PLANTS Batching plant 1600tons/hr capacity with operator Dump Trucks 10tons capacity with driver & fuel Paver finisher with operator & fuel Steel Wheel roller with operator & fuel Pneumatic tyre roller with operator & fuel Water Bouzer with water, driver & fuel Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours Hours Hours Hours Hours

1 2 1 1 1 1

1.0 1.0 1.0 1.5 1.5 1.0

1600.0 1313.00 2500.0 1500.00 1500.00 434.00

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 46

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-29 UNIT: Sq.m. DESCRIPTION:-

Providing and laying asphalt concrete wearing course compacted thickness 5 Cms (50mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be spread using paver machine. paid as per VOL-II & III pf specifications.

Detail Detail for 100 Sq.m. or 1076 Sft. Density of asphalt concrete considered Weight of asphalt concrete Qty. of asphalt concrete 5 Cu.m. or A. MATERIAL Asphalt concrete Asphalt 60/70 grade 3% Fine aggregate 50 % M3 4 Coarse aggregate 43 % M3 3 Filler material 4 % M3 0.35 Wastage 5% B. LABOUR Skilled Workers Un-skilled Workers

Unit

No.

Quantity 70.78

Rate

2500 Kg./Cu.m. or 12500 Kgs. 176.61 Cft.

12500.00 12500.00 12500.00 12500.00 Total of "A"

Kg. Cft. Cft. Cft.

375 142 122 12.25

70.00 22.00 27.97 20.00

Hours Hours Total of "B"

1 4

4.0 4.0

93.75 56.25

C. TOOLS & PLANTS Batching plant 1600tons/hr capacity with operator Dump Trucks 10tons capacity with driver & fuel Paver finisher with operator & fuel Steel Wheel roller with operator & fuel Pneumatic tyred roller with operator & fuel Water Bouzer with water, driver & fuel Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours Hours Hours Hours Hours

1 2 1 1 1 1

0.8 0.8 0.8 1.0 1.0 1.0

1600.0 1313.00 2500.0 1500.00 1500.00 434.00

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 47

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-30 UNIT: Sq.m. DESCRIPTION:-

Providing and laying asphalt concrete wearing course compacted thickness 4 Cms (40mm thick) as per approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of grade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. The procedure of laying binder course material & methodology shall fully comply with AASHTO and as directed by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be spread using paver machine. paid as per VOL-II & III pf specifications.

Detail Detail for 100 Sq.m. or 1076 Sft. Density of asphalt concrete considered Weight of asphalt concrete Qty. of asphalt concrete 4 Cu.m. or A. MATERIAL Asphalt concrete Asphalt 60/70 grade 3% Fine aggregate 50 % M3 3 Coarse aggregate 43 % M3 3 Filler material 4 % M3 0.28 Wastage 5% B. LABOUR Skilled Workers Un-skilled Workers

Unit

No.

Quantity 70.78

Rate

2500 Kg./Cu.m. or 10000 Kgs. 141.28 Cft.

10000.00 10000.00 10000.00 10000.00 Total of "A"

Kg. Cft. Cft. Cft.

300 113 97 9.80

70.00 22.00 27.97 20.00

Hours Hours Total of "B"

1 4

4.0 4.0

93.75 56.25

C. TOOLS & PLANTS Batching plant 1600tons/hr capacity with operator Dump Trucks 10tons capacity with driver & fuel Paver finisher with operator & fuel Steel Wheel roller with operator & fuel Pneumatic tyred roller with operator & fuel Water Bouzer with water, driver & fuel Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours Hours Hours Hours Hours

1 2 1 1 1 1

0.8 0.8 0.8 1.0 1.0 1.0

1600.0 1313.00 2500.0 1500.00 1500.00 434.00

25 % 1076 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 48

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-31 UNIT: Cu.m. DESCRIPTION:-

Providing and laying lean concrete having 1450 PSI cylindrical strength (ready mixed concrete) including placing compacting, finishing, curing complete , screening and washing of crushed stone aggregate excluding the cost of shuttering. Detail 100 Cft. or Unit 2.83 Cu.m. No. Quantity Rate

Detail for

A. MATERIAL Ready mixed concrete 1450 PSI Wastage 5% Water charges 1% Total of "A" B. LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

135.9

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft.

100.00

11.3

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 49

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-32 UNIT: Cu.m. DESCRIPTION:-

Providing and laying reinforced cement concrete 2250 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, curing, compacting and finishing complete in all respect as shown on the drawings and as directed by the Engineer. (excluding the cost of steel reinforcement). Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for

100 Cft.

or

A. MATERIAL Ready mixed concrete 2250 PSI Wastage 5% Water charges 1% Total of "A" B.LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Vibrator including fuel & operator Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

150.05

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft. Hours

100.00 1.00

11.3 160.0

Sft.

150.00

39.31

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 50

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-33 UNIT: Cu.m. DESCRIPTION:-

Providing and laying reinforced cement concrete having 2450 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost of steel reinforcement). Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for

100 Cft.

or

A. MATERIAL Ready mixed concrete 2450 PSI Wastage 5% Water charges 1% Total of "A" B.LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Vibrator including fuel & operator Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

154.3

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft. Hours

100.00 1.00

11.3 160.0

Sft.

150.00

39.31

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 51

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-34 UNIT: Cu.m. DESCRIPTION:-

Providing and laying reinforced cement concrete having 3000 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost of steel reinforcement). Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for

100 Cft.

or

A. MATERIAL Ready mixed concrete 3000 PSI Wastage 5% Water charges 1% Total of "A" B. LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Vibrator including fuel & operator Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

164.2

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft. Hours

100.00 1.00

11.3 160.0

Sft.

150.00

39.31

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 52

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-35 UNIT: Cu.m. DESCRIPTION:-

Providing and laying reinforced cement concrete having 4000 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost of steel reinforcement). Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for

100 Cft.

or

A. MATERIAL Ready mixed concrete 4000 PSI Wastage 5% Water charges 1% Total of "A" B. LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Vibrator including fuel & operator Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

178.4

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft. Hours

100.00 1.00

11.3 160.0

Sft.

150.00

39.31

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 53

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-36 UNIT: Cu.m. DESCRIPTION:-

Providing and laying plain cement concrete 2250 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, curing, compacting and finishing complete in all respect as shown on the drawings and as directed by the Engineer. Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for

100 Cft.

or

A. MATERIAL Ready mixed concrete 2250 PSI Wastage 5% Water charges 1% Total of "A" B.LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

150.05

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft.

100.00

11.3

Sft.

150.00

39.31

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 54

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-37 UNIT: Cu.m. DESCRIPTION:-

Providing and laying plain cement concrete having 2450 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer.

Detail Detail for 100 Cft. or 2.83 Cu.m.

Unit

No.

Quantity

Rate

A. MATERIAL Ready mixed concrete 2450 PSI Wastage 5% Water charges 1% Total of "A" B.LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

154.3

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft.

100.00

11.3

Sft.

150.00

39.31

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 55

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-38 UNIT: Cu.m. DESCRIPTION:-

Providing and laying plain cement concrete having 3000 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer. Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for

100 Cft.

or

A. MATERIAL Ready mixed concrete 3000 PSI Wastage 5% Water charges 1% Total of "A" B. LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

164.2

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft.

100.00

11.3

Sft.

150.00

39.31

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 56

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-39 UNIT: Cu.m. DESCRIPTION:-

Providing and laying plain cement concrete having 4000 PSI cylindrical strength (ready mixed concrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing complete in all respect as shown on the drawings and as directed by the Engineer. Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for

100 Cft.

or

A. MATERIAL Ready mixed concrete 4000 PSI Wastage 5% Water charges 1% Total of "A" B. LABOUR Coolies for placing of concrete Mason Total of "B" C. TOOLS AND PLANTS Concrete pump Total of "C" D. FORMWORK P/F & removing steel formwork. Total of "D"

Cft.

100.00

178.4

Hours Hours

1 1

1.00 1.00

56.3 93.8

Cft.

100.00

11.3

Sft.

150.00

39.31

Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft. Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 57

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-40 UNIT: tonne DESCRIPTION:Providing, cutting, bending and binding high tensile deformed billet steel round bars (60,000 psi) conforming to ASTM 615 including the cost of binding wire, wastages, chairs, spacers block, hoisting and placing in position and such over laps as are not shown over the drawing, etc; at any level and any height complete in all respect as per drawings and instructions/ approval of the Engineer. Detail Detail for A. MATERIAL Steel bars Binding wire @ Wastage
Chairs, spacer block etc. Cartage & handling

Unit

No.

Quantity

Rate

1 tonne

10 Kg./tonne 5%

tonne Kg.

