Planeacin de los requerimientos de materiales (MRP)

Gestin de Sistemas de Produccin

Del Plan Agregado al Plan Maestro


Plan Agregado de Produccin
No
Podemos producir 10.000 unidades equivalentes (total de los productos A, B y C) por mes para el ao que viene?

Capacidad?

Si Plan Maestro de Produccin No Es Viable? Si Plan de Requerimiento de Materiales


2-508-97 Production and Operations Management

Podemos producir 500 unidades de A, 600 B y 400 de la C a la semana durante el prximo mes?

Plan de Produccin VS Plan Maestro de Produccin


Plan Agregado MPS
Mediano Plazo Produccin de las Ordenes

Objetivo

Largo Plazo Decisiones de Capacidad Familia de productos


(Unidades Equivalentes)

Producto

SKU level
(stock keeping unit)

Horizonte

12 a 15 meses

Alrededor 3 meses

Revisin

1 Mes

1 Semana

2-508-97 Production and Operations Management

El Plan agregado y el Plan Maestro de produccin

2-508-97 Production and Operations Management

When to Order ?
Three approaches
Reorder
REACTIVE SYSTEMS

Point (continuous review system)

Constant amount ordered when inventory declines to predetermined level

Periodic Review System


(fixed time review period)
Order placed for variable amount after fixed passage of time

PROACTIVE SYSTEMS

Time Phased Order Point


Master Production Schedule Material Requirements Planning

Distribution Requirements Planning


5

2-508-97 Production and Operations Management

Objectives of the Master Production Schedule


Sales

Establish and meet delivery dates Determine launch dates for orders Optimize the use of available capacity

Purch.

Operations

Operations

Meet the objectives of the aggregate plan


Make trade-off decisions between production and marketing
6

Systemic Approach

2-508-97 Production and Operations Management

Master Production Plan : Inputs


Inputs to the MPS are : Beginning Inventory

Forecasts for each week of the schedule


Customer orders (quantities already committed to customers) Total available capacity for each week of the schedule

2-508-97 Production and Operations Management

Developing a MPS
Identification of individual products. Development of an MPS grid for each product in real units according to the available data (forecast, committed orders, inventory levels, lot sizes, lead times) and the specified constraints.

Rough cut capacity planning in equivalent units (for all products).


Does the plans meet all constraints? (capacity limits, stock levels, etc.)

2-508-97 Production and Operations Management

Developing a MPS
Periods

Forecast Customer Orders Proj. on-hand Inv. MPS - Order Receipt MPS - Order Release

1 75 80 200 120

2 3 85 80 60 55 35 55 100 100

Lot size 100 units Lead time: 1 period

Forecast of the demand for the products with independent demand Firm orders received from the customers for period i. Projected on-hand Inventory (i) = Projected on-hand inv. (i - 1) + Planned production (i) - Max (Forecast (i) , Customer orders (i) )

2-508-97 Production and Operations Management

Developing a MPS
1) 2) Forecast for products with an independant demand Committed customer orders
Product X12DE Lot Size 200 Lead Time 1 Beginning Inventory 410

2a) Identify the Max between forecast and customer orders 3) Planned order receipts for each period:

Period Forecast Customer Orders

1 250 230 160 0 200

2 250 280 80 200 200

3 250 180 30 200 400

4 250 150 180 400

Projected inventory
Planned receipts Planned releases

4) Projected on-hand inventory (i) = beginning inventory (i - 1) + planned order receipts (i) - Max (forecast (i) , customer orders (i) )
2-508-97 Production and Operations Management

5) Planned order releases shifted back the length of the lead time
10

Preliminary Plan : Complete the following MPS


Product A
Periods

Forecast Customer Orders Projected on-hand inv. 100 Planned Order Receipts Planned Order Releases

1 50 25

2 45 60

3 45 15

4 50 55

5 50 25

6 50 35

7 40

8 40

9 40

10 50

Product A Beginning Inventory = 100 Lot Size: 100 units Lead Time: 1 week 1 equivalent unit

2-508-97 Production and Operations Management

11

Preliminary Plan : Complete the following MPS


Product B
Periods

Forecast Customer Orders Proj. on-hand inv. 300 Planned Order Receipts Planned Order Releases

1 60 35

2 120 150

3 80 60

4 40 30

5 30 25

6 50 35

7 20

8 20

9 20

10 30

Product B Beginning Inv. = 300 Lot Size : 100 units Lead Time: 1 week 2 equivalent units

2-508-97 Production and Operations Management

12

Rough Cut Capacity Planning


Approximate calculation of the capacity required at critical work centers to meet the demand in order to check the feasibility of a Master Production Schedule. When the capacity required exceeds the capacity available the MPS must be adjusted before proceeding to the MRP.