1.00 10.00

73500.0 115.0

Total of "A" B.LABOUR Skilled worker Coolies Total of "B" C. TOOLS AND PLANTS Cutting machine Bending machine Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one tonne

Hours Hours

4 8

8.00 8.00

93.8 56.3

Hours Hours

1 1

1.00 1.00

75.0 55.0

25 % 1 tonne

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 58

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-41 UNIT: tonne DESCRIPTION:-

Providing, cutting, bending and binding high tensile tor steel bars (60,000 psi) conforming to ASTM 615 including the cost of binding wire, wastages, chairs, spacers block, hoisting and placing in position and such over laps as are not shown over the drawing, etc; at any level and any height complete in all respect as per drawings and instructions/ approval of the Engineer.As per general specification Vol-II and special specification Vol-III. Detail Unit No. Quantity Rate

Detail for A. MATERIAL Steel bars Binding wire @ Wastage

1 tonne

10 Kg./tonne 5%

tonne Kg.

1.00 10.00

62000.0 115.0

Chairs, spacer block etc. Cartage & handling

Total of "A" B.LABOUR Skilled worker Coolies Total of "B" C. TOOLS AND PLANTS Cutting machine Bending machine Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one tonne

Hours Hours

4 8

8.00 8.00

93.8 56.3

Hours Hours

1 1

1.00 1.00

75.0 55.0

25 % 1 tonne

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 59

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-42 UNIT: Running meter DESCRIPTION:Providing and laying fairfaced reinforced cement concrete new jersey barrier having 3000 PSI compressive cylindrical strength Concrete (Ready mixed concrete) (area 3.50 Sft) as per drawing including the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength etc. complete in all respect. (Excluding the cost steel reinforcement) Detail Detail for Size 10 Rft.
3.05

Unit M
Volume of concrete for 1M Volume of concrete for 3.05 M

No.

Quantity
10.24 Cft. 31.22 Cft.

Rate

0.29 m3 or 0.88 m3 or

Bottom width =500mm, (1'-8") Top width= 100mm (4"), Height= 950mm ( 3'-2") A. MATERIAL Ready mixed concrete 1450 PSI concrete 0.21 m3 or 7.541 Cft. (ratio 1:3:6) Cft. 7.54 3000 PSI concrete Cft. 31.22 Wastage 5 % Total of "A" B.LABOUR Coolies for excavation & placing of concrete Hours 4 1.00 Mason for levelling of concrete Hours 2 1.00 Total of "B" C. TOOLS AND PLANTS Vibrator incl.fuel & driver Hours 1 1.00 Concrete pump Cft. 1 38.76 Crane 10 Ton including operator Hours 1 0.50 Total of "C" D. FORMWORKS Providing,fixing & removing steel formwork Sft. 1 78.05 @ 2.5Sft./Cft. Total of "D" Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 10 Rft. Rate for one Rft. (for section area 3.50 Sft.) Rate for one RM.

135.90 164.21

56.25 93.75

160.00 11.32 1491.54

39.31

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 60

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-43 UNIT: Running meter DESCRIPTION:Providing and laying fairfaced reinforced cement concrete new jersey barrier having 3000 PSI compressive cylindrical strength Concrete (Ready mixed concrete) (area 2.0 Sft) as per drawing including the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength etc. complete in all respect. (Excluding the cost steel reinforcement) Detail Detail for Size 10 Rft.
3.05

Unit M
Volume of concrete for 1M Volume of concrete for 3.05 M

No.

Quantity
10.24 Cft. 31.22 Cft.

Rate

0.29 m3 or 0.88 m3 or

Bottom width =500mm, (1'-8") Top width= 100mm (4"), Height= 950mm ( 3'-2") 5.28 A. MATERIAL Ready mixed concrete 1450 PSI concrete 0.21 m3 or 7.541 Cft. (ratio 1:3:6) Cft. 7.54 3000 PSI concrete Cft. 31.22 Wastage 5 % Total of "A" B.LABOUR Coolies for excavation & placing of concrete Hours 4 1.00 Mason for levelling of concrete Hours 2 1.00 Total of "B" C. TOOLS AND PLANTS Vibrator incl.fuel & driver Hours 1 1.00 Concrete pump Cft. 1 38.76 Crane 10 Ton including operator Hours 1 0.50 Total of "C" D. FORMWORKS Providing,fixing & removing steel formwork Sft. 1 78.05 @ 2.5Sft./Cft. Total of "D" Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 10 Rft. Rate for one Rft. (for section area 3.50 Sft.) Rate for one Rft. (for section area 1 Sft.) Rate for one Rft. (for section area 2 Sft.) Rate for one RM.

135.90 164.21

56.25 93.75

160.00 11.32 1491.54

39.31

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 61

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-44 UNIT: Running metre DESCRIPTION:Providing and laying fairfaced reinforced cement concrete new jersey barrier having 3000 PSI compressive cylindrical strength Concrete (Ready mixed concrete) (area 1.50 Sft) as per drawing including the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength etc. complete in all respect. (Excluding the cost steel reinforcement) Detail Detail for Size 10 Rft.
3.05

Unit M
Volume of concrete for 1M Volume of concrete for 3.05 M

No.

Quantity
10.24 Cft. 31.22 Cft.

Rate

0.29 m3 or 0.88 m3 or

Bottom width =500mm, (1'-8") Top width= 100mm (4"), Height= 950mm ( 3'-2") 5.28 A. MATERIAL Ready mixed concrete 1450 PSI concrete 0.21 m3 or 7.541 Cft. (ratio 1:3:6) Cft. 7.54 3000 PSI concrete Cft. 31.22 Wastage 5 % Total of "A" B.LABOUR Coolies for excavation & placing of concrete Hours 4 1.00 Mason for levelling of concrete Hours 2 1.00 Total of "B" C. TOOLS AND PLANTS Vibrator incl.fuel & driver Hours 1 1.00 Concrete pump Cft. 1 38.76 Crane 10 Ton including operator Hours 1 0.50 Total of "C" D. FORMWORKS Providing,fixing & removing steel formwork Sft. 1 78.05 @ 2.5Sft./Cft. Total of "D" Basic Cost "A+B+C+D" Add Contractor's overhead & Profit 25 % Total Cost for 10 Rft. Rate for one Rft. (for section area 3.50 Sft.) Rate for one Rft. (for section area 1 Sft.) Rate for one Rft. (for section area 1.50 Sft.) Rate for one RM.

135.90 164.21

56.25 93.75

160.00 11.32 1491.54

39.31

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 62

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-45 UNIT: Running metre DESCRIPTION:Providing & fixing Precast Kerb Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x 18 inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean concrete, 2250 PSI concrete for haunching, 1:4 cement sand mortar etc Complete in all respect. Detail 100 Rft. or 30 Metres Unit No. Quantity Rate

Detail for A. MATERIAL Kerbstone No. Cartage No. Cement mortar (1:4) in base 3 Cft. Cement Bags Sand Cft. 1450 PSI concrete (lean) 49.50 Cft. (ratio 1:3:6) Cement Bags Sand Cft. Crushed stone Cft. 2250 PSI concrete for haunching 10.90 Cft. (ratio 1:2:4) Cement Bags Sand Cft. Crushed stone Cft. Wastage 5 % Water charges 2 % Total of "A" B.LABOUR Skilled worker Hours 2 Unskilled worker Hours 2 Coolies for excavation Hours 1 Total of "B" C. FORMWORKS Providing, fixing & removing formwork (ordinary) Sft. 1 Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Rft. Rate for one Rft. Rate for one RM.

100.00 100.00 0.71 3.53 5.82 21.83 43.66 1.83 4.58 9.16

175.00 11.00 395.00 22.00 395.00 22.00 27.97 395.00 22.00 27.97

8.00 8.00 8.00

93.75 56.25 56.25

100.00

20.00

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 63

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-46 UNIT: Running metre DESCRIPTION:Providing & fixing Precast Kerb Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x 18 inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean concrete, 2250 PSI concrete 6"x18" fill beweeen two kerbs, laid in 1:4 cement sand mortar etc Complete in all respect. Detail for 100 Rft. Detail or 30 Metres Unit No. Quantity Rate

A. MATERIAL Kerbstone No. Cartage No. Cement mortar (1:4) in base 3 Cft. Cement Bags Sand Cft. 1450 PSI concrete (lean) 49.50 Cft. (ratio 1:3:6) Cement Bags Sand Cft. Crushed stone Cft. 2250 PSI concrete fill between kerbs 75.00 Cft. (ratio 1:2:4) Cement Bags Sand Cft. Crushed stone Cft. Wastage 5 % Water charges 2 % Total of "A" B.LABOUR Skilled worker Hours Unskilled worker Hours Coolies for excavation Hours Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Rft. Rate for one RM.

100.00 100.00 0.71 3.53 5.82 21.83 43.66 12.60 31.50 63.00

175.00 11.00 395.00 22.00 395.00 22.00 27.97 395.00 22.00 27.97

2 2 1

8.00 8.00 8.00

93.75 56.25 56.25

25 % 100 Rft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 64

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-47 UNIT: Running metre DESCRIPTION:Providing & fixing Precast Edge Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x 12 inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean concrete, 2250 PSI concrete for haunching, 1:4 cement sand mortar etc Complete in all respect. Detail 100 Rft. or 30 Metres Unit No. Quantity Rate

Detail for A. MATERIAL Kerbstone No. Cartage No. Cement mortar (1:4) in base 3 Cft. Cement Bags Sand Cft. 1450 PSI concrete (lean) 49.50 Cft. (ratio 1:3:6) Cement Bags Sand Cft. Crushed stone Cft. 2250 PSI concrete for haunching 10.90 Cft. (ratio 1:2:4) Cement Bags Sand Cft. Crushed stone Cft. Wastage 5 % Water charges 2 % Total of "A" B.LABOUR Skilled worker Hours 2 Unskilled worker Hours 2 Coolies for excavation Hours 1 Total of "B" C. FORMWORKS Providing, fixing & removing formwork (ordinary) Sft. 1 Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Rft. Rate for one Rft. Rate for one RM.

100.00 100.00 0.71 3.53 5.82 21.83 43.66 1.83 4.58 9.16

170.00 11.00 395.00 22.00 395.00 22.00 27.97 395.00 22.00 27.97

8.00 8.00 8.00

93.75 56.25 56.25

100.00

20.00

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 65

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-48 UNIT: No. DESCRIPTION:Detail for 100 No.

Reflectorized pavement studs (raised profile type single) aluminium. Detail Unit No. Quantity

Rate

A. MATERIAL
Road studs raised profile type single (aluminium) Cement sand

Cartage Total of "A" B. LABOUR Skilled Workers Un-skilled Workers Total of "B"

No. Bag. Cft. LS

100.00 1.00 0.05

385.00 395.00 22.00

Hours Hours

1 3

8.0 8.0

93.75 56.25

C. TOOLS & PLANTS


Compressor 300cfm

Rock driller Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for

Hours Hours

1 1

5.00 5.00

625.00 325.00

25 % 100 No.

Rate for one No.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 66

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-49 UNIT: No. DESCRIPTION:-

Providing & Fixing traffic sign boards (regulatory sign 3 feet dia.) comprising 3" dia. G.I. pipe post, m.s. base plate, stiffeners, nuts, bolts, 16 guage G.I. sheet, lean concrete, 3000 PSI concrete in foundations, excavation, enamel paint, retroreflective sheet diamond grade, lettering & signs complete in all respect as shown on the drawings and as directed by the Engineer. Detail 5 Signs Unit No. Quantity Rate

Detail for A. MATERIAL G.I. pipe Post 3" dia. (medium duty) 20mm (3/4") thick base plate (350x350mm) 8mm thick stiffener plate Bolts 12mm dia. 300mm long G.I.Sheet sign board 16 guage CC 1:4:8 lean concrete CC 1:2:4 (3000 PSI) concrete Providing and applying enamel paint. Providing retroreflecting sheet diamond grade 3M Providing base sheet border & letting Cartage of materials Wastage 5 % Total of "A" B.LABOUR Skilled worker Unskilled worker Fabrication & erection of pipe post & sign etc. Fixing of reflective sheet Total of "B" C. FORMWORKS Providing, fixing & removing formwork @ 2Sft./Cft. Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for

Rft. tonne tonne No. Kg. Cft. Cft. Sft. Sft. Sft. LS

34.45 0.096 0.006 20.000 50.870 3.580 18.000 53.160 43.580 13.074

271.06 92000.0 92000.0 350.0 100.0 71.5 100.3 30.0 490.0 490.0

Hours Hours Kg. Sft.

1 4

8.00 8.00 50.972 56.654

93.75 56.25 25.0 25.0

Sft.

36.00

20.00

25 % 5 Signs

Rate for one Regulatory Sign (3'' dia.)

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 67

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-50 UNIT: No. DESCRIPTION:-

Providing & Fixing traffic sign boards (warning sign 3'x3'x3' triangle) comprising 3" dia. G.I. pipe post, m.s.. base plate, stiffeners, nuts, bolts, 16 guage G.I. sheet, lean concrete, 3000 PSI concrete in foundations, excavation, enamel paint, retroreflective sheet diamond grade, lettering & signs complete in all respect as shown on the drawings and as directed by the Engineer. Detail 5 Signs Unit No. Quantity Rate

Detail for A. MATERIAL G.I. pipe Post 3" dia. (medium duty) 20mm (3/4") thick base plate (350x350mm) 8mm thick stiffener plate Bolts 12mm dia. 300mm long G.I.Sheet sign board 16 guage CC 1:4:8 lean concrete CC 1:2:4 (3000 PSI) concrete Providing and applying enamel paint. Providing retroreflecting sheet diamond grade 3M Providing base sheet border & letting Cartage of materials Wastage 5 % Total of "A" B.LABOUR Skilled worker Unskilled worker Fabrication & erection of pipe post & sign etc. Fixing of reflective sheet Total of "B" C. FORMWORKS Providing, fixing & removing formwork @ 2Sft./Cft. Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for

Rft. tonne tonne No. Kg. Cft. Cft. Sft. Sft. Sft. LS

34.45 0.096 0.006 20.000 33.910 3.580 18.000 53.160 14.530 4.359

271.06 92000.0 92000.0 350.0 100.0 71.5 100.3 30.0 490.0 490.0

Hours Hours Kg. Sft.

1 4

8.00 8.00 34.012 18.889

93.75 56.25 25.0 25.0

Sft.

36.00

20.00

25 % 5 Signs

Rate for one Warning Sign (3'x3'x3') triangle

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 68

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-51 UNIT: Sq.m. DESCRIPTION:-

Providing and Fixing cement paving blocks flooring having size of 197x97 60(mm) of city / Quadra / cobble shape with pigmented having strength between 5000 psi to 8500 psi including filling the joints with approved sand and laid in approved pattern and design including 50mm thick sand cushion/ bedding complete in all respect. Detail Unit No. Quantity Rate 100 Sft.

Detail for

A. MATERIAL Paving stone 60mm thick pigmented Cartage Sand cushion 50mm (2") thick Wastage 5 % Total of "A" B.LABOUR Skilled worker Unskilled worker Total of "B" C. TOOLS AND PLANTS Plate Compactor including operator Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Sft. Sft. Cft.

100.00 100.00 16.00

56.69 11.00 22.00

Hours Hours

1 2

4.00 4.00

93.75 56.25

Hours

1.00

212.00

25 % 100 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 69

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-52 UNIT: Sq.m. DESCRIPTION:-

Providing and Laying 2" Thick 3000 PSI (Ready Mixed) Cylindrical Strength cement concrete floor smooth finished including glass dividing strips laid in panels etc; complete in all respect. 100 Sft. Detail or 16 Cft. Unit No. Quantity Rate

Detail for

A. MATERIAL 3000 PSI ready mixed concrete Glass dividing strips Wastage 5 % Water charges 2 % Total of "A" B.LABOUR Skilled worker Unskilled worker Coolies for curing Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Cft. Rft.

16.00 10.00

164.21 5.00

Hours Hours Hours

2 2 1

8.00 8.00 4.00

93.75 56.25 56.25

25 % 100 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 70

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-53 UNIT: Sq.m. DESCRIPTION:-

Providing and Laying 3" Thick 3000 PSI (Ready Mixed) Cylindrical Strength cement concrete floor smooth finished including glass dividing strips laid in panels etc; complete in all respect. Detail 100 Sft. or 25 Cft. Unit No. Quantity Rate

Detail for

A. MATERIAL 3000 PSI ready mixed concrete Glass dividing strips Wastage 5 % Water charges 2 % Total of "A" B.LABOUR Skilled worker Unskilled worker Coolies for curing Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Cft. Rft.

25.00 10.00

164.21 5.00

Hours Hours Hours

2 2 1

8.00 8.00 4.00

93.75 56.25 56.25

25 % 100 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 71

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-54 UNIT: Sq.m. DESCRIPTION:-

Providing and Fixing Fair Face steel form work the form shall be made with 10 gauge steel plate and fixed at site with the help of steel and clamps on such a way that form will hold and resist the vibrating and pouring force and when form is open the concrete. The concrete surfaces shall be smooth and free from honey combing that no plaster and repair is required and compacted the job as per instruction. Detail Unit 9.29 Sq.m. No. Quantity Rate

Detail for A. MATERIAL A-1 Steel plates Steel plates 10 guage density taken Add for bracking etc. less salvaged value

100 Sft.

or

3.15 mm thick 7850 kg./Cu.m. 10 % Total 252.79 Kg.

Kg. Kg. Kg.