2-508-97 Production and Operations Management

13

Final MPS : Rough Cut Capacity Planning


Products A and B
100 Prod B - Planned Order Releases 0 Total 100
Prod A - Planned Order Releases

0 0 0

100 200 300

0 0 0

100 200 300

0 0 0

0 0 0

100 0 100

0 0 0

0 0 0

Total capacity is 200 equivalent units per period. Establish the final MPS for each product. Because the total planned order releases of products A and B
is superior to 200 units in periods 3 and 5, we must move the release of one of the two articles to periods 2 and 4.

We decide, for example, to move the release of product A to periods 2 and 4. We must then complete the final plan for both products.
14

2-508-97 Production and Operations Management

Final MPS : Modifications to the Preliminary Plan


Product A
Periods

Forecast Customer Orders Proj. on-hand inv. 100 Planned Order Receipts Planned Order Releases

1 2 3 4 5 6 50 45 45 50 50 50 25 60 15 55 25 35 50 90 145 90 140 90 100 0 0 100 100 0 100 0 100 0 100 0

7 40
50 0 0

8 40

9 40

10 50
20 0 0

10 70 0 100 100 0

Planned Order Release is moved from period 3 to period 2. Consequently, Planned Order Receipts are moved from period 4 to period 3. Projected on-hand inventories must be recalculated to account for the changes.

2-508-97 Production and Operations Management

15

Final MPS : Modifications to the Preliminary Plan


Product B
Periods

Forecast Customer Orders Proj. on-hand inv. 300 Planned Order Receipts Planned Order Releases

1 2 3 4 60 120 80 40 35 150 60 30 240 90 10 70 0 0 0 100 0 0 100 0

5 30 25 40 0 0

6 7 50 20 35 90 70 0 100 100 0

8 20 50 0 0

9 20 30 0 0

10 30 0 0 0

Since weve made no changes to the planned order releases of prodcut B, le preliminary and final plans are identical.

2-508-97 Production and Operations Management

16

Reading
MPS: Pages 466-473
Not:

example 6 (pages 467-468)


Available to promise (page 472)

Stabilizing MPS (page 473)

2-508-97 Production and Operations Management

17

Demand Characteristics
Independent demand Dependent demand

100 x 1 = 100 tabletops

100 tables

100 x 4 = 400 table legs

Continuous demand
400 No. of tables 400 No. of tables 300 200 100

Discrete demand

300
200 100
1 2 3 Week 4 5

M T W Th F

M T W Th F

2-508-97 Production and Operations Management

18

Reorder Point System VS MRP


Demand for the tables Quantity

Time Inventory of tables On-hand inventory Time


2-508-97 Production and Operations Management

19

Reorder Point System VS MRP


Demand for the table legs
Quantity

Inventory of the table legs

Quantity

2-508-97 Production and Operations Management

20

Objectives of MRP
Calculate with precision the quantities of components, parts and raw material that must be produced or purchased in order to realize the MPS HOW MANY ? To determine when to release production or to place the orders in order to receive the required units at the right moment WHEN ?

2-508-97 Production and Operations Management

21

Material Requirements Planning : Information Structure


Aggregate Planning

Forecasts

MPS

Customer Orders

Item Master File

MRP
- Stocks on hand - Safety stocks - Lot sizes - Economic Order Quantities - Lead time

Bill of Material

2-508-97 Production and Operations Management

22

Bill of Materials (BOM)


Product Structure Tree
Level 0

X Y (3) Z (2) W (2) Y (1)

Parent Component Parent

Level 1

Level 2

Component

For each product X we need 3 Y and 2 Z For each product Z we need 2 W and 1 Y
2-508-97 Production and Operations Management

23

Problems
S&H (2007) p.515 #3 - S&H (2004) p.628 #3

Item

Lead Time

Amount on Hand

Direct Components

End
L C K B J G H
2-508-97 Production and Operations Management

1
2 3 3 2 3 3 2

0
10 15 20 30 30 5 0

L(2), C(1), K(3)