229.81 22.98 -252.79

95.00 95.00 25.00

Total after deduction of salvaged value Considering repetitions 40 times Total of "A-1" A-2 Scaffolding pipes, joints, runner etc. LS Total of "A-2" Total of "A" B.LABOUR Skilled worker Unskilled worker Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours

1 1

8.00 8.00

93.75 56.25

25 % 100 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 72

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-55 UNIT: Per Hour DESCRIPTION:Detail for A. MATERIAL Pipes Add Misc. Cartage B.LABOUR
For Excavation Phase Pumping set operators (12 hoursx 30 days)=360 For construction Phase Pumping set operators (24 hoursx 30 days)=720 Skilled worker for fixing pumps & piping Unskilled work for fixing pumps & piping

Bailing/ Dewatering and pumping out water Dewatering from excavation. Detail Unit No. Quantity 1440.00 Hours R.M. 20 % for fittings 120.00

Rate

550.0

Total of "A"

Hours Hours Hours Hours Total of "B"

1 1 2 2

360.00 720.00 16.00 16.00

93.8 93.8 93.8 56.3

C. TOOLS AND PLANTS


Working pumps Pumping set 30 Cu.m./hour Pumping set 60 Cu.m./hour Standby pumps Pumping set 30 Cu.m./hour Pumping set 60 Cu.m./hour Less salvage value -25% Repair & maintenance 25 % No. No. No. No. 1 1 1 1 1 25000.00 1 30000.00 1 25000.00 1 30000.00

Total of "C"
D. PUMP FUEL CONSUMPTION consumption @ 1 litre/ hour For Excavation Phase 12 hours for 30 days 2 pumps 12 hours For Construction Phase 24 hours for 30 days 2 pumps 24 hours Total consumption Litres 2160 100.00

30 days 30 days

720 litres 1440 litres 2160 Litres

Total of "D" Basic Cost "A+B+C+D" Add Contractor's overhead & Profit Total Cost for Rate for one Hour

25 % 1440 Hours

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 73

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-56 UNIT: Sq.m. DESCRIPTION:-

Providing and applying thermoplastic traffic marking paint (1.50mm thick) with drop of glass bead, cleaning of dust & dirt by mechanical means and all neceesary arrangement for diversion of traffic complete in all respect as directed by the Engineer. Detail Unit 375 No. Quantity Rate 100 Sft.

Detail for A. MATERIAL Thermoplastic paint coverage Glass beads Wastage Cartage B.LABOUR Skilled worker Unskilled worker

Kg. 4.00 Kg./Sq.m. (1.5mm thick) 250 gms/Sq.m. 5 % Total of "A" Hours Hours Total of "B" 1 1 Kg.

37.17 2.32

165.00 86.50

1.00 1.00

93.75 56.25

C. TOOLS & PLANTS Power broom including operator Paint spray machine with boiler including operator Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours

1 1

0.25 1.00

625.00 600.00

25 % 100 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 74

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-57 UNIT: Sq.m. DESCRIPTION:-

Providing and applying chlorinated rubber traffic marking paint (DFT 100microns) including cleaning of dust & dirt by mechanical means and all neceesary arrangement for diversion of traffic complete in all respect as directed by the Engineer. Detail Unit No. Quantity Rate 100 Sft.

Detail for

A. MATERIAL Chlorinated rubber paint coverage Thinner Wastage Cartage B.LABOUR Skilled worker Unskilled worker

Litres 2.5 Sq.m./litre 10 % 5 % Total of "A" Hours Hours Total of "B" 1 1 Litres

3.72 0.37

425.00 215.00

2.00 2.00

93.75 56.25

C. TOOLS & PLANTS Power broom including operator Paint spray machine including operator Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours Hours

1 1

1.00 1.00

625.00 600.00

25 % 100 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 75

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-58 UNIT: Running meter DESCRIPTION:Fixing Precast Kerb Block aleady stock at site including the cost of excavation, form Work for haunching, 450 PSI lean concrete, 2250 PSI concrete for haunching, 1:4 cement sand mortar etc Complete in all respect. Detail for Detail 100 Rft. or 30 Metres Unit No. Quantity Rate

A. MATERIAL Cement mortar (1:4) 3 Cft. Cement Bags Sand Cft. 1450 PSI concrete (lean) 49.50 Cft. (ratio 1:3:6) Cement Bags Sand Cft. Crushed stone Cft. 2250 PSI concrete for haunching 10.90 Cft. (ratio 1:2:4) Cement Bags Sand Cft. Crushed stone Cft. Wastage 5 % Water charges 2 % Total of "A" B.LABOUR Skilled worker Hours 2 Unskilled worker Hours 2 Coolies for excavation Hours 1 Total of "B" C. FORMWORKS Providing, fixing & removing formwork Sft. 1 Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Rft. Rate for one Rft. Rate for one RM.

0.71 3.53 5.82 21.83 43.66 1.83 4.58 9.16

395.00 22.00 395.00 22.00 27.97 395.00 22.00 27.97

8.00 8.00 8.00

93.75 56.25 56.25

50.00

39.31

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 76

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-59 UNIT: Sq.m. DESCRIPTION:-

Fixing paving blocks already stock at site including filling the joints with approved sand and laid in approved pattern and design including 50mm thick sand cushion/ bedding complete in all respect.

Detail Detail for 100 Sft.

Unit

No.

Quantity

Rate

A. MATERIAL Sand cushion 50mm (2") thick Wastage B.LABOUR Skilled worker Unskilled worker

Cft. 5 % Total of "A" Hours Hours Total of "B" 1 2

16.00

22.00

4.00 4.00

93.75 56.25

C. TOOLS AND PLANTS Plate Compactor Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

Hours

1.00

212.00

25 % 100 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 77

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-60 UNIT: Running meter DESCRIPTION:Removing of existing Precast Kerb Block any pattern, any thickness including stacking at suitable places all leads and lifts Complete in all respect as directed by the Engineer. Detail 100 Rft. or 30 Metres Unit No. Quantity Rate

Detail for A. LABOUR Unskilled worker

Hours Total of "A"

8.00

56.25

B. TOOLS AND PLANTS Misc. Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Rft. Rate for one RM.

LS

25 % 100 Rft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 78

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-61 UNIT: Sq.m. DESCRIPTION:-

Removing paving blocks including stacking at suitable place all lead and lifts complete in all respect as directed by the Engineer.. Detail Unit No. Quantity Rate

Detail for A. LABOUR Unskilled worker

100 Sft.

Hours Total of "A"

8.00

56.25

B. TOOLS AND PLANTS Misc. Total of "B" Basic Cost "A+B" Add Contractor's overhead & Profit Total Cost for Rate for one Sq.ft. Rate for one Sq.m.

LS

25 % 100 Sft.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 79

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-62 UNIT: Cu.m. DESCRIPTION:-

Providing & laying random rubble stone masonry dry, roughly hammer dressed stone, well bonded, faced with hammer dresssed selected stone, Complete in all respect. 100 Cft Detail or Unit 2.83 Cu.m. Cft. 5 % Total of "A" 100.00 20.00 No. Quantity Rate

Detail for A. MATERIAL Random stone Wastage B.LABOUR Skilled worker Unskilled worker

Hours Hours Total of "B"

2 2

8.00 8.00

93.75 56.25

C. TOOLS AND PLANTS Misc. Total of "C"

LS

Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 80

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-63 UNIT: Cu.m. DESCRIPTION:-

Providing & laying random rubble stone masonry dry, roughly hammer dressed stone, well bonded, faced with hammer dresssed selected stone, laind and jointed in 1:4 cement sand mortar Complete in all respect. Unit Cu.m. Cft. Bags Cft. 100.00 2.35 11.76 20.00 395.00 22.00 No. Quantity Rate

Detail Detail for 100 Cft or 2.83 A. MATERIAL Random stone Laid in 1:4 cement mortar 10 Cft. Cement Sand Wastage 5 % Water charges 2 %

Total of "A" B.LABOUR Skilled worker Unskilled worker Total of "B" C. TOOLS AND PLANTS Misc. Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft Rate for one Cu.ft. Rate for one Cu.m. Hours Hours 3 3 8.00 8.00 93.75 56.25

LS

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 81

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-64 UNIT: Cu.m. DESCRIPTION:-

Providing & laying stone masonry squared rubble, dressed, uncoursed dry, well bonded, faced with hammer dresssed selected stone, Complete in all respect. Detail 100 Cft or Unit 2.83 Cu.m. Cft. 5 % Total of "A" 100.00 60.00 No. Quantity Rate

Detail for A. MATERIAL Dressed stone Wastage B.LABOUR Skilled worker Unskilled worker

Hours Hours Total of "B"

2 2

8.00 8.00

93.75 56.25

C. TOOLS AND PLANTS Misc. Total of "C"

LS

Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 82

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-65 UNIT: Cu.m. DESCRIPTION:-

Providing & laying stone masonry squared rubble, dressed, uncoursed, well bonded, faced with hammer dresssed selected stone, laid and joint in 1:4 cenment sand mortarComplete in all respect. Unit Cu.m. Cft. Bags Cft. 100.00 2.35 11.76 60.00 395.00 22.00 No. Quantity Rate

Detail Detail for 100 Cft or 2.83 A. MATERIAL Dressed stone Laid in 1:4 cement mortar 10 Cft. Cement Sand Wastage 5 % Water charges 2 %

Total of "A" B.LABOUR Skilled worker Unskilled worker Total of "B" C. TOOLS AND PLANTS Misc. Total of "C" Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft Rate for one Cu.ft. Rate for one Cu.m. Hours Hours 2 2 8.00 8.00 93.75 56.25

LS

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 83

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-66 UNIT: Sq.m. DESCRIPTION:-