B(2), J(3) G(2), B(2) H(4), B(2)

24

MRP Matrix

Note: The book from Stevenson shows the projected inventory at the beginning of the period, this is not the usual way to do it, so we will always show the projected inventory at the END of the period
2-508-97 Production and Operations Management

25

MRP calculation process


Always process the items in the order of their low level code: level 0 level 1 level 2 When an item appears at different levels of the product structure(s), the lowest level (highest number) is the level that we must use. Gross requirements for an item are calculated by:

Multiplying the quantity of the planned order release(s) of the parent(s) of the item by the quantity required as per the BOM for the specific parent-component relationship(s).
2-508-97 Production and Operations Management

26

Lot Sizing in MRP Systems


Lot-for-lot (L4L) ordering policy Minimum order quantity (Ex: Min 250) Multiple order quantity (Ex: X100) Economic order quantity (Ex: 350; annual demand: 4 200) Periodic order quantity (Ex: 2 months)

2-508-97 Production and Operations Management

27

Example
A company is manufacturing several office supply items among which we have:
Clipboard Lapdesk etc.

2-508-97 Production and Operations Management

28

Product Structure

Clipboard

Top clip (1)

Bottom clip (1)

Pivot (1)

Spring (1)

Rivets (2) Finished clipboard Pressboard (1)

2-508-97 Production and Operations Management

29

Product Structure Tree

Clipboard

Level 0

Pressboard (1)

Clip Assy (1)

Rivets (2)

Level 1

Top Clip (1)

Bottom Clip (1)

Pivot (1)

Spring (1)

Level 2

2-508-97 Production and Operations Management

30

MRP: Example (cont.)


Product Structure Record

Clipboard

Level 0

Pressboard (1)

Clip Assy (1)

Rivets (2)

Level 1

Lapdesk

Level 0

Pressboard (2)

Trim (3)

Beanbag (1)

Glue (4 oz)

Level 1

2-508-97 Production and Operations Management

31

MRP: Example (cont.)


ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 LLC: 0 LT: 1 1 2 PERIOD 3 4 5

M.P.S.

Planned Order Releases


ITEM: LAPDESK LOT SIZE: MULT 50 1 50 1

100
2

100
PERIOD 3 50 PERIOD 3

100
4 5

Planned Order Releases ITEM: PRESSBOARD LLC: 1 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases

M.R.P.

2-508-97 Production and Operations Management

32

MRP: Example (cont.)


ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 1 2 100 PERIOD 3 100 PERIOD 3 50 4 100 5

M.P.S.

Planned Order Releases ITEM: LAPDESK LOT SIZE: MULT 50 LLC: 0 LT: 1

x1
1 50 2

x1
4

x1
5

Planned Order Releases ITEM: PRESSBOARD LLC: 1 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases

x2
1 100

x2

PERIOD 2 3 4 100 200 100

5 0

M.R.P.

2-508-97 Production and Operations Management

33

MRP: Example (cont.)


ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 LLC: 0 LT: 1 1 2 100 1 50 1 100 50 2 PERIOD 3 100 PERIOD 3 50 PERIOD 2 3 4 100 200 100 50 50 100 150 0 150 150 100 0 100 100 5 0 0 4 100 4 5 5

M.P.S. M.R.P.

Planned Order Releases ITEM: LAPDESK LOT SIZE: MULT 50

Planned Order Releases ITEM: PRESSBOARD LLC: 1 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases

100

2-508-97 Production and Operations Management

34

MRP: Example (cont.)

Planned Order Report PERIOD ITEM Clipboard Lapdesk Pressboard 1 2 100 50 100 150 3 100 50 100 4 100 5

2-508-97 Production and Operations Management

35

Product A

Item Product A MPS Sales Forecast Customer Orders Projected inventory Order Receipts Order releases Item Product Z

Lot size 200

Sub.-Ass. B (2)

Component C (1)

135

LT 1 1 25 30 105

2 25 20 80

3 25 15 55

4 25 10 30

5 25 5 200

6 25 5 180 200

Lot size 500

Component C (3)

Component D (4)

MPS Sales Forecast Customer Orders Projected inventory Order Receipts Order releases