Providing & laying roll pointing.Complete in all respect. Detail or Unit 9.29 Sq.m. No. Quantity Rate

Detail for A. MATERIAL 1:4 cement mortar Cement Sand Wastage Water charges

100 Sft.

5 Cft. Bags Cft. 5 % 2 % Total of "A" 1.18 5.88 395.00 22.00

B.LABOUR Skilled worker Unskilled worker Total of "B" C. TOOLS AND PLANTS Misc. Total of "C"

Hours Hours

1 1

8.00 8.00

93.75 56.25

LS

Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Sft. Rate for one Sq.ft. Rate for one Sq.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 84

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-67 UNIT: Cu.m. DESCRIPTION:-

Providing & laying stone masonry squared rubble, dressed, coursed, well bonded, faced with hammer dresssed selected stone, laid and joint in 1:4 cenment sand mortarComplete in all respect. Detail 100 Cft or Unit 2.83 Cu.m. Cft. 10 Cft. Bags Cft. 5 % 2 % Total of "A" 2.35 11.76 395.00 22.00 100.00 60.00 No. Quantity Rate

Detail for A. MATERIAL Dressed stone Laid in 1:4 cement mortar Cement Sand Wastage Water charges

B.LABOUR Skilled worker Unskilled worker Total of "B" C. TOOLS AND PLANTS Misc. Total of "C"

Hours Hours

2 2

10.00 10.00

93.75 56.25

LS

Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 85

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-68 UNIT: Cu.m. DESCRIPTION:-

Providing & laying Rip Rap Class "A" Comprising natural stone weighing 15 Kg. to 25Kg. complete in all respect. Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for A. MATERIAL Stone Wastage

100 Cft

or

Cft. 5 % Total of "A"

100.00

22.00

B.LABOUR Skilled worker Unskilled worker Total of "B" C. TOOLS AND PLANTS Misc. Total of "C"

Hours Hours

1 1

8.00 8.00

93.75 56.25

LS

Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 86

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO. R-69 UNIT: Cu.m. DESCRIPTION:-

Providing & laying Rip Rap Class "B" Comprising natural stone weighing 30 Kg. to 70Kg. complete in all respect. Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for A. MATERIAL Stone Wastage

100 Cft

or

Cft. 5 % Total of "A"

100.00

25.00

B.LABOUR Skilled worker Unskilled worker Total of "B" C. TOOLS AND PLANTS Misc. Total of "C"

Hours Hours

1 2

8.00 8.00

93.75 56.25

LS

Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 87

Karachi Metropolitan Corporation


RATE ANALYSIS ITEM NO9 R-70 UNIT: Cu.m. DESCRIPTION:-

Providing & laying Rip Rap Class "C" Comprising natural stone weighing 60 Kg. to 100Kg. complete in all respect. Detail Unit 2.83 Cu.m. No. Quantity Rate

Detail for A. MATERIAL Stone Wastage

100 Cft

or

Cft. 5 % Total of "A"

100.00

30.00

B.LABOUR Skilled worker Unskilled worker Total of "B" C. TOOLS AND PLANTS Misc. Total of "C"

Hours Hours

1 2

8.00 8.00

93.75 56.25

LS

Basic Cost "A+B+C" Add Contractor's overhead & Profit 25 % Total Cost for 100 Cft Rate for one Cu.ft. Rate for one Cu.m.

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 88

Karachi Metropolitan Corporation


RATE ANALYSIS

earing and grubbing the site by cutting, uprooting and removing all rubbish and shrubs including sposal to (outside Muncipal limits) designated places.

Amount

750.00 3600.00 4350.00

8480.00 4000.00 2626.00 15106.00

19456.00 4864.00 24320.00 1.00 10.81

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 89

Karachi Metropolitan Corporation


RATE ANALYSIS

emoval trees 150mm to 300mm girth including disposal to (outside Muncipal limits) designated aces.

Amount

375.00 900.00 1275.00

530.00 50.00 580.00 1855.00 463.75 2318.75 231.88

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 90

Karachi Metropolitan Corporation


RATE ANALYSIS

emoval trees 301mm to 600mm girth including disposal to (outside Muncipal limits) designated aces.

Amount

750.00 1800.00 2550.00

2120.00 150.00 2270.00 4820.00 1205.00 6025.00 602.50

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 91

Karachi Metropolitan Corporation


RATE ANALYSIS

emoval trees 601mm or over girth including disposal to (outside Muncipal limits) designated places.

Amount

750.00 1800.00 2550.00

16960.00 500.00 17460.00 20010.00 5002.50 25012.50 2501.25

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 92

Karachi Metropolitan Corporation


RATE ANALYSIS

smantling of existing plain cement concrete including disposal of dismantled materials to designated aces. Amount

3000.00 1800.00 4800.00

1786.10 16000.00 10504.00 28290.10 33090.10 8272.53 41362.63 413.63

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 93

Karachi Metropolitan Corporation


RATE ANALYSIS

smantling of existing reinforced cement concrete including separation of steel reinforcement, eaning, straightening of steel and disposal of dismantled materials to designated places. Amount

6000.00 3600.00 9600.00

61600.00 3292.25 33600.00 16000.00 10504.00 124996.25 134596.25 33649.06 168245.31 1682.45

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 94

Karachi Metropolitan Corporation


RATE ANALYSIS

smantling of existing asphalt concrete road including base, subbase and disposal of dismantled aterials to designated places. Amount

450.00 750.00 450.00

8000.00 10504.00 18504.00 18954.00 4738.50 23692.50 6.71 236.93

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 95

Karachi Metropolitan Corporation


RATE ANALYSIS

arifying/Tucking the existing asphalt concrete surface by pick axe with 10 tucks per square meter of t more than 20mm depth including removing the debris, cleaning and disposal of materials to signated places as directed by the Engineer. Amount

900.00 900.00

62.50 62.50 962.50 240.63 1203.13 1.12 12.03

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 96

Karachi Metropolitan Corporation


RATE ANALYSIS

aking diagonal grooves on existing asphalt surfaces as per Vol-II & III of special specification. Amount

450.00 450.00

1800.00 156.25 1956.25 2406.25 601.56 3007.81 2.80 30.08

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 97

Karachi Metropolitan Corporation


RATE ANALYSIS

cavation in for road works in hard rock upto required depth and gradient including disposal of rplus / rejected excavated to designated places (outside Municipal limits). Amount

1500.00 900.00 2400.00

30800.00 8000.00 10504.00 49304.00

51704.00 12926.00 64630.00 18.30 646.30

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 98

Karachi Metropolitan Corporation


RATE ANALYSIS

cavation for road work in medium rock upto required depth and gradient including disposal of surplus ejected excavated to designated places. (Outside Municipal limits) Amount

1500.00 900.00 2400.00

15400.00 8000.00 10504.00 33904.00

36304.00 9076.00 45380.00 12.85 453.80

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 99

Karachi Metropolitan Corporation


RATE ANALYSIS

cavation for road work in soft rock upto required depth and gradient including disposal of surplus / ected excavated to designated places (outside Municipal limits). Amount

1500.00 900.00 2400.00

7700.00 8000.00 10504.00 26204.00

28604.00 7151.00 35755.00 10.12 357.55

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 100

Karachi Metropolitan Corporation


RATE ANALYSIS

cavation for road work in normal soil upto required depth and gradient including disposal of surplus / ected excavated to designated places. (Outside Municipal limits) Amount

750.00 450.00 1200.00

79.50 8000.00 10504.00 18583.50

19783.50 4945.88 24729.38 7.00 247.29

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 101

Karachi Metropolitan Corporation


RATE ANALYSIS

cavation for road work in wet or silty soil required depth and gradient including disposal of surplus / ected excavated to designated places. (Outside Municipal limits) Amount

750.00 1800.00 2550.00

2120.00 8000.00 10504.00 20624.00

23174.00 5793.50 28967.50 8.20 289.68

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 102

Karachi Metropolitan Corporation


RATE ANALYSIS

eparation of sub-grade including cutting or filling to an average depth of 9", dressing to camber and nsolidation with power roller for compaction 95% modified AASHTO density and achieving the design vel. Amount

750.00 450.00 1200.00

16000.00 24000.00 3472.00 43472.00

44672.00 11168.00 55840.00 1.48 52.37

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 103

Karachi Metropolitan Corporation


RATE ANALYSIS

essing and levelling of roadway excavated material to designated section including compaction by eep foot roller and power roller with optimum moisture content or 90% modified AASHTO density in yers not more than 6 inches (150mm). Amount

750.00 1800.00 2550.00

16000.00 61600.00 24000.00 24000.00 3472.00 129072.00

131622.00 32905.50 164527.50 4.44 156.69

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 104

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding, laying and compacting 300mm thick improved sub-grade fill with material having CBR value 15% at 95% modified AASHTO density. Amount

35321.00 8830.25 44151.25 1500.00 900.00 2400.00

1060.00 6000.00 434.00 7494.00

54045.25 13511.31 67556.56 19.13 675.57

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 105

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying Granular Sub-Base course as per (AASHTO) standard specification including mpacting to the required density by approved mechanical means (vibratory roller road packer and mooth wheel roller etc) i/c watering with all lead and lift etc complete paid as per VOL-II & III of ecification. Amount

56501.60 14125.40 1693.60 72320.60 1500.00 900.00 2400.00

2120.00 2000.00 9000.00 868.00 13988.00 88708.60 22177.15 110885.74 31.39 1108.86

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 106

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying Aggregate base course CBR 80% as per (AASHTO) standard specification cluding compacting to the required density by approved mechanical means (vibratory roller road cker and smooth wheel roller etc) i/c watering with all lead and lift etc complete paid as per VOL-II & of specifications. Amount

59281.68 28256.80 21884.62 1693.60 111116.69 1500.00 900.00 2400.00 4000.00 2626.00 4000.00 6000.00 868.00 17494.00 131010.69 32752.67 163763.37 46.36 1637.63

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 107

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying 4" thick compacted stone metal using 1-1/2" to 3/4" broken stone ballast approved ade and quality including watering, leveling and compacting to required density etc.

Amount

7101.60 3572.32 250.00 10923.92 750.00 1800.00 2550.00 1060.00 12000.00 434.00 13494.00 26967.92 6741.98 33709.90 31.33 337.10

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 108

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying stone soling 9" thick. including watering, leveling and compacting to required density c. Amount

6357.78 635.78 250.00 7243.56 750.00 1800.00 2550.00 848.00 434.00 1282.00 11075.56 2768.89 13844.45 39.20 421.75

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 109

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying stone soling 12" thick. including watering, leveling and compacting to required nsity etc. Amount

6357.78 635.78 250.00 7243.56 1500.00 1800.00 3300.00 848.00 434.00 1282.00 11825.56 2956.39 14781.95 41.85 450.31

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 110

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and spraying prime coat MC-70 cold applied Bitushield-M as per VOL-II & III of special ecification paid according to drums @ site or Bill of Lading Sprayed with Distributor Truck. 30% Rate l be reduce if Sprayed with Hand Operated Boiler Amount

10137.53 506.88 10644.41 93.75 112.50 206.25

650.00 93.75 93.75 837.50 11688.16 2922.04 14610.20 13.58 146.10

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 111

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and spraying tack coat MC-70 cold applied Bitushield-R as per VOL-II & III of special ecification paid according to drums @ site or Bill of Lading. 30% Rate will be reduce if Sprayed with and Operated Boiler Amount

1339.49 133.95 1473.44 93.75 337.50 431.25

650.00 625.00 1275.00 3179.69 794.92 3974.61 3.69 39.75

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 112

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying asphalt concrete binder course compacted thickness 5 Cms (50mm thick) as r approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of ade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. e procedure of laying binder course material & methodology shall fully comply with AASHTO and as ected by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be read using paver machine. paid as per VOL-II & III pf specifications.

Amount

30625.00 2614.90 3918.86 244.94 1870.19 39273.89 375.00 900.00 1275.00 1280.00 2100.80 2000.00 1500.00 1500.00 434.00 8814.80 49363.69 12340.92 61704.62 57.35 617.05

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 113

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying asphalt concrete binder course compacted thickness 6 Cms (60mm thick) as r approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of ade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. e procedure of laying binder course material & methodology shall fully comply with AASHTO and as ected by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be read using paver machine. paid as per VOL-II & III of special specification.

Amount

36750.00 3137.88 4702.63 293.93 2244.22 47128.67 375.00 900.00 1275.00 1280.00 2100.80 2000.00 1500.00 1500.00 434.00 8814.80 57218.47 14304.62 71523.09 66.47 715.23

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 114

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying asphalt concrete binder course compacted thickness 7.5 Cms (75mm thick) as r approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of ade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. e procedure of laying binder course material & methodology shall fully comply with AASHTO and as ected by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be read using paver machine. paid as per VOL-II & III of special specification.

Amount

45937.50 3922.36 5878.29 367.42 2805.28 58910.84 375.00 900.00 1275.00 1280.00 2100.80 2000.00 1500.00 1500.00 434.00 8814.80 69000.64 17250.16 86250.80 80.16 862.51

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 115

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying asphalt concrete binder course compacted thickness 10 Cms (100mm thick) as r approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of ade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. e procedure of laying binder course material & methodology shall fully comply with AASHTO and as ected by the Engineer Incharge. Minimum bitumen content should be 3.5% binder course shall be read using paver machine. paid as per VOL-II & III of special specification.

Amount

61250.00 5229.81 7837.72 489.89 3740.37 78547.79 375.00 900.00 1275.00 1600.00 2626.00 2500.00 2250.00 2250.00 434.00 11660.00 91482.79 22870.70 114353.49 106.28 1143.53
Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 116

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying asphalt concrete wearing course compacted thickness 5 Cms (50mm thick) as r approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of ade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. e procedure of laying binder course material & methodology shall fully comply with AASHTO and as ected by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be read using paver machine. paid as per VOL-II & III pf specifications.

Amount

26250.00 3112.98 3404.26 244.94 1650.61 34662.80 375.00 900.00 1275.00 1280.00 2100.80 2000.00 1500.00 1500.00 434.00 8814.80 44752.60 11188.15 55940.75 51.99 559.41

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 117

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying asphalt concrete wearing course compacted thickness 4 Cms (40mm thick) as r approved job mix formula using crush aggregate from hub sources or equivalent. Using asphalt of ade 60/70 during laying temperature not less than 140C compacted by steel wheel & PTR roller. e procedure of laying binder course material & methodology shall fully comply with AASHTO and as ected by the Engineer Incharge. Minimum bitumen content should be 3.5% wearing course shall be read using paver machine. paid as per VOL-II & III pf specifications.

Amount

21000.00 2490.38 2723.41 195.96 1320.49 27730.24 375.00 900.00 1275.00 1280.00 2100.80 2000.00 1500.00 1500.00 434.00 8814.80 37820.04 9455.01 47275.05 43.94 472.75

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 118

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying lean concrete having 1450 PSI cylindrical strength (ready mixed concrete) cluding placing compacting, finishing, curing complete , screening and washing of crushed stone gregate excluding the cost of shuttering. Amount

13589.65 679.48 135.90 14405.03

56.25 93.75 150.00

1132.47 1132.47

0.00 15687.50 3921.87 19609.37 196.09 6926.03

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 119

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying reinforced cement concrete 2250 PSI cylindrical strength (ready mixed concrete) cluding all kinds of formwork, lifting, hoisting, placing, curing, compacting and finishing complete in all spect as shown on the drawings and as directed by the Engineer. (excluding the cost of steel nforcement). Amount

15005.24 750.26 150.05 15905.55

56.25 93.75 150.00

1132.47 160.00 1292.47

5896.50 5896.50 23244.52 5811.13 29055.65 290.56 10262.46

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 120

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying reinforced cement concrete having 2450 PSI cylindrical strength (ready mixed ncrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing mplete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost steel reinforcement). Amount

15429.91 771.50 154.30 16355.71

56.25 93.75 150.00

1132.47 160.00 1292.47

5896.50 5896.50 23694.68 5923.67 29618.35 296.18 10461.20

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 121

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying reinforced cement concrete having 3000 PSI cylindrical strength (ready mixed ncrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing mplete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost steel reinforcement). Amount

16421.29 821.06 164.21 17406.57

56.25 93.75 150.00

1132.47 160.00 1292.47

5896.50 5896.50 24745.54 6186.38 30931.92 309.32 10925.16

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 122

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying reinforced cement concrete having 4000 PSI cylindrical strength (ready mixed ncrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing mplete in all respect as shown on the drawings and as directed by the Engineer. (Excluding the cost steel reinforcement). Amount

17836.92 891.85 178.37 18907.13

56.25 93.75 150.00

1132.47 160.00 1292.47

5896.50 5896.50 26246.11 6561.53 32807.63 328.08 11587.66

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 123

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying plain cement concrete 2250 PSI cylindrical strength (ready mixed concrete) cluding all kinds of formwork, lifting, hoisting, placing, curing, compacting and finishing complete in all spect as shown on the drawings and as directed by the Engineer. Amount

15005.24 750.26 150.05 15905.55

56.25 93.75 150.00

1132.47 1132.47

5896.50 5896.50 23084.52 5771.13 28855.65 288.56 10191.82

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 124

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying plain cement concrete having 2450 PSI cylindrical strength (ready mixed ncrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing mplete in all respect as shown on the drawings and as directed by the Engineer.