135

LT 2 1 30 35 100

2 30 20 70

3 30 15 40 500

4 30 20 10

5 30 10 480 500

6 30 5 450

Product Z

Item Sub-ass. B MRP Gross Requirements Gross Requirements Gross Req. Tot. Projected inventory Net Requirements Planned Order Receipts Planned Order Releases Item Component C MRP Gross Requirements Gross Requirements Gross Req. Tot. Projected inventory Net Requirements Planned Order Receipts Planned Order Releases Item Component D MRP Gross Requirements Gross Requirements Gross Req. Tot. Projected inventory Net Requirements Planned Order Receipts Planned Order Releases

Lot size 1 500


Prod. A Prod. Z

Sub.-Ass. B (3)

Component D (2)

200

LT 2 1 0 0 0 200

2 0 0 0 200

1 500 Lot size 4 500


Prod. A

3 0 1 500 1 500 200 1 300 1 500 1 500

4 0 0 0 200

5 400 0 400 1 300 200 1 500

6 0 0 0 1 300

Component C (3)

Component D (4)

Sub-ass. B 4 600

LT 1 1 0 4 500 4 500 100

2 0 0 0 100

3 0 4 500 4 500 100 4 400 4 500

4 0 0 0 100

5 200 0 200 4 400 100 4 500

6 0 0 0 4 400

4 500 Lot size 10 000


Prod. Z

4 500

Sub-ass. B 6500

LT 1 1 0 6 000 6 000 500

2 0 0 0 500

3 1 000 6 000 7 000 3 500 6 500 10 000

4 0 0 0 3 500

5 0 0 0 3 500

6 0 0 0 3 500

10 000

Month 0 1 2 3 4 5

Gross Requirements
Lot-for-lot (L4L) ordering policy Net Requirements Planned order receipts Projected on-hand inventory Fixed-size lot ordering policy (Ex: 500) Net Requirements Planned order receipts Projected on-hand inventory Minimum order quantity (Ex: Min 250) Net Requirements Planned order receipts Projected on-hand inventory Multiple order quantity (Ex: X100) Net Requirements Planned order receipts Projected on-hand inventory Economic order quantity (ex: 700; Ann. Dem: 4200) Net Requirements Planned order receipts Projected on-hand inventory Periodic order quantity (2 months) Net Requirements Planned order receipts Projected on-hand inventory

75
75 75 0

350
350 350 0

200
200 200 0

750
750 750 0

1000
1000 1000 0

75 500 425

75

125 500 375

375 500 125

875 1000 125

75 250 175

175 250 75

125 250 125

625 625 0

1000 1000 0

75 100 25

325 400 75

125 200 75

675 700 25

975 1000 25

75 700 625

275

75

675 700 25

975 1400 425

75 425 350

200 950 750

1000 1000 0

Establishing the Minimum Planning Horizon


A
Lead Time = 2 periods

B
Lead Time = 2 periods

C
Lead Time = 3 periods

4 periods

D(2)
Lead Time = 2 periods

E
Lead Time = 4 periods

7 periods 9 periods
2-508-97 Production and Operations Management

38

Establishing the Minimum Planning Horizon


LT = 2 periods

LT = 2 periods

LT = 4 periods

D(2)
LT = 3 periods

LT = 2 periods

Periods
A B C D E Assembly Purchase Assembly Purchase Purchase LT 2 2 3 2 4 2 3 4 5 6 7 100 100 8 100 9 100 10 100

100 200 100 100 200

2-508-97 Production and Operations Management

39

MPS / MRP PROCESS


Planned Order Receipt

MPS

Level 0
Planned Order Release Gross Requirements Net Requirements Planned Order Receipt Planned Order Release

Bill of materials

Materials Requirement Planning

Level 1

On-hand Inv. Lot Sizing

Lead time

Level 2

Gross Requirements Net Requirements Planned Order Receipt

Minimum Planning Horizon

Planned Order Release Supplier


2-508-97 Production and Operations Management

Ref.: adapted from D. A. Turbide, MRP+, Industrial Press, 1993.

40

Readings
Review problems:
To be announced

Review Reading for MRP:


S&H 2007, 484-497

Readings for next class (scheduling) :


S&H 2007, chap. 15 pp 547-560

2-508-97 Production and Operations Management

41