Amount

15429.91 771.50 154.30 16355.71

56.25 93.75 150.00

1132.47 1132.47

5896.50 5896.50 23534.68 5883.67 29418.35 294.18 10390.56

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 125

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying plain cement concrete having 3000 PSI cylindrical strength (ready mixed ncrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing mplete in all respect as shown on the drawings and as directed by the Engineer. Amount

16421.29 821.06 164.21 17406.57

56.25 93.75 150.00

1132.47 1132.47

5896.50 5896.50 24585.54 6146.38 30731.92 307.32 10854.52

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 126

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying plain cement concrete having 4000 PSI cylindrical strength (ready mixed ncrete) including all kinds of formwork, lifting, hoisting, placing, placing compacting, finishing, curing mplete in all respect as shown on the drawings and as directed by the Engineer. Amount

17836.92 891.85 178.37 18907.13

56.25 93.75 150.00

1132.47 1132.47

5896.50 5896.50 26086.11 6521.53 32607.63 326.08 11517.02

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 127

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding, cutting, bending and binding high tensile deformed billet steel round bars (60,000 psi) nforming to ASTM 615 including the cost of binding wire, wastages, chairs, spacers block, hoisting d placing in position and such over laps as are not shown over the drawing, etc; at any level and any ight complete in all respect as per drawings and instructions/ approval of the Engineer. Amount

73500.00 1150.00 3732.50 500.00 500.00 79382.50

3000.00 3600.00 6600.00

75.00 55.00 130.00 86112.50 21528.13 107640.63 107,640.63

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 128

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding, cutting, bending and binding high tensile tor steel bars (60,000 psi) conforming to ASTM 5 including the cost of binding wire, wastages, chairs, spacers block, hoisting and placing in position d such over laps as are not shown over the drawing, etc; at any level and any height complete in all spect as per drawings and instructions/ approval of the Engineer.As per general specification Vol-II d special specification Vol-III. Amount

62000.00 1150.00 3157.50 500.00 500.00 67307.50

3000.00 3600.00 6600.00

75.00 55.00 130.00 74037.50 18509.38 92546.88 92,546.88

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 129

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying fairfaced reinforced cement concrete new jersey barrier having 3000 PSI mpressive cylindrical strength Concrete (Ready mixed concrete) (area 3.50 Sft) as per drawing cluding the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength c. complete in all respect. (Excluding the cost steel reinforcement) Amount

1024.80 5126.63 307.57 6459.00 225.00 187.50 412.50 160.00 438.95 745.77 1344.72 3068.15 3068.15 11284.37 2821.09 14105.46 1410.55 4628.00

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 130

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying fairfaced reinforced cement concrete new jersey barrier having 3000 PSI mpressive cylindrical strength Concrete (Ready mixed concrete) (area 2.0 Sft) as per drawing cluding the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength c. complete in all respect. (Excluding the cost steel reinforcement) Amount

1024.80 5126.63 307.57 6459.00 225.00 187.50 412.50 160.00 438.95 745.77 1344.72 3068.15 3068.15 11284.37 2821.09 14105.46 1410.55 403.01 806.03 2644.57

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 131

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and laying fairfaced reinforced cement concrete new jersey barrier having 3000 PSI mpressive cylindrical strength Concrete (Ready mixed concrete) (area 1.50 Sft) as per drawing cluding the cost of excavation, formwork, lean concrete 1450 PSI compressive cylindrical strength c. complete in all respect. (Excluding the cost steel reinforcement) Amount

1024.80 5126.63 307.57 6459.00 225.00 187.50 412.50 160.00 438.95 745.77 1344.72 3068.15 3068.15 11284.37 2821.09 14105.46 1410.55 403.01 604.52 1983.43

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 132

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & fixing Precast Kerb Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean ncrete, 2250 PSI concrete for haunching, 1:4 cement sand mortar etc Complete in all respect. Amount

17500.00 1100.00 278.71 77.61 2299.37 480.21 1221.27 723.32 100.71 256.12 1201.87 480.75 25719.94 1500.00 900.00 450.00 2850.00 2000.00 2000.00 30569.94 7642.48 38212.42 382.12 1253.75

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 133

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & fixing Precast Kerb Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean ncrete, 2250 PSI concrete 6"x18" fill beweeen two kerbs, laid in 1:4 cement sand mortar etc omplete in all respect. Amount

17500.00 1100.00 278.71 77.61 2299.37 480.21 1221.27 4977.00 692.94 1762.29 1519.47 607.79 32516.66 1500.00 900.00 450.00 2850.00 35366.66 8841.67 44208.33 442.08 1450.48

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 134

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & fixing Precast Edge Block 3750 PSI Industrial Made Size 6 inches thick x 12 inches long x inches high including the cost of Cartage, excavation, form Work for haunching, 1450 PSI lean ncrete, 2250 PSI concrete for haunching, 1:4 cement sand mortar etc Complete in all respect. Amount

17000.00 1100.00 278.71 77.61 2299.37 480.21 1221.27 723.32 100.71 256.12 1176.87 470.75 25184.94 1500.00 900.00 450.00 2850.00 2000.00 2000.00 30034.94 7508.73 37543.67 375.44 1231.81

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 135

Karachi Metropolitan Corporation


RATE ANALYSIS

eflectorized pavement studs (raised profile type single) aluminium. Amount

38500.00 395.00 1.10 150.00 39046.10 750.00 1350.00 2100.00

3125.00 1625.00 4750.00 45896.10 11474.02 57370.12 573.70

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 136

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & Fixing traffic sign boards (regulatory sign 3 feet dia.) comprising 3" dia. G.I. pipe post, s. base plate, stiffeners, nuts, bolts, 16 guage G.I. sheet, lean concrete, 3000 PSI concrete in undations, excavation, enamel paint, retroreflective sheet diamond grade, lettering & signs complete all respect as shown on the drawings and as directed by the Engineer. Amount

9338.07 8846.72 552.00 7000.00 5087.00 255.93 1805.09 1594.80 21354.20 6406.26 750.00 1723.98 64714.05 750.00 1800.00 1274.30 1416.35 5240.65 720.00 720.00 70674.70 17668.67 88343.37 17668.67

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 137

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & Fixing traffic sign boards (warning sign 3'x3'x3' triangle) comprising 3" dia. G.I. pipe post, s.. base plate, stiffeners, nuts, bolts, 16 guage G.I. sheet, lean concrete, 3000 PSI concrete in undations, excavation, enamel paint, retroreflective sheet diamond grade, lettering & signs complete all respect as shown on the drawings and as directed by the Engineer. Amount

9338.07 8846.72 552.00 7000.00 3391.00 255.93 1805.09 1594.80 7119.70 2135.91 750.00 1639.18 44428.40 750.00 1800.00 850.30 472.23 3872.53 720.00 720.00 49020.92 12255.23 61276.16 12255.23

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 138

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and Fixing cement paving blocks flooring having size of 197x97 60(mm) of city / Quadra / bble shape with pigmented having strength between 5000 psi to 8500 psi including filling the joints h approved sand and laid in approved pattern and design including 50mm thick sand cushion/ dding complete in all respect. Amount

5669.14 1100.00 351.97 356.06 7477.17 375.00 450.00 825.00 212.00 212.00 8514.17 2128.54 10642.72 106.43 1145.16

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 139

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and Laying 2" Thick 3000 PSI (Ready Mixed) Cylindrical Strength cement concrete floor mooth finished including glass dividing strips laid in panels etc; complete in all respect. Amount

2627.41 50.00 133.87 55.23 2866.50 1500.00 900.00 225.00 2625.00 5491.50 1372.88 6864.38 68.64 738.61

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 140

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and Laying 3" Thick 3000 PSI (Ready Mixed) Cylindrical Strength cement concrete floor mooth finished including glass dividing strips laid in panels etc; complete in all respect. Amount

4105.32 50.00 207.77 86.26 4449.35 1500.00 900.00 225.00 2625.00 7074.35 1768.59 8842.94 88.43 951.50

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 141

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and Fixing Fair Face steel form work the form shall be made with 10 gauge steel plate and ed at site with the help of steel and clamps on such a way that form will hold and resist the vibrating d pouring force and when form is open the concrete. The concrete surfaces shall be smooth and free m honey combing that no plaster and repair is required and compacted the job as per instruction. Amount

21831.90 2183.19 24015.09 -6319.76 17695.33 442.38 442.38 1502.00 1502.00 1944.38

750.00 450.00 1200.00 3144.38 786.10 3930.48 39.30 422.92

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 142

Karachi Metropolitan Corporation


RATE ANALYSIS

iling/ Dewatering and pumping out water Dewatering from excavation. Amount

66000.00 13200.00 9600.00 2500.00 91300.00

33750.00 67500.00 3000.00 1800.00 106050.00

25,000.00 30,000.00 25,000.00 30,000.00 -27,500.00 27,500.00

110000.00
216,000.00

216000.00 523350.00 130837.50 654187.50 454.30

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 143

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and applying thermoplastic traffic marking paint (1.50mm thick) with drop of glass bead, eaning of dust & dirt by mechanical means and all neceesary arrangement for diversion of traffic mplete in all respect as directed by the Engineer. Amount

6133.83 200.98 316.74 50.00 6701.55 93.75 56.25 150.00 156.25 600.00 756.25 7607.80 1901.95 9509.74 95.10 1023.25

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 144

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding and applying chlorinated rubber traffic marking paint (DFT 100microns) including eaning of dust & dirt by mechanical means and all neceesary arrangement for diversion of traffic mplete in all respect as directed by the Engineer. Amount

1579.93 79.93 82.99 50.00 1792.84 187.50 112.50 300.00 625.00 600.00 1225.00 3317.84 829.46 4147.30 41.47 446.25

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 145

Karachi Metropolitan Corporation


RATE ANALYSIS

xing Precast Kerb Block aleady stock at site including the cost of excavation, form Work for unching, 450 PSI lean concrete, 2250 PSI concrete for haunching, 1:4 cement sand mortar etc omplete in all respect. Amount

278.71 77.61 2299.37 480.21 1221.27 723.32 100.71 256.12 271.87 108.75 5817.94 1500.00 900.00 450.00 2850.00 1965.50 1965.50 10633.44 2658.36 13291.79 132.92 436.10

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 146

Karachi Metropolitan Corporation


RATE ANALYSIS

xing paving blocks already stock at site including filling the joints with approved sand and laid in proved pattern and design including 50mm thick sand cushion/ bedding complete in all respect.

Amount

351.97 17.60 369.57 375.00 450.00 825.00 212.00 212.00 1406.57 351.64 1758.21 17.58 189.18

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 147

Karachi Metropolitan Corporation


RATE ANALYSIS

emoving of existing Precast Kerb Block any pattern, any thickness including stacking at suitable aces all leads and lifts Complete in all respect as directed by the Engineer. Amount

900.00 900.00 75.00 75.00 975.00 243.75 1218.75 12.19 39.99

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 148

Karachi Metropolitan Corporation


RATE ANALYSIS

emoving paving blocks including stacking at suitable place all lead and lifts complete in all respect directed by the Engineer.. Amount

1350.00 1350.00 250.00 250.00 1600.00 400.00 2000.00 20.00 215.20

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 149

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying random rubble stone masonry dry, roughly hammer dressed stone, well bonded, ced with hammer dresssed selected stone, Complete in all respect. Amount

2000.00 100.00 2100.00 1500.00 900.00 2400.00

258.00 258.00 4758.00 1189.50 5947.50 59.48 2100.72

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 150

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying random rubble stone masonry dry, roughly hammer dressed stone, well bonded, ced with hammer dresssed selected stone, laind and jointed in 1:4 cement sand mortar Complete in respect. Amount

2000.00 929.04 258.70 159.39 63.75 3410.88 2250.00 1350.00 3600.00

250.00 250.00 7260.88 1815.22 9076.10 90.76 3205.77

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 151

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying stone masonry squared rubble, dressed, uncoursed dry, well bonded, faced with mmer dresssed selected stone, Complete in all respect. Amount

6000.00 300.00 6300.00 1500.00 900.00 2400.00

150.00 150.00 8850.00 2212.50 11062.50 110.63 3907.39

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 152

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying stone masonry squared rubble, dressed, uncoursed, well bonded, faced with mmer dresssed selected stone, laid and joint in 1:4 cenment sand mortarComplete in all respect. Amount

6000.00 929.04 258.70 359.39 143.75 7690.88 1500.00 900.00 2400.00

150.00 150.00 10240.88 2560.22 12801.10 128.01 4521.48

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 153

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying roll pointing.Complete in all respect. Amount

464.52 129.35 29.69 11.88 635.44 750.00 450.00 1200.00

150.00 150.00 1985.44 496.36 2481.80 24.82 267.04

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 154

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying stone masonry squared rubble, dressed, coursed, well bonded, faced with hammer esssed selected stone, laid and joint in 1:4 cenment sand mortarComplete in all respect. Amount

6000.00 929.04 258.70 359.39 143.75 7690.88 1875.00 1125.00 3000.00

150.00 150.00 10840.88 2710.22 13551.10 135.51 4786.38

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 155

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying Rip Rap Class "A" Comprising natural stone weighing 15 Kg. to 25Kg. complete in respect. Amount

2200.00 110.00 2310.00 750.00 450.00 1200.00

50.00 50.00 3560.00 890.00 4450.00 44.50 1571.78

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 156

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying Rip Rap Class "B" Comprising natural stone weighing 30 Kg. to 70Kg. complete in respect. Amount

2500.00 125.00 2625.00 750.00 900.00 1650.00

50.00 50.00 4325.00 1081.25 5406.25 54.06 1909.54

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

ROAD WORKS
Sheet- 157

Karachi Metropolitan Corporation


RATE ANALYSIS

oviding & laying Rip Rap Class "C" Comprising natural stone weighing 60 Kg. to 100Kg. complete in respect. Amount

3000.00 150.00 3150.00 750.00 900.00 1650.00

100.00 100.00 4900.00 1225.00 6125.00 61.25 2163.41

Approved..........................
DIRECTOR GENERAL TECHNICAL SERVICES

Sheet- 158 Prep. by Dated:

Calculation sheet-Traffic sign


Description Quantity of five signs Excavation Foundation No. 5 Nos. 5 L B H/D Qty.

0.45

0.45 0.35 Total Qty. in Cu.m.. Total Qty. in Cft. 0.45 0.10 Total Qty. in Cu.m.. Total Qty. in Cft. 0.45 0.50 Total Qty. in Cu.m.. Total Qty. in Cft.

0.35 0.35 12.52 0.10 0.10 3.58 0.51 0.51 17.88

CC1:4:8 concrete Foundation

0.45

3000 PSI concrete Foundation

0.45

m.s. base plate 20mm (3/4") thick 5 Density taken Quantity converted in to kg. 7850 kg./Cu.m. 0.35 0.35 0.02 Total Qty. in Cu.m.. Total Qty. in Kg. 0.01 0.01 96.16

m.s. stiffner plate 8mm thick 4 Density taken Quantity converted in to kg. 7850 kg./Cu.m. 5 0.20 0.03 0.01 Total Qty. in Cu.m.. Total Qty. in Kg. 0.0008 0.00080 6.28

G.I Sheet sign board 900mm dia. 16 guage (1.6mm) 5 Density taken Quantity converted in to kg. 7850 kg./Cu.m. 0.90 0.90 0.0016 Total Qty. in Cu.m.. Total Qty. in Kg. 0.0065 0.0065 50.87

G.I Sheet sign board 3'x3'x3 triangle boarad 16 guage (1.6mm) 2 5 0.30 0.90 0.0016 Density taken 7850 kg./Cu.m. Total Qty. in Cu.m.. Quantity converted in to kg. Total Qty. in Kg. G.I.pipe 75mm dia. 5 2.10 0.00 0.00 Total Qty. in R.M. Total Qty. in Rft.

0.0043 0.0043 33.91 10.50 10.50 34.45

Enamel paint to sign board backside to pipe

1 1

5 5

0.64 0.17

0.00 0.0000 0.00 2.1000 Total Qty. in Sq.m. Total Qty. in Sft.

3.1813 1.7960 4.9773 53.56

Retroreflective sheet diamond grade for regulatory sign 3 feet dia. to sign board front face 5 0.90 0.90 0.0000 Total Qty. in Sq.m. Total Qty. in Sft. Retroreflective sheet diamond grade for warning sign 3'x3'x3' to sign board front face 2 0.5 5 0.90

4.0500 4.0500 43.58

0.30 0.0000 Total Qty. in Sq.m. Total Qty. in Sft.

1.3500 1.3500 14.53

Sheet- 159 Prep. by Dated:

Calculation sheet-Traffic sign


Description No. L B H/D Qty.

MATERIAL REQUIREMENT AND THEIR UNIT COST ONE CUBIC FEETOF CONCRETE FOR KARACHI LIMITS Basic material prices November, 2011
Cement (OP) Sand Crushed stone Rs. 7,900.00 per tonne icnl.cartage Rs. Rs. 22.00 per Cft. 27.97 per Cft.

Type of concrete A B C D E

COST OF ONE CUBIC FEET/OF CEMENT CONCRETE Ratio CEMENT SAND CRUSHED STONE unit Qty. Total Rs. unit Qty. Total unit Qty. Total OPC Rs. Rs. 1:1:2 1:1-1/2:3 1:2:4 1:3:3 1:3:6 1:4:8 tonne tonne tonne tonne tonne tonne 0.0149769 0.0108717 0.0085502 0.0085502 0.0059738 0.0045865 118.32 85.89 67.55 67.55 47.19 36.23 Cft. Cft. Cft. Cft. Cft. Cft. 0.368 0.401 0.420 0.630 0.441 0.452 8.08 Cft. 8.82 Cft. 9.24 Cft. 13.86 Cft. 9.70 Cft. 9.95 Cft. 0.735 0.802 0.840 0.630 0.882 0.905 20.56 22.43 23.50 17.62 24.67 25.30

AL REQUIREMENT AND THEIR UNIT COST IC FEETOF CONCRETE FOR KARACHI LIMITS c material prices November, 2011

Cost of one Cft.


Total Cost in Cft. with OPC 146.96 117.13 100.28 99.03 81.57 71.